Armenia Enabling the Energy Transition Program

Abstract*

Armenia is an upper-middle-income country with a per-capita gross domestic product (GDP) of US6,661 dollars in 2022 that has experienced high yet volatile growth over the past two decades. The government’s vision for the development of the energy sector aims at enhancing Armenia’s energy security while reducing the country’s GHG emissions. In 2021, the Government of Armenia (GoA) issued the “Republic of Armenia Energy Sector Development Strategy to...

* The project abstract is drawn from the PAD, SAR or PGD and may not accurately reflect the project's current nature

Show More

Development Objective

Enable the integration of increased renewable energy capacity into the power transmission grid and enhance the commercial viability of the power transmission company.

Key Details

Project Details

  • P179336

  • Active

  • Gor Khachatryan , Claudio Protano

  • Republic of Armenia

  • Armenia

  • December 15, 2023

  • (as of board presentation)

    May 30, 2024

  • February 19, 2025

  • US$ 50.00 million

  • Electric Power System Operator (EPSO),Ministry of Territorial Administration and Infrastructure (MTAI),Public Services Regulatory Commission (PSRC),High-Voltage Electric Networks (HVEN)

  • Europe and Central Asia

  • 2024

  • US$ 40.00 million

  • N/A

  • April 24, 2023

  • June 30, 2029

  • No

  • BANK APPROVED

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
International Bank for Reconstruction and Development 40.00
Borrower/Recipient 5.00

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment 40.00
IDA Commitment N/A
IBRD + IDA Commitment 40.00
Lending Instrument
Grant Amount N/A
Total Project Cost** 50.00

Summary Status of World Bank Financing (US$ Millions) as of March 31, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of March 31, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)
May 30, 2024 IBRD-96810 Loan Commitment 40,000,000.00

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Progress towards achievement of PDO Satisfactory 2025-02-25
Monitoring and Evaluation Satisfactory 2025-02-25
Overall Implementation Progress (IP) Satisfactory 2025-02-25

COMPLETION RATINGS

No data available.

INDEPENDENT EVALUATION RATINGS

No data available.

Results Framework

No data available.