Integrated Flood Resilience and Adaptation Project

Abstract*

The development objective of the Integrated Flood Resilience and Adaptation Project for Pakistan is to improve livelihoods and essential services and enhance flood risk protection in selected communities affected by the 2022 floods. The project comprises of six components. The first component, community infrastructure rehabilitation will finance the rehabilitation of priority community infrastructure damaged by floods, including irrigation and flood...

* The project abstract is drawn from the PAD, SAR or PGD and may not accurately reflect the project's current nature

Show More

Development Objective

The project development objective (PDO) is to improve livelihoods and essential services and enhance flood risk protection in selected communities affected by the 2022 floods.

Key Details

Project Details

  • P180323

  • Active

  • Kamran Akbar , Carlo Amadei

  • Islamic Republic of Pakistan

  • Pakistan

  • April 21, 2023

  • (as of board presentation)

    May 25, 2023

  • July 20, 2023

  • US$ 400.00 million

  • Ministry of Planning, Development and Special Initiatives,Irrigation Department, Province of Balochistan,Planning and Development Department, Province of Balochistan

  • South Asia

  • 2023

  • US$ 213.00 million

  • N/A

  • January 25, 2024

  • December 31, 2028

  • Yes

  • BANK APPROVED

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
IDA Credit 213.00

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment N/A
IDA Commitment 213.00
IBRD + IDA Commitment 213.00
Lending Instrument
Grant Amount N/A
Total Project Cost** 400.00

Summary Status of World Bank Financing (US$ Millions) as of March 31, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of March 31, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)
Aug 1, 2024 IDA-73330 Int Charges 54,427.51
Mar 29, 2024 IDA-73330 Loan Disb 1,784,357.10
May 7, 2024 IDA-73330 Loan Disb 1,035,766.30
Aug 1, 2024 IDA-73330 Int Charges 54,427.51
May 25, 2023 IDA-73330 Loan Commitment 213,000,000.00
Mar 5, 2024 IDA-73330 Loan Disb 10,573,011.00
May 10, 2024 IDA-73330 Loan Disb 8,989,053.00

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Progress towards achievement of PDO Moderately Satisfactory 2024-11-26
Procurement Moderately Satisfactory 2024-11-26
Monitoring and Evaluation Moderately Satisfactory 2024-11-26
Overall Implementation Progress (IP) Moderately Unsatisfactory 2024-11-26
Financial Management Moderately Satisfactory 2024-11-26
Monitoring and Evaluation Moderately Satisfactory 2024-11-26
Project Management Moderately Satisfactory 2024-11-26
Progress towards achievement of PDO Moderately Satisfactory 2024-11-26
Procurement Satisfactory 2024-11-26
Project Management Moderately Satisfactory 2024-11-26
Overall Implementation Progress (IP) Moderately Unsatisfactory 2024-11-26
Financial Management Moderately Satisfactory 2024-11-26

COMPLETION RATINGS

No data available.

INDEPENDENT EVALUATION RATINGS

No data available.

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • People with enhanced protection to flood riskValue0.000.001800000.00
    DateMarch 31, 2023August 16, 2023December 31, 2027
    Comment
  • People regaining access to at least one essential serviceValue0.000.001500000.00
    DateFebruary 10, 2023August 16, 2023December 31, 2028
    Comment
  • Households with improved livelihoodsValue0.000.0080000.00
    DateMarch 31, 2023August 16, 2023December 31, 2028
    Comment
  • of which are femalesValue0.000.000.00
    Date
    Comment
  • Of which female-headed households and households with vulnerable womenValue0.000.000.00
    Date
    Comment
  • of which are femalesValue0.000.000.00
    Date
    Comment
  • Increase in weather forecast lead time of PMDValue3.000.005.00
    DateMarch 31, 2023August 16, 2023December 31, 2028
    Comment

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • Land area benefitting from restored irrigation systemsValue0.000.0050000.00
    DateMarch 31, 2023August 16, 2023December 31, 2027
    Comment
  • Housing units restored/reconstructedValue0.000.0035100.00
    DateMarch 31, 2023August 16, 2023December 31, 2027
    Comment
  • Watershed area under climate-resilient practicesValue0.000.0020000.00
    DateMarch 31, 2023August 16, 2023December 31, 2027
    Comment
  • Weather radars installed and operationalizedValue0.000.004.00
    DateMarch 31, 2023August 16, 2023December 31, 2027
    Comment
  • Citizens' Engagement Strategy developed and rolled outValueCitizens' Engagement Strategy not developed.in progressCitizens' Engagement Strategy developed and rolled
    DateMarch 6, 2023August 16, 2023December 31, 2028
    Comment
  • Community flood resilience plans preparedValue0.000.0020.00
    DateApril 14, 2023August 16, 2023December 31, 2028
    Comment
  • Land area with improved protection through rehabilitated flood protection infrastructureValue0.000.0050000.00
    DateMarch 31, 2023August 16, 2023December 31, 2027
    Comment
  • Households receiving livelihood supportValue0.000.0080000.00
    DateMarch 31, 2023August 16, 2023December 31, 2028
    Comment
  • Automatic Weather Stations (AWS) installed and operationalizedValue0.000.00300.00
    DateMarch 31, 2023August 16, 2023December 31, 2028
    Comment
  • Registered grievances satisfactorily resolved in line with the GRMValue0.000.00100.00
    DateApril 17, 2023August 16, 2023December 31, 2028
    Comment
  • River basin planning studiesValue0.000.003.00
    DateApril 14, 2023August 16, 2023December 31, 2028
    Comment
  • of which female headed households and households with vulnerable womenValue0.000.000.00
    Date
    Comment
  • Length of roads rehabilitatedValue0.000.0020.00
    DateMarch 31, 2023August 16, 2023December 31, 2028
    Comment
  • Hydrological modelling based early warning system established for hill torrents in BalochistanValueNoNoYes
    DateMarch 31, 2023August 16, 2023December 31, 2028
    Comment
  • Water supply schemes rehabilitatedValue0.000.0040.00
    DateMarch 31, 2023August 16, 2023December 31, 2028
    Comment
  • Restoration of small community facilitiesValue0.000.0040.00
    DateMarch 31, 2023August 16, 2023December 31, 2028
    Comment