Romania Rural Pollution Prevention and Reduction Project (RAPID)

Abstract*

The Project supports strengthening the institutional capacity of the Ministry of Environment Waters and Forests (MEWF), the National Administration Romanian Waters (ANAR), the National Phytosanitary Authority (NFA) and the Directorate of Land Improvements and Land Fund (LILF) of the MARD to monitor pollution reduction from agriculture. The Project will go beyond the previous support provided for nutrient pollution in the Integrated Nutrient Pollution...

* The project abstract is drawn from the PAD, SAR or PGD and may not accurately reflect the project's current nature

Show More

Development Objective

The Project Development Objective is to strengthen the institutional capacity of selected public entities to monitor pollution from agriculture, and to transfer knowledge on agricultural pollution reduction for adoption by participating farmers.

Key Details

Project Details

  • P179786

  • Active

  • Alexandru Buteica

  • Ministry of Finance

  • Romania

  • October 17, 2022

  • (as of board presentation)

    March 30, 2023

  • December 13, 2023

  • US$ 58.47 million

  • Ministry of Environment, Waters and Forests

  • Europe and Central Asia

  • 2023

  • US$ 63.60 million

  • N/A

  • February 6, 2024

  • June 30, 2028

  • TBD

  • BANK APPROVED

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
International Bank for Reconstruction and Development 63.60

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment 63.60
IDA Commitment N/A
IBRD + IDA Commitment 63.60
Lending Instrument
Grant Amount N/A
Total Project Cost** 58.47

Summary Status of World Bank Financing (US$ Millions) as of March 31, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of March 31, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)
Jun 18, 2024 IBRD-95050 Loan Disb 97,812.71
Dec 21, 2023 IBRD-95050 Fee Charges 164,700.00
Mar 30, 2023 IBRD-95050 Loan Commitment 63,600,000.00
Aug 13, 2024 IBRD-95050 Loan Disb 111,614.06
May 6, 2024 IBRD-95050 Loan Disb 113,593.08
Apr 15, 2024 IBRD-95050 Int Charges 137,831.40

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Progress towards achievement of PDO Moderately Satisfactory 2024-12-18
Financial Management Satisfactory 2024-12-18
Monitoring and Evaluation Satisfactory 2024-12-18
Overall Implementation Progress (IP) Moderately Satisfactory 2024-12-18
Procurement Satisfactory 2024-12-18
Project Management Moderately Satisfactory 2024-12-18

COMPLETION RATINGS

No data available.

INDEPENDENT EVALUATION RATINGS

No data available.

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • Reporting by public entities meeting defined criteriaValue0.000.0080.00
    DateJune 30, 2023November 30, 2023June 30, 2028
    Comment
  • Participating farmers adopting agricultural pollution reduction practices as a result of the projectValue0.000.0050.00
    DateJune 30, 2023November 30, 2023June 30, 2028
    Comment
  • Reports by MEWF meeting defined criteriaValue0.000.0080.00
    DateJune 30, 2023November 30, 2023June 30, 2028
    Comment
  • Participating farmers adopting agricultural pollution reduction practices as a result of the project - femaleValue0.000.000.00
    Date
    Comment
  • Reports produced by ANAR meeting defined criteriaValue0.000.0080.00
    DateJune 30, 2023November 30, 2023June 30, 2028
    Comment
  • Reports produced by NFA meeting defined criteriaValue0.000.0080.00
    DateJune 30, 2023November 30, 2023June 30, 2028
    Comment
  • Reports produced by LILF meeting defined criteriaValue0.000.0080.00
    DateJune 30, 2023November 30, 2023June 30, 2028
    Comment

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • Demonstration farms that function as training sites are createdValue0.000.0070.00
    DateJune 30, 2023November 30, 2023June 30, 2028
    Comment
  • NRRP’s agriculture waste management component financing mobilized by MEWF with support by the projectValue0.000.00250000000.00
    DateJune 30, 2023November 30, 2023June 30, 2028
    Comment
  • Grievances registered related to delivery of project benefits that are addressedValue0.000.0080.00
    DateJune 30, 2023November 30, 2023June 30, 2028
    Comment
  • ANAR staff have obtained skills to use the equipment provided by the projectValue0.000.00100.00
    DateJune 30, 2023November 30, 2023June 30, 2028
    Comment
  • Share of demonstration farms that function as training sites are created (female-led farms)Value0.000.000.00
    Date
    Comment
  • Regions with established and functioning KTNsValue0.000.008.00
    DateJune 30, 2023November 30, 2023June 30, 2028
    Comment
  • NFA staff have obtained skills to use the equipment provided by the projectValue0.000.00100.00
    DateJune 30, 2023November 30, 2023June 30, 2028
    Comment
  • Farmer Discussion Groups on knowledge transfer to prevent and reduce agricultural pollution are set-up and operationalValue0.000.00400.00
    DateJune 30, 2023November 30, 2023June 30, 2028
    Comment
  • Software platform to trace pesticides and pollutants is developed and is operationalValueNo platform is in placeNo platform is in placePlatform is in place and operational
    DateJune 30, 2023November 30, 2023June 30, 2028
    Comment
  • Share of women participating in knowledge networks, trainings, and consultationsValue0.000.000.00
    Date
    Comment
  • Land area under sustainable landscape management practicesValue0.000.0030000.00
    DateJune 30, 2023November 30, 2023June 30, 2028
    Comment
  • Agricultural pollution reduction and knowledge sharing events organizedValue0.000.0012.00
    DateJune 30, 2023November 30, 2023June 30, 2028
    Comment
  • Beneficiaries satisfied with project-supported servicesValue0.000.0080.00
    DateJune 30, 2023November 30, 2023June 30, 2028
    Comment
  • Beneficiaries satisfied with project-supported services - femaleValue0.000.000.00
    Date
    Comment
  • Beneficiaries reporting effective engagement processes established by the projectValue0.000.0080.00
    DateJune 30, 2023November 30, 2023June 30, 2028
    Comment
  • Beneficiaries reporting effective engagement processes established by the project - femaleValue0.000.000.00
    Date
    Comment
  • Content on climate smart agriculture, climate mitigation, adaptation and practices for emissions reductions from agriculture integrated in training materials and programs for KTNs and FDGsValue0.000.0080.00
    DateJune 30, 2023November 30, 2023June 30, 2028
    Comment
  • Content on climate smart agriculture, climate mitigation, adaptation and practices for emissions reductions from agriculture integrated in the awareness campaignValue0.000.0080.00
    DateJune 30, 2023November 30, 2023June 30, 2028
    Comment
  • Grants mobilized for CSA/GHG emission reduction/adaptation measuresValue0.000.0080.00
    DateJune 30, 2023November 30, 2023June 30, 2028
    Comment