Financier | Commitments |
---|---|
IDA Credit | 50.00 |
Borrower/Recipient | 13.95 |
IDA Shorter Maturity Loan (SML) | 76.00 |
P180228
Active
Aguiratou Savadogo-Tinto , Alejandro Espinosa-Wang, Solange Mizero
Republic of Rwanda
Rwanda
June 6, 2023
(as of board presentation)
March 29, 2024
August 2, 2024
US$ 113.60 million
Rwanda Transport Development Agency (RTDA),Ministry of Trade and Industry (MINICOM),Ministry of Infrastructure (MININFRA)
2024
US$ 126.00 million
N/A
High
September 30, 2030
Yes
BANK APPROVED
May 30, 2023
Financier | Commitments |
---|---|
IDA Credit | 50.00 |
Borrower/Recipient | 13.95 |
IDA Shorter Maturity Loan (SML) | 76.00 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | N/A |
IDA Commitment | 126.00 |
IBRD + IDA Commitment | 126.00 |
Lending Instrument | |
---|---|
Grant Amount | N/A |
Total Project Cost** | 113.60 |
Period | Financier | Transaction Type | Amount (US$) |
---|---|---|---|
Mar 29, 2024 | IDA-75300 | Loan Commitment | 76,000,000.00 |
Mar 29, 2024 | IDA-75310 | Loan Commitment | 50,000,000.00 |
Name | Review | Date |
---|---|---|
Overall Implementation Progress (IP) | Satisfactory | 2025-03-27 |
Project Management | Satisfactory | 2025-03-27 |
Progress towards achievement of PDO | Satisfactory | 2025-03-27 |
Financial Management | Satisfactory | 2025-03-27 |
Monitoring and Evaluation | Satisfactory | 2025-03-27 |
Procurement | Satisfactory | 2025-03-27 |