Financier | Commitments |
---|---|
IDA Credit | 48.00 |
Borrower/Recipient | 0.20 |
IDA Shorter Maturity Loan (SML) | 8.00 |
P179284
Active
Pratap Tvgssshrk , Sombath Southivong
Lao People's Democratic Republic
May 23, 2023
(as of board presentation)
September 30, 2024
February 24, 2025
US$ 34.00 million
Ministry of Public Works and Transport
2025
US$ 56.00 million
N/A
Moderate
August 30, 2030
TBD
BANK APPROVED
June 12, 2023
Financier | Commitments |
---|---|
IDA Credit | 48.00 |
Borrower/Recipient | 0.20 |
IDA Shorter Maturity Loan (SML) | 8.00 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | N/A |
IDA Commitment | 56.00 |
IBRD + IDA Commitment | 56.00 |
Lending Instrument | |
---|---|
Grant Amount | N/A |
Total Project Cost** | 34.00 |
Name | Review | Date |
---|---|---|
Procurement | Satisfactory | 2025-05-03 |
Overall Implementation Progress (IP) | Satisfactory | 2025-05-03 |
Project Management | Satisfactory | 2025-05-03 |
Progress towards achievement of PDO | Satisfactory | 2025-05-03 |
Financial Management | Satisfactory | 2025-05-03 |
Monitoring and Evaluation | Satisfactory | 2025-05-03 |