Financier | Commitments |
---|---|
IDA Credit | 213.00 |
P180323
Active
Kamran Akbar , Carlo Amadei
Islamic Republic of Pakistan
April 21, 2023
(as of board presentation)
May 25, 2023
July 20, 2023
US$ 400.00 million
Ministry of Planning, Development and Special Initiatives,Irrigation Department, Province of Balochistan,Planning and Development Department, Province of Balochistan
2023
US$ 213.00 million
N/A
January 25, 2024
December 31, 2028
Yes
BANK APPROVED
Financier | Commitments |
---|---|
IDA Credit | 213.00 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | N/A |
IDA Commitment | 213.00 |
IBRD + IDA Commitment | 213.00 |
Lending Instrument | |
---|---|
Grant Amount | N/A |
Total Project Cost** | 400.00 |
Period | Financier | Transaction Type | Amount (US$) |
---|---|---|---|
Aug 1, 2024 | IDA-73330 | Int Charges | 54,427.51 |
Mar 29, 2024 | IDA-73330 | Loan Disb | 1,784,357.10 |
May 7, 2024 | IDA-73330 | Loan Disb | 1,035,766.30 |
Aug 1, 2024 | IDA-73330 | Int Charges | 54,427.51 |
May 25, 2023 | IDA-73330 | Loan Commitment | 213,000,000.00 |
Mar 5, 2024 | IDA-73330 | Loan Disb | 10,573,011.00 |
May 10, 2024 | IDA-73330 | Loan Disb | 8,989,053.00 |
Name | Review | Date |
---|---|---|
Progress towards achievement of PDO | Moderately Satisfactory | 2024-11-26 |
Procurement | Moderately Satisfactory | 2024-11-26 |
Monitoring and Evaluation | Moderately Satisfactory | 2024-11-26 |
Overall Implementation Progress (IP) | Moderately Unsatisfactory | 2024-11-26 |
Financial Management | Moderately Satisfactory | 2024-11-26 |
Monitoring and Evaluation | Moderately Satisfactory | 2024-11-26 |
Project Management | Moderately Satisfactory | 2024-11-26 |
Progress towards achievement of PDO | Moderately Satisfactory | 2024-11-26 |
Procurement | Satisfactory | 2024-11-26 |
Project Management | Moderately Satisfactory | 2024-11-26 |
Overall Implementation Progress (IP) | Moderately Unsatisfactory | 2024-11-26 |
Financial Management | Moderately Satisfactory | 2024-11-26 |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
People with enhanced protection to flood risk | Value | 0.00 | 0.00 | 1800000.00 |
Date | March 31, 2023 | August 16, 2023 | December 31, 2027 | |
Comment |
People regaining access to at least one essential service | Value | 0.00 | 0.00 | 1500000.00 |
Date | February 10, 2023 | August 16, 2023 | December 31, 2028 | |
Comment |
Households with improved livelihoods | Value | 0.00 | 0.00 | 80000.00 |
Date | March 31, 2023 | August 16, 2023 | December 31, 2028 | |
Comment |
of which are females | Value | 0.00 | 0.00 | 0.00 |
Date | ||||
Comment |
Of which female-headed households and households with vulnerable women | Value | 0.00 | 0.00 | 0.00 |
Date | ||||
Comment |
of which are females | Value | 0.00 | 0.00 | 0.00 |
Date | ||||
Comment |
Increase in weather forecast lead time of PMD | Value | 3.00 | 0.00 | 5.00 |
Date | March 31, 2023 | August 16, 2023 | December 31, 2028 | |
Comment |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Land area benefitting from restored irrigation systems | Value | 0.00 | 0.00 | 50000.00 |
Date | March 31, 2023 | August 16, 2023 | December 31, 2027 | |
Comment |
Housing units restored/reconstructed | Value | 0.00 | 0.00 | 35100.00 |
Date | March 31, 2023 | August 16, 2023 | December 31, 2027 | |
Comment |
Watershed area under climate-resilient practices | Value | 0.00 | 0.00 | 20000.00 |
Date | March 31, 2023 | August 16, 2023 | December 31, 2027 | |
Comment |
Weather radars installed and operationalized | Value | 0.00 | 0.00 | 4.00 |
Date | March 31, 2023 | August 16, 2023 | December 31, 2027 | |
Comment |
Citizens' Engagement Strategy developed and rolled out | Value | Citizens' Engagement Strategy not developed. | in progress | Citizens' Engagement Strategy developed and rolled |
Date | March 6, 2023 | August 16, 2023 | December 31, 2028 | |
Comment |
Community flood resilience plans prepared | Value | 0.00 | 0.00 | 20.00 |
Date | April 14, 2023 | August 16, 2023 | December 31, 2028 | |
Comment |
Land area with improved protection through rehabilitated flood protection infrastructure | Value | 0.00 | 0.00 | 50000.00 |
Date | March 31, 2023 | August 16, 2023 | December 31, 2027 | |
Comment |
Households receiving livelihood support | Value | 0.00 | 0.00 | 80000.00 |
Date | March 31, 2023 | August 16, 2023 | December 31, 2028 | |
Comment |
Automatic Weather Stations (AWS) installed and operationalized | Value | 0.00 | 0.00 | 300.00 |
Date | March 31, 2023 | August 16, 2023 | December 31, 2028 | |
Comment |
Registered grievances satisfactorily resolved in line with the GRM | Value | 0.00 | 0.00 | 100.00 |
Date | April 17, 2023 | August 16, 2023 | December 31, 2028 | |
Comment |
River basin planning studies | Value | 0.00 | 0.00 | 3.00 |
Date | April 14, 2023 | August 16, 2023 | December 31, 2028 | |
Comment |
of which female headed households and households with vulnerable women | Value | 0.00 | 0.00 | 0.00 |
Date | ||||
Comment |
Length of roads rehabilitated | Value | 0.00 | 0.00 | 20.00 |
Date | March 31, 2023 | August 16, 2023 | December 31, 2028 | |
Comment |
Hydrological modelling based early warning system established for hill torrents in Balochistan | Value | No | No | Yes |
Date | March 31, 2023 | August 16, 2023 | December 31, 2028 | |
Comment |
Water supply schemes rehabilitated | Value | 0.00 | 0.00 | 40.00 |
Date | March 31, 2023 | August 16, 2023 | December 31, 2028 | |
Comment |
Restoration of small community facilities | Value | 0.00 | 0.00 | 40.00 |
Date | March 31, 2023 | August 16, 2023 | December 31, 2028 | |
Comment |