Financier | Commitments |
---|---|
Early Learning Partnership | 5.00 |
International Bank for Reconstruction and Development | 40.00 |
Global Partnership for Education Fund | 4.80 |
Concessional Financing Facility | 10.00 |
P179363
Active
Anna Olefir
Republic of Moldova
November 17, 2022
(as of board presentation)
May 31, 2023
September 11, 2023
US$ 40.00 million
Ministry of Education and Research,National Office for Regional and Local Development (NORLD)
2023
US$ 59.80 million
N/A
Moderate
December 31, 2029
Yes
BANK APPROVED
February 20, 2024
Financier | Commitments |
---|---|
Early Learning Partnership | 5.00 |
International Bank for Reconstruction and Development | 40.00 |
Global Partnership for Education Fund | 4.80 |
Concessional Financing Facility | 10.00 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | 40.00 |
IDA Commitment | N/A |
IBRD + IDA Commitment | 40.00 |
Lending Instrument | |
---|---|
Grant Amount | 19.80 |
Total Project Cost** | 40.00 |
Period | Financier | Transaction Type | Amount (US$) |
---|---|---|---|
May 31, 2023 | IBRD-95360 | Loan Commitment | 40,000,000.00 |
Jun 1, 2024 | IBRD-95360 | Int Charges | 9,275.67 |
Jun 1, 2024 | IBRD-95360 | Int Charges | 9,275.67 |
Jun 1, 2024 | IBRD-95360 | Int Charges | 39,792.42 |
Feb 6, 2024 | IBRD-95360 | Loan Disb | 322,170.00 |
Jul 8, 2024 | IBRD-95360 | Loan Disb | 433,200.00 |
Jul 17, 2024 | IBRD-95360 | Loan Disb | 95,450.59 |
Jul 17, 2024 | IBRD-95360 | Loan Disb | -95,450.59 |
Jun 18, 2024 | IBRD-95360 | Loan Disb | -308,964.56 |
Jun 18, 2024 | IBRD-95360 | Loan Disb | 308,964.56 |
Dec 1, 2023 | IBRD-95360 | Int Charges | 25,607.95 |
Sep 14, 2023 | IBRD-95360 | Fee Charges | 97,956.88 |
Jan 18, 2024 | IBRD-95360 | Loan Disb | 217,780.00 |
Name | Review | Date |
---|---|---|
Progress towards achievement of PDO | Satisfactory | 2025-02-26 |
Project Management | Satisfactory | 2025-02-26 |
Financial Management | Satisfactory | 2025-02-26 |
Monitoring and Evaluation | Satisfactory | 2025-02-26 |
Procurement | Satisfactory | 2025-02-26 |
Overall Implementation Progress (IP) | Satisfactory | 2025-02-26 |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Participating teachers with improved teaching practices | Value | 0.00 | 0.00 | 90.00 |
Date | February 1, 2023 | February 20, 2024 | December 31, 2029 | |
Comment |
Annual education statistics reports produced and publicly disseminated based on data generated by the integrated EMIS and used for education sector management including refugee response | Value | No integrated EMIS in place | No integrated EMIS in place | Integrated EMIS is operational and reports, produc |
Date | February 1, 2023 | February 20, 2024 | December 31, 2029 | |
Comment |
Improved learning outcomes of students benefitting from project-supported tutoring program (disaggregated by gender, urban/rural, refugee/vulnerability status) | Value | No tutoring program in place | No tutoring program in place | Improvement in scores of beneficiaries compared to |
Date | February 1, 2023 | February 20, 2024 | December 31, 2029 | |
Comment |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Number of schools renovated under the project that meet infrastructure requirements (national quality assurance standards includingon safety, resilience, inclusion, and sustainability requirements) | Value | 0.00 | 0.00 | 15.00 |
Date | February 1, 2023 | February 20, 2024 | December 31, 2029 | |
Comment |
Number of sector staff participating in capacity building trainings under the project | Value | 0.00 | 0.00 | 1000.00 |
Date | February 1, 2023 | February 20, 2024 | December 31, 2029 | |
Comment |
Teachers trained on professional standards under the project (% of teachers in ECEC facilities and grades 1–12) | Value | 0.00 | 0.00 | 20.00 |
Date | February 1, 2023 | February 20, 2024 | December 31, 2029 | |
Comment |
Targeted schools equipped with school labs, IT equipment, and teaching and learning materials including for students with disabilities | Value | 0.00 | 0.00 | 200.00 |
Date | February 1, 2023 | February 20, 2024 | December 31, 2029 | |
Comment |
Monitoring tool with reliable gender-disaggregated data to identify disadvantaged students to receive accelerated learning | Value | No | No | Yes |
Date | February 1, 2023 | February 20, 2024 | December 31, 2029 | |
Comment |
Rapid student assessment mechanism developed and piloted (for selected grade) | Value | No | No | Yes |
Date | February 1, 2023 | February 20, 2024 | December 31, 2029 | |
Comment |
Students benefiting from improved learning environment under the project (disaggregated by urban/rural, refugee/host community, gender, vulnerability status, education level) | Value | 0,00 | 0.00 | 85,000,00 |
Date | February 1, 2023 | February 20, 2024 | December 31, 2029 | |
Comment |
Improved regulatory environment for affordable and quality childcare for preschool children | Value | 0.00 | 0.00 | 4.00 |
Date | February 1, 2023 | February 20, 2024 | December 31, 2029 | |
Comment |
Tutoring/accelerated learning program for disadvantaged students developed and implemented (for selected grade) | Value | No | No | Yes |
Date | February 1, 2023 | February 20, 2024 | December 31, 2029 | |
Comment |
Number of additional students (disadvantaged/refugee), enrolled in preschool premises renovated and endowed under the project | Value | 0.00 | 0.00 | 300.00 |
Date | February 1, 2023 | February 20, 2024 | December 31, 2029 | |
Comment |
Parents reporting an improved capacity to work due to ECEC service provision under the project | Value | 0 | 0 | +20% |
Date | February 1, 2023 | February 20, 2024 | December 31, 2029 | |
Comment |
Students benefiting from direct interventions to enhance learning | Value | 0.00 | 0.00 | 18000.00 |
Date | February 1, 2023 | February 20, 2024 | December 31, 2029 | |
Comment |
Number of direct project host community beneficiaries disaggregated by gender | Value | 0.00 | 0.00 | 28,000.00 |
Date | February 1, 2023 | February 20, 2024 | December 31, 2029 | |
Comment |
Impact evaluations of: (i) tutoring/accelerated learning program and (ii) intervention to accommodate more children in childcare (disadvantaged and refugees) | Value | No | No | Yes |
Date | February 1, 2023 | February 20, 2024 | December 31, 2029 | |
Comment |
Students benefiting from direct interventions to enhance learning - Female | Value | 0.00 | 0.00 | 0.00 |
Date | ||||
Comment |
Number of direct beneficiaries (refugees) disaggregated by gender | Value | 0.00 | 0.00 | 1200.00 |
Date | February 1, 2023 | February 20, 2024 | December 31, 2029 | |
Comment |
Percentage of students and teachers satisfied with improved classroom learning environment and functionality of schools and preschools under the project | Value | 0.00 | 0.00 | 85.00 |
Date | February 1, 2023 | February 20, 2024 | December 31, 2029 | |
Comment |
Teachers recruited or trained | Value | 0.00 | 0.00 | 5300.00 |
Date | February 1, 2023 | February 20, 2024 | December 31, 2029 | |
Comment |
Number of new high schools constructed in priority areas that meet infrastructure requirements under national quality assurance standards | Value | 0.00 | 0.00 | 3.00 |
Date | February 1, 2023 | February 20, 2024 | December 31, 2029 | |
Comment |
Percentage of school users who report that consultation processes are effective | Value | 0.00 | 0.00 | 70.00 |
Date | February 2, 2023 | February 20, 2024 | December 31, 2029 | |
Comment |
Gender gap in STEM education reduced | Value | 7.00 | 7.00 | 5.00 |
Date | February 1, 2023 | February 20, 2024 | December 31, 2029 | |
Comment |