Kenya Jobs and Economic Transformation (KJET) Project

Abstract*

To improve private sector access to markets and finance to create and improve jobs. This will be accomplished via 3 main components: 1. Component 1: Strengthening Business and Investment Enabling Reforms - This components will target government failures in the business regulatory and FDI environment via diagnostics related to risk-based regulatory approaches and FDI policy and promotion at the national, county, and value chain levels, followed by...

* The project abstract is drawn from the PAD, SAR or PGD and may not accurately reflect the project's current nature

Show More

Development Objective

To increase private sector investments, access to markets and sustainable finance to create and improve jobs

Key Details

Project Details

  • P179381

  • Active

  • Ahmed Rostom , Asta Bareisaite, Leah Kiwara

  • Republic of Kenya

  • Kenya

  • August 3, 2023

  • (as of board presentation)

    December 11, 2023

  • July 9, 2024

  • US$ 225.00 million

  • Ministry of Co-operatives and Micro, Small and Medium Enterprises (MSME) Development,Ministry of Investment, Trade, and Industry

  • Eastern and Southern Africa

  • 2024

  • US$ 150.00 million

  • N/A

  • May 24, 2023

  • December 31, 2028

  • TBD

  • BANK APPROVED

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
IDA Credit 150.00

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment N/A
IDA Commitment 150.00
IBRD + IDA Commitment 150.00
Lending Instrument
Grant Amount N/A
Total Project Cost** 225.00

Summary Status of World Bank Financing (US$ Millions) as of February 28, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of February 28, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)
Dec 11, 2023 IDA-74500 Loan Commitment 150,000,000.00

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Overall Implementation Progress (IP) Satisfactory 2024-11-25
Project Management Satisfactory 2024-11-25
Financial Management Satisfactory 2024-11-25
Progress towards achievement of PDO Satisfactory 2024-11-25
Procurement Satisfactory 2024-11-25
Monitoring and Evaluation Satisfactory 2024-11-25

COMPLETION RATINGS

No data available.

INDEPENDENT EVALUATION RATINGS

No data available.

Results Framework

No data available.