Sindh Flood Emergency Housing Reconstruction Project

Abstract*

The development objective of the Sindh Flood Emergency Housing Reconstruction Project for Pakistan is to deliver beneficiary‐driven, multi‐hazard resilient reconstruction of core housing units affected by the 2022 floods in selected districts of Sindh. The project comprises of three components. The first component, housing reconstruction grants will support the provision of housing reconstruction grants to beneficiaries for reconstruction and or restoration...

* The project abstract is drawn from the PAD, SAR or PGD and may not accurately reflect the project's current nature

Show More

Development Objective

To deliver beneficiary-driven, multi-hazard resilient reconstruction of core housing units affected by the 2022 floods in selected districts of Sindh.

Key Details

Project Details

  • P180008

  • Active

  • Kamran Akbar , Yunziyi Lang

  • Islamic Republic of Pakistan

  • Pakistan

  • November 11, 2022

  • (as of board presentation)

    December 19, 2022

  • January 16, 2023

  • US$ 500.00 million

  • Province of Sindh, Sindh Peoples Housing for Flood Affectees

  • South Asia

  • 2023

  • US$ 500.00 million

  • N/A

  • December 17, 2023

  • June 30, 2028

  • Yes

  • BANK APPROVED

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
IDA Credit 500.00

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment N/A
IDA Commitment 500.00
IBRD + IDA Commitment 500.00
Lending Instrument
Grant Amount N/A
Total Project Cost** 500.00

Summary Status of World Bank Financing (US$ Millions) as of January 31, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of January 31, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)
Nov 1, 2023 IDA-72530 Loan Disb 50,000,000.00
Dec 15, 2023 IDA-72530 Loan Disb 50,000,000.00
Nov 1, 2023 IDA-72530 Int Charges 569,430.56
Nov 1, 2023 IDA-72530 Int Charges 2,042.68
Nov 1, 2023 IDA-72530 Int Charges 341,658.38
Nov 1, 2023 IDA-72530 Int Charges 341,658.38
May 1, 2024 IDA-72530 Int Charges 14,592.25
May 1, 2024 IDA-72530 Int Charges 14,592.25
May 1, 2024 IDA-72530 Int Charges 868,318.94
May 1, 2024 IDA-72530 Int Charges 868,318.94
May 1, 2024 IDA-72530 Int Charges 1,471,518.60
Feb 2, 2024 IDA-72530 Loan Disb 100,000,000.00
May 28, 2024 IDA-72530 Loan Disb 50,000,000.00
Dec 19, 2022 IDA-72530 Loan Commitment 500,000,000.00
Jul 30, 2024 IDA-72530 Loan Disb 50,000,000.00
Feb 14, 2023 IDA-72530 Loan Disb 61,100,000.00
May 2, 2023 IDA-72530 Int Charges 98,232.27
May 2, 2023 IDA-72530 Int Charges 98,232.27
May 2, 2023 IDA-72530 Int Charges 161,622.33
Jun 7, 2023 IDA-72530 Loan Disb 40,000,000.00

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Project Management Satisfactory 2024-12-18
Progress towards achievement of PDO Satisfactory 2024-12-18
Financial Management Satisfactory 2024-12-18
Monitoring and Evaluation Satisfactory 2024-12-18
Overall Implementation Progress (IP) Satisfactory 2024-12-18
Project Management Satisfactory 2024-12-18
Progress towards achievement of PDO Satisfactory 2024-12-18
Monitoring and Evaluation Satisfactory 2024-12-18
Overall Implementation Progress (IP) Satisfactory 2024-12-18
Procurement Satisfactory 2024-12-18
Project Management Satisfactory 2024-12-18
Procurement Satisfactory 2024-12-18
Financial Management Satisfactory 2024-12-18
Progress towards achievement of PDO Satisfactory 2024-12-18
Financial Management Satisfactory 2024-12-18
Monitoring and Evaluation Satisfactory 2024-12-18
Overall Implementation Progress (IP) Satisfactory 2024-12-18
Procurement Satisfactory 2024-12-18

COMPLETION RATINGS

No data available.

INDEPENDENT EVALUATION RATINGS

No data available.

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • Core housing units reconstructed/restored to multi-hazard resilient standards.Value0.00165.00350000.00
    DateDecember 1, 2022October 24, 2023December 1, 2025
    Comment
  • Beneficiaries that have received project trainings for multi-hazard resilient reconstruction practices.Value0.0077001.00400000.00
    DateDecember 1, 2022October 24, 2023December 1, 2025
    Comment
  • Households reporting satisfaction with project interventionsValue0.000.0080.00
    DateDecember 1, 2022October 24, 2023December 15, 2027
    Comment
  • Of which are for female headed householdsValue0.000.000.00
    Date
    Comment
  • Participants in project trainings who are female.Value0.000.000.00
    Date
    Comment
  • Number of vulnerable people benefiting from the housing reconstructionValue0.0019.005500.00
    DateDecember 1, 2022October 24, 2023December 1, 2025
    Comment

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • Beneficiaries from housing subsidy cash grants with improved WASH outcomes.Value0.000.001400000.00
    DateDecember 15, 2022October 24, 2023June 30, 2026
    Comment
  • Housing reconstruction strategy is formulated and adopted.ValueNoYesYes
    DateDecember 1, 2022October 24, 2023January 16, 2023
    Comment
  • Multi-hazard resilient housing solution(s) developed and adopted.ValueNoYesYes
    DateDecember 1, 2022October 24, 2023December 31, 2022
    Comment
  • Of which are female beneficiaries.Value0.000.000.00
    Date
    Comment
  • Housing subsidy cash grants disbursed.Value0.0061170000.00470000000.00
    DateDecember 15, 2022October 24, 2023June 30, 2026
    Comment
  • Intended beneficiaries aware of project information and project investments.Value0.0093.00100.00
    DateDecember 15, 2022October 24, 2023June 30, 2026
    Comment
  • Housing subsidy cash grant recipients who are female.Value0.0028.0020.00
    DateDecember 15, 2022October 24, 2023June 30, 2026
    Comment