Water Emergency Relief Project

Abstract*

Operation Abstract: Summary Description of Proposed Project (Approved as part of Approval package on 28 Jun 2023) The project aims to restore access to vital water supply and surface water irrigation services in selected areas in Afghanistan with priority to extreme and severe drought affected rural areas. The project will be financed by an ARTF grant of US$100 million using an IPF instrument with five components of (i) Component 1: Provision of Emergency...

* The project abstract is drawn from the PAD, SAR or PGD and may not accurately reflect the project's current nature

Show More

Development Objective

Improve access to safe drinking water and irrigation water services in selected rural areas

Key Details

Project Details

  • P179311

  • Active

  • Zhimin Mao , Abdul Quraishi

  • Aga Khan Foundation USA,The United Nations Office for Project Services,The United Nations Office for Project Services

  • Afghanistan

  • June 5, 2023

  • (as of board presentation)

    June 28, 2023

  • July 5, 2023

  • US$ 100.00 million

  • The United Nations Office for Project Services,Aga Khan Foundation USA,Aga Khan Foundation-Afghanistan

  • South Asia

  • 2023

  • US$ 100.00 million

  • N/A

  • February 7, 2024

  • June 30, 2025

  • TBD

  • BANK APPROVED

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
Afghanistan Resilience Trust Fund 100.00

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment N/A
IDA Commitment N/A
IBRD + IDA Commitment N/A
Lending Instrument
Grant Amount 100.00
Total Project Cost** 100.00

Summary Status of World Bank Financing (US$ Millions) as of March 31, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of March 31, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Financial Management Satisfactory 2025-02-18
Monitoring and Evaluation Satisfactory 2025-02-18
Overall Implementation Progress (IP) Moderately Satisfactory 2025-02-18
Progress towards achievement of PDO Moderately Satisfactory 2025-02-18
Procurement Moderately Satisfactory 2025-02-18
Project Management Moderately Satisfactory 2025-02-18

COMPLETION RATINGS

No data available.

INDEPENDENT EVALUATION RATINGS

No data available.

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • People provided with access to safe drinking water services/of which are femalesValue0.000.001226880.00
    DateSeptember 16, 2022December 15, 2023June 27, 2025
    Comment
  • Number of farmers gaining access to irrigation water services/of which are femalesValue0.000To be quantified within 45 days upon completion of
    DateAugust 31, 2023December 15, 2023June 27, 2025
    Comment
  • Of which femaleValue0.000.000.00
    Date
    Comment
  • Of which are femalesValue00
    Date
    Comment
  • Percentage of water sampled that complies with WHO standards for biological and physical qualityValue0.000.0080.00
    DateSeptember 23, 2022December 15, 2023June 27, 2025
    Comment

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • Private energy service companies engaged in new operations and maintenance contracts in the water sector in drought-affected regionsValue0.000.004.00
    DateDecember 2, 2022December 15, 2023June 27, 2025
    Comment
  • Number of new constructed water points and schemes/ networksValue0.000.0010224.00
    DateJuly 31, 2023December 15, 2023June 27, 2025
    Comment
  • Number of people trained with water conservation and WASH awareness campainValue0.000.00204480.00
    DateDecember 2, 2022December 15, 2023June 27, 2025
    Comment
  • Contribution to UN Basic Human Needs Indicator 3.1Value0.000.000.00
    Date
    Comment
  • Contribution to UN Basic Human Needs Indicator 2.1Value0.000.000.00
    Date
    Comment
  • Of which femaleValue0.000.00102240.00
    DateDecember 2, 2022December 15, 2023June 27, 2025
    Comment
  • Number of rehabilitated water points and schemes/networksValue0.000.0015226.00
    DateJune 9, 2023December 15, 2023July 31, 2025
    Comment
  • Number of local authorities, CDC members, faculty students (interns) and water technical people trainedValue0.000.002400.00
    DateJune 9, 2023December 15, 2023July 31, 2025
    Comment
  • Number of latrines constructed at health/schools and public centersValue0.000.0042873.00
    DateJune 9, 2023December 15, 2023July 31, 2025
    Comment