Skip to Main Navigation

Restoration Project of Winterization and Energy Resources

Abstract*

The financing for Re-PoWER was approved on April 11, 2023, under the innovative framework approach aimed to support Ukraine addressing the ongoing emergency caused by the attacks on its energy infrastructure, with a scope of support that is informed by both available and future financing over the immediate- and short-term. The project development objective (PDO) is to enable the restoration of essential energy services in Ukraine. The project has...

* The project abstract is drawn from the PAD, SAR or PGD and may not accurately reflect the project's current nature

Show More

Development Objective

The project development objective (PDO) is to enable the restoration of essential energy services in Ukraine

Key Details

Project Details

  • P180332

  • Active

  • Sandu Ghidirim , Koji Nishida , Silvia Martinez Romero

  • Ukraine

  • Ukraine

  • January 2, 2023

  • (as of board presentation)

    April 11, 2023

  • August 3, 2023

  • US$ 450.00 million

  • Ministry of Energy,Ukrenergo

  • Europe and Central Asia

  • 2023

  • US$ 247.00 million

  • N/A

  • January 17, 2024

  • April 30, 2025

  • Yes

  • BANK APPROVED

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
Trust Funds 247.00

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment N/A
IDA Commitment N/A
IBRD + IDA Commitment N/A
Lending Instrument
Grant Amount 247.00
Total Project Cost** 450.00

Summary Status of World Bank Financing (US$ Millions) as of February 28, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of February 28, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Procurement Satisfactory 2024-08-07
Financial Management Satisfactory 2024-08-07
Overall Implementation Progress (IP) Moderately Satisfactory 2024-08-07
Progress towards achievement of PDO Moderately Satisfactory 2024-08-07
Project Management Satisfactory 2024-08-07
Monitoring and Evaluation Satisfactory 2024-08-07

COMPLETION RATINGS

No data available.

INDEPENDENT EVALUATION RATINGS

No data available.

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • Number of heating equipment delivered and installed or operationalValue0.000.0050.00
    DateNovember 28, 2022July 28, 2023December 31, 2024
    Comment
  • Number of equipment for the transmission system operator delivered and installed or operationalValue0.000.0022.00
    DateNovember 28, 2022July 28, 2023December 31, 2024
    Comment

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • Operational transformation capacity provided under the projectValue0.000.002000000.00
    DateDecember 24, 2022July 28, 2023December 31, 2024
    Comment
  • Operational heat-only-boiler capacity installed under the projectValue0.000.00100.00
    DateNovember 28, 2022July 28, 2023December 31, 2024
    Comment
  • Technical consultant hiredValueNoNoYes
    DateNovember 28, 2022July 28, 2023July 31, 2023
    Comment