Financier | Commitments |
---|---|
IDA Credit | 500.00 |
P180008
Active
Kamran Akbar , Yunziyi Lang
Islamic Republic of Pakistan
November 11, 2022
(as of board presentation)
December 19, 2022
January 16, 2023
US$ 500.00 million
Province of Sindh, Sindh Peoples Housing for Flood Affectees
2023
US$ 500.00 million
N/A
December 17, 2023
June 30, 2028
Yes
BANK APPROVED
Financier | Commitments |
---|---|
IDA Credit | 500.00 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | N/A |
IDA Commitment | 500.00 |
IBRD + IDA Commitment | 500.00 |
Lending Instrument | |
---|---|
Grant Amount | N/A |
Total Project Cost** | 500.00 |
Period | Financier | Transaction Type | Amount (US$) |
---|---|---|---|
Nov 1, 2023 | IDA-72530 | Loan Disb | 50,000,000.00 |
Dec 15, 2023 | IDA-72530 | Loan Disb | 50,000,000.00 |
Nov 1, 2023 | IDA-72530 | Int Charges | 569,430.56 |
Nov 1, 2023 | IDA-72530 | Int Charges | 2,042.68 |
Nov 1, 2023 | IDA-72530 | Int Charges | 341,658.38 |
Nov 1, 2023 | IDA-72530 | Int Charges | 341,658.38 |
May 1, 2024 | IDA-72530 | Int Charges | 14,592.25 |
May 1, 2024 | IDA-72530 | Int Charges | 14,592.25 |
May 1, 2024 | IDA-72530 | Int Charges | 868,318.94 |
May 1, 2024 | IDA-72530 | Int Charges | 868,318.94 |
May 1, 2024 | IDA-72530 | Int Charges | 1,471,518.60 |
Feb 2, 2024 | IDA-72530 | Loan Disb | 100,000,000.00 |
May 28, 2024 | IDA-72530 | Loan Disb | 50,000,000.00 |
Dec 19, 2022 | IDA-72530 | Loan Commitment | 500,000,000.00 |
Jul 30, 2024 | IDA-72530 | Loan Disb | 50,000,000.00 |
Feb 14, 2023 | IDA-72530 | Loan Disb | 61,100,000.00 |
May 2, 2023 | IDA-72530 | Int Charges | 98,232.27 |
May 2, 2023 | IDA-72530 | Int Charges | 98,232.27 |
May 2, 2023 | IDA-72530 | Int Charges | 161,622.33 |
Jun 7, 2023 | IDA-72530 | Loan Disb | 40,000,000.00 |
Name | Review | Date |
---|---|---|
Project Management | Satisfactory | 2024-12-18 |
Progress towards achievement of PDO | Satisfactory | 2024-12-18 |
Financial Management | Satisfactory | 2024-12-18 |
Monitoring and Evaluation | Satisfactory | 2024-12-18 |
Overall Implementation Progress (IP) | Satisfactory | 2024-12-18 |
Project Management | Satisfactory | 2024-12-18 |
Progress towards achievement of PDO | Satisfactory | 2024-12-18 |
Monitoring and Evaluation | Satisfactory | 2024-12-18 |
Overall Implementation Progress (IP) | Satisfactory | 2024-12-18 |
Procurement | Satisfactory | 2024-12-18 |
Project Management | Satisfactory | 2024-12-18 |
Procurement | Satisfactory | 2024-12-18 |
Financial Management | Satisfactory | 2024-12-18 |
Progress towards achievement of PDO | Satisfactory | 2024-12-18 |
Financial Management | Satisfactory | 2024-12-18 |
Monitoring and Evaluation | Satisfactory | 2024-12-18 |
Overall Implementation Progress (IP) | Satisfactory | 2024-12-18 |
Procurement | Satisfactory | 2024-12-18 |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Core housing units reconstructed/restored to multi-hazard resilient standards. | Value | 0.00 | 165.00 | 350000.00 |
Date | December 1, 2022 | October 24, 2023 | December 1, 2025 | |
Comment |
Beneficiaries that have received project trainings for multi-hazard resilient reconstruction practices. | Value | 0.00 | 77001.00 | 400000.00 |
Date | December 1, 2022 | October 24, 2023 | December 1, 2025 | |
Comment |
Households reporting satisfaction with project interventions | Value | 0.00 | 0.00 | 80.00 |
Date | December 1, 2022 | October 24, 2023 | December 15, 2027 | |
Comment |
Of which are for female headed households | Value | 0.00 | 0.00 | 0.00 |
Date | ||||
Comment |
Participants in project trainings who are female. | Value | 0.00 | 0.00 | 0.00 |
Date | ||||
Comment |
Number of vulnerable people benefiting from the housing reconstruction | Value | 0.00 | 19.00 | 5500.00 |
Date | December 1, 2022 | October 24, 2023 | December 1, 2025 | |
Comment |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Beneficiaries from housing subsidy cash grants with improved WASH outcomes. | Value | 0.00 | 0.00 | 1400000.00 |
Date | December 15, 2022 | October 24, 2023 | June 30, 2026 | |
Comment |
Housing reconstruction strategy is formulated and adopted. | Value | No | Yes | Yes |
Date | December 1, 2022 | October 24, 2023 | January 16, 2023 | |
Comment |
Multi-hazard resilient housing solution(s) developed and adopted. | Value | No | Yes | Yes |
Date | December 1, 2022 | October 24, 2023 | December 31, 2022 | |
Comment |
Of which are female beneficiaries. | Value | 0.00 | 0.00 | 0.00 |
Date | ||||
Comment |
Housing subsidy cash grants disbursed. | Value | 0.00 | 61170000.00 | 470000000.00 |
Date | December 15, 2022 | October 24, 2023 | June 30, 2026 | |
Comment |
Intended beneficiaries aware of project information and project investments. | Value | 0.00 | 93.00 | 100.00 |
Date | December 15, 2022 | October 24, 2023 | June 30, 2026 | |
Comment |
Housing subsidy cash grant recipients who are female. | Value | 0.00 | 28.00 | 20.00 |
Date | December 15, 2022 | October 24, 2023 | June 30, 2026 | |
Comment |