Financier | Commitments |
---|---|
Trust Funds | 247.00 |
P180332
Active
Sandu Ghidirim , Koji Nishida , Silvia Martinez Romero
Ukraine
January 2, 2023
(as of board presentation)
April 11, 2023
August 3, 2023
US$ 450.00 million
Ministry of Energy,Ukrenergo
2023
US$ 247.00 million
N/A
January 17, 2024
April 30, 2025
Yes
BANK APPROVED
Financier | Commitments |
---|---|
Trust Funds | 247.00 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | N/A |
IDA Commitment | N/A |
IBRD + IDA Commitment | N/A |
Lending Instrument | |
---|---|
Grant Amount | 247.00 |
Total Project Cost** | 450.00 |
Name | Review | Date |
---|---|---|
Procurement | Satisfactory | 2024-08-07 |
Financial Management | Satisfactory | 2024-08-07 |
Overall Implementation Progress (IP) | Moderately Satisfactory | 2024-08-07 |
Progress towards achievement of PDO | Moderately Satisfactory | 2024-08-07 |
Project Management | Satisfactory | 2024-08-07 |
Monitoring and Evaluation | Satisfactory | 2024-08-07 |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Number of heating equipment delivered and installed or operational | Value | 0.00 | 0.00 | 50.00 |
Date | November 28, 2022 | July 28, 2023 | December 31, 2024 | |
Comment |
Number of equipment for the transmission system operator delivered and installed or operational | Value | 0.00 | 0.00 | 22.00 |
Date | November 28, 2022 | July 28, 2023 | December 31, 2024 | |
Comment |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Operational transformation capacity provided under the project | Value | 0.00 | 0.00 | 2000000.00 |
Date | December 24, 2022 | July 28, 2023 | December 31, 2024 | |
Comment |
Operational heat-only-boiler capacity installed under the project | Value | 0.00 | 0.00 | 100.00 |
Date | November 28, 2022 | July 28, 2023 | December 31, 2024 | |
Comment |
Technical consultant hired | Value | No | No | Yes |
Date | November 28, 2022 | July 28, 2023 | July 31, 2023 | |
Comment |