Kigali Logistics Platform Connectivity Development Project

Abstract*

The Kigali Logistics Platform Connectivity Development Project (KLPConnect) will provide connectivity to the logistics platform at Massaka (Kigali) to expand the traffic capacity in a safe, convenient, and cost-effective manner and promote regional and international trade. The KLPConnect will rehabilitate 69.45 km to link Massaka to Bugesera Industrial Park located on NR 5 between Ramiro and Kibugabuga towns and open opportunities for industries to...

* The project abstract is drawn from the PAD, SAR or PGD and may not accurately reflect the project's current nature

Show More

Development Objective

The objectives of the Project are to improve resilient and safe connectivity from the KLP (Masaka) to the regional logistics corridors and support local and regional economic activities around the corridors.

Key Details

Project Details

  • P180228

  • Active

  • Aguiratou Savadogo-Tinto , Alejandro Espinosa-Wang, Solange Mizero

  • Republic of Rwanda

  • Rwanda

  • June 6, 2023

  • (as of board presentation)

    March 29, 2024

  • August 2, 2024

  • US$ 113.60 million

  • Rwanda Transport Development Agency (RTDA),Ministry of Trade and Industry (MINICOM),Ministry of Infrastructure (MININFRA)

  • Eastern and Southern Africa

  • 2024

  • US$ 126.00 million

  • N/A

  • High

  • September 30, 2030

  • Yes

  • BANK APPROVED

  • May 30, 2023

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
IDA Credit 50.00
Borrower/Recipient 13.95
IDA Shorter Maturity Loan (SML) 76.00

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment N/A
IDA Commitment 126.00
IBRD + IDA Commitment 126.00
Lending Instrument
Grant Amount N/A
Total Project Cost** 113.60

Summary Status of World Bank Financing (US$ Millions) as of April 30, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of April 30, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)
Mar 29, 2024 IDA-75300 Loan Commitment 76,000,000.00
Mar 29, 2024 IDA-75310 Loan Commitment 50,000,000.00

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Overall Implementation Progress (IP) Satisfactory 2025-03-27
Project Management Satisfactory 2025-03-27
Progress towards achievement of PDO Satisfactory 2025-03-27
Financial Management Satisfactory 2025-03-27
Monitoring and Evaluation Satisfactory 2025-03-27
Procurement Satisfactory 2025-03-27

COMPLETION RATINGS