Tunisia-Italy Electricity Integration and Renewable Energy Ecosystem

Abstract*

The Elmed Interconnector is a planned 500 KV/600 MW sub-sea high-voltage direct-current (HVDC) cable with a length of 200 km at amax depth of 750m connecting the existing electrical substation in Partanna (Sicily) on the Italian side and a newly builtsubstation in Menzel Temime (Mlaaba, Cap Bon Peninsula) on the Tunisian side. Besides the undersea cable routes and the converterstations, the Italy-Tunisia interconnection comprises also the onshore...

* The project abstract is drawn from the PAD, SAR or PGD and may not accurately reflect the project's current nature

Show More

Development Objective

To increase Tunisia’s resilient transmission capacity for the trade of electricity with Europe for the benefit of Tunisian households and businesses

Key Details

Project Details

  • P179240

  • Active

  • Anas Benbarka , Lucine Lominy, Amira Klibi

  • STEG (Components 1, 2, 3.1, and 3.2),Republic of Tunisia (Subcomponent 3.3)

  • Tunisia

  • October 24, 2022

  • (as of board presentation)

    June 21, 2023

  • December 13, 2023

  • US$ 920.00 million

  • Ministry of Higher Education and Scientific Research (Subcomponent 3.3),STEG (Components 1, 2, 3.1, and 3.2)

  • Middle East and North Africa

  • 2023

  • US$ 293.40 million

  • N/A

  • April 1, 2024

  • December 28, 2028

  • Yes

  • BANK APPROVED

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
International Bank for Reconstruction and Development 268.40
Green Climate Fund 25.00

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment 268.40
IDA Commitment N/A
IBRD + IDA Commitment 268.40
Lending Instrument
Grant Amount 25.00
Total Project Cost** 920.00

Summary Status of World Bank Financing (US$ Millions) as of March 31, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of March 31, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)
Jun 21, 2023 IBRD-95370 Loan Commitment 268,400,000.00
Jul 16, 2024 IBRD-95370 Int Charges 605,076.40
Mar 13, 2024 IBRD-95370 Fee Charges 674,989.25
Mar 13, 2024 IBRD-95370 Loan Disb 674,989.25
Jul 16, 2024 IBRD-95370 Int Charges 11,845.77
Jun 21, 2023 TF-C3832 Loan Commitment 20,000,000.00

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Progress towards achievement of PDO Satisfactory 2024-12-20
Monitoring and Evaluation Satisfactory 2024-12-20
Overall Implementation Progress (IP) Satisfactory 2024-12-20
Financial Management Moderately Satisfactory 2024-12-20
Procurement Satisfactory 2024-12-20
Project Management Satisfactory 2024-12-20

COMPLETION RATINGS

No data available.

INDEPENDENT EVALUATION RATINGS

No data available.

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • Increased Tunisia-Italy electricity trade capacityValue0.000.00600.00
    DateDecember 30, 2022April 1, 2024December 28, 2028
    Comment
  • Solar/wind capacity additionally installed in TunisiaValue0.000.00400.00
    DateDecember 30, 2022April 1, 2024December 28, 2028
    Comment
  • GHG emissions reduced from the electricity sector (tons/year)Value0.000.00490000.00
    DateDecember 30, 2022April 1, 2024December 28, 2028
    Comment
  • Private investments additionally leveragedValue0.000.00380000000.00
    DateDecember 30, 2022April 1, 2024December 28, 2028
    Comment

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • Transmission line constructedValue0.000.00116.00
    DateDecember 30, 2022April 1, 2024December 28, 2028
    Comment
  • Project grievances addressed within a time frame and publicly communicated by the ProjectValue0.000.0080.00
    DateDecember 30, 2022April 1, 2024December 28, 2028
    Comment
  • Substation constructedValue0.000.001.00
    DateDecember 30, 2022April 1, 2024December 31, 2027
    Comment
  • VRE projects identified and enhanced competitive bidding process completedValueNoNoYes
    DateDecember 30, 2022April 1, 2024June 30, 2026
    Comment
  • Tunisia HDVC converter station constructedValue0.000.001.00
    DateDecember 30, 2022April 1, 2024December 28, 2028
    Comment
  • Share of women in technical positions at STEGValue7.007.0014.00
    DateDecember 30, 2022April 1, 2024December 28, 2028
    Comment
  • Share of women in director positions at STEGValue18.0018.0024.00
    DateDecember 30, 2022April 1, 2024December 28, 2028
    Comment
  • Community members reporting that community engagement processes were effective (transparent, inclusive, responsive)Value0.000.0060.00
    DateDecember 30, 2022April 1, 2024December 28, 2028
    Comment
  • New technical standards for grid resilient infrastructure developed and adoptedValueNoNoYes
    DateDecember 30, 2022April 1, 2024December 28, 2028
    Comment
  • Number of firms/businesses that are grid customers that are indirectly benefiting from improved resilience of the gridValue610780.00610780.00700000.00
    DateDecember 30, 2022April 1, 2024December 28, 2028
    Comment
  • Reduction in System Average Interruption Duration Index (SAIDI)Value0.000.0050.00
    DateDecember 30, 2022April 1, 2024December 28, 2028
    Comment