Nigeria Distributed Access through Renewable Energy Scale-up Project

Abstract*

The development objective of the Distributed Access Through Renewable Energy Scale-Up Project for Nigeria is to increase access to electricity services for households and micro, small, and medium-sized enterprises (MSMEs) with private sector led distributed renewable energy generation. The project comprises of three components. The first component, solar hybrid mini grids for economic development will support the development of privately owned and...

* The project abstract is drawn from the PAD, SAR or PGD and may not accurately reflect the project's current nature

Show More

Development Objective

The project development objective (PDO) is to increase private sector led access to reliable electricity services for households, public institutions, and commercial customers in Nigeria, and facilitate increased productive uses of clean electricity.

Key Details

Project Details

  • P179687

  • Active

  • Arsh Sharma , Ashish Shrestha, Collins Obi

  • Federal Republic of Nigeria

  • Nigeria

  • March 1, 2023

  • (as of board presentation)

    December 14, 2023

  • November 15, 2024

  • US$ 750.00 million

  • Lagos State Electricity Board,Rural Electrification Agency

  • Western and Central Africa

  • 2024

  • US$ 750.00 million

  • N/A

  • May 12, 2023

  • December 31, 2028

  • Yes

  • BANK APPROVED

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
IDA Credit 150.00
Foundation/s (identified) 40.00
IDA Shorter Maturity Loan (SML) 600.00

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment N/A
IDA Commitment 750.00
IBRD + IDA Commitment 750.00
Lending Instrument
Grant Amount N/A
Total Project Cost** 750.00

Summary Status of World Bank Financing (US$ Millions) as of February 28, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of February 28, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)
Dec 14, 2023 IDA-74660 Loan Commitment 350,000,000.00
Dec 14, 2023 IDA-74680 Loan Commitment 150,000,000.00
Dec 14, 2023 IDA-74670 Loan Commitment 250,000,000.00

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Procurement Satisfactory 2024-10-31
Financial Management Satisfactory 2024-10-31
Monitoring and Evaluation Satisfactory 2024-10-31
Overall Implementation Progress (IP) Satisfactory 2024-10-31
Project Management Satisfactory 2024-10-31
Progress towards achievement of PDO Satisfactory 2024-10-31

COMPLETION RATINGS

No data available.

INDEPENDENT EVALUATION RATINGS

No data available.

Results Framework

No data available.