Education Quality Improvement Project

Abstract*

Operation Abstract: Summary Description of Proposed Project (Approved as part of Approval package on 31 May 2023) Education is a national priority for Moldova in the National Development Strategy (NDS) ‘European Moldova 2030’. Under the Moldova Education Strategy 2014-2020, the Government of Moldova (GoM) implemented comprehensive reforms to improve learning and value for money in education. Moldova made significant progress on education outcomes...

* The project abstract is drawn from the PAD, SAR or PGD and may not accurately reflect the project's current nature

Show More

Development Objective

The objectives of the Project are to: (i) improve the learning environment in participating institutions, with an emphasis on supporting disadvantaged students; and (ii) strengthen the capacity of the Ministry of Education and Research for sector management and refugee response.

Key Details

Project Details

  • P179363

  • Active

  • Anna Olefir

  • Republic of Moldova

  • Moldova

  • November 17, 2022

  • (as of board presentation)

    May 31, 2023

  • September 11, 2023

  • US$ 40.00 million

  • Ministry of Education and Research,National Office for Regional and Local Development (NORLD)

  • Europe and Central Asia

  • 2023

  • US$ 59.80 million

  • N/A

  • Moderate

  • December 31, 2029

  • Yes

  • BANK APPROVED

  • February 20, 2024

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
Early Learning Partnership 5.00
International Bank for Reconstruction and Development 40.00
Global Partnership for Education Fund 4.80
Concessional Financing Facility 10.00

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment 40.00
IDA Commitment N/A
IBRD + IDA Commitment 40.00
Lending Instrument
Grant Amount 19.80
Total Project Cost** 40.00

Summary Status of World Bank Financing (US$ Millions) as of April 30, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of April 30, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)
May 31, 2023 IBRD-95360 Loan Commitment 40,000,000.00
Jun 1, 2024 IBRD-95360 Int Charges 9,275.67
Jun 1, 2024 IBRD-95360 Int Charges 9,275.67
Jun 1, 2024 IBRD-95360 Int Charges 39,792.42
Feb 6, 2024 IBRD-95360 Loan Disb 322,170.00
Jul 8, 2024 IBRD-95360 Loan Disb 433,200.00
Jul 17, 2024 IBRD-95360 Loan Disb 95,450.59
Jul 17, 2024 IBRD-95360 Loan Disb -95,450.59
Jun 18, 2024 IBRD-95360 Loan Disb -308,964.56
Jun 18, 2024 IBRD-95360 Loan Disb 308,964.56
Dec 1, 2023 IBRD-95360 Int Charges 25,607.95
Sep 14, 2023 IBRD-95360 Fee Charges 97,956.88
Jan 18, 2024 IBRD-95360 Loan Disb 217,780.00

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Progress towards achievement of PDO Satisfactory 2025-02-26
Project Management Satisfactory 2025-02-26
Financial Management Satisfactory 2025-02-26
Monitoring and Evaluation Satisfactory 2025-02-26
Procurement Satisfactory 2025-02-26
Overall Implementation Progress (IP) Satisfactory 2025-02-26

COMPLETION RATINGS

No data available.

INDEPENDENT EVALUATION RATINGS

No data available.

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • Participating teachers with improved teaching practicesValue0.000.0090.00
    DateFebruary 1, 2023February 20, 2024December 31, 2029
    Comment
  • Annual education statistics reports produced and publicly disseminated based on data generated by the integrated EMIS and used for education sector management including refugee responseValueNo integrated EMIS in placeNo integrated EMIS in placeIntegrated EMIS is operational and reports, produc
    DateFebruary 1, 2023February 20, 2024December 31, 2029
    Comment
  • Improved learning outcomes of students benefitting from project-supported tutoring program (disaggregated by gender, urban/rural, refugee/vulnerability status)ValueNo tutoring program in placeNo tutoring program in placeImprovement in scores of beneficiaries compared to
    DateFebruary 1, 2023February 20, 2024December 31, 2029
    Comment

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • Number of schools renovated under the project that meet infrastructure requirements (national quality assurance standards includingon safety, resilience, inclusion, and sustainability requirements)Value0.000.0015.00
    DateFebruary 1, 2023February 20, 2024December 31, 2029
    Comment
  • Number of sector staff participating in capacity building trainings under the projectValue0.000.001000.00
    DateFebruary 1, 2023February 20, 2024December 31, 2029
    Comment
  • Teachers trained on professional standards under the project (% of teachers in ECEC facilities and grades 1–12)Value0.000.0020.00
    DateFebruary 1, 2023February 20, 2024December 31, 2029
    Comment
  • Targeted schools equipped with school labs, IT equipment, and teaching and learning materials including for students with disabilitiesValue0.000.00200.00
    DateFebruary 1, 2023February 20, 2024December 31, 2029
    Comment
  • Monitoring tool with reliable gender-disaggregated data to identify disadvantaged students to receive accelerated learningValueNoNoYes
    DateFebruary 1, 2023February 20, 2024December 31, 2029
    Comment
  • Rapid student assessment mechanism developed and piloted (for selected grade)ValueNoNoYes
    DateFebruary 1, 2023February 20, 2024December 31, 2029
    Comment
  • Students benefiting from improved learning environment under the project (disaggregated by urban/rural, refugee/host community, gender, vulnerability status, education level)Value0,000.0085,000,00
    DateFebruary 1, 2023February 20, 2024December 31, 2029
    Comment
  • Improved regulatory environment for affordable and quality childcare for preschool childrenValue0.000.004.00
    DateFebruary 1, 2023February 20, 2024December 31, 2029
    Comment
  • Tutoring/accelerated learning program for disadvantaged students developed and implemented (for selected grade)ValueNoNoYes
    DateFebruary 1, 2023February 20, 2024December 31, 2029
    Comment
  • Number of additional students (disadvantaged/refugee), enrolled in preschool premises renovated and endowed under the projectValue0.000.00300.00
    DateFebruary 1, 2023February 20, 2024December 31, 2029
    Comment
  • Parents reporting an improved capacity to work due to ECEC service provision under the projectValue00+20%
    DateFebruary 1, 2023February 20, 2024December 31, 2029
    Comment
  • Students benefiting from direct interventions to enhance learningValue0.000.0018000.00
    DateFebruary 1, 2023February 20, 2024December 31, 2029
    Comment
  • Number of direct project host community beneficiaries disaggregated by genderValue0.000.0028,000.00
    DateFebruary 1, 2023February 20, 2024December 31, 2029
    Comment
  • Impact evaluations of: (i) tutoring/accelerated learning program and (ii) intervention to accommodate more children in childcare (disadvantaged and refugees)ValueNoNoYes
    DateFebruary 1, 2023February 20, 2024December 31, 2029
    Comment
  • Students benefiting from direct interventions to enhance learning - FemaleValue0.000.000.00
    Date
    Comment
  • Number of direct beneficiaries (refugees) disaggregated by genderValue0.000.001200.00
    DateFebruary 1, 2023February 20, 2024December 31, 2029
    Comment
  • Percentage of students and teachers satisfied with improved classroom learning environment and functionality of schools and preschools under the projectValue0.000.0085.00
    DateFebruary 1, 2023February 20, 2024December 31, 2029
    Comment
  • Teachers recruited or trainedValue0.000.005300.00
    DateFebruary 1, 2023February 20, 2024December 31, 2029
    Comment
  • Number of new high schools constructed in priority areas that meet infrastructure requirements under national quality assurance standardsValue0.000.003.00
    DateFebruary 1, 2023February 20, 2024December 31, 2029
    Comment
  • Percentage of school users who report that consultation processes are effectiveValue0.000.0070.00
    DateFebruary 2, 2023February 20, 2024December 31, 2029
    Comment
  • Gender gap in STEM education reducedValue7.007.005.00
    DateFebruary 1, 2023February 20, 2024December 31, 2029
    Comment