Kenya Green and Resilient Expansion of Energy (GREEN) Program Phase 2 Project

Abstract*

1. The Government of Kenya’s goal of universal access to clean, adequate, affordable, and reliable electricity is critically dependent on a robust transmission system to connect the main generation sources and bulk collection substation (geothermal, hydro and wind) in the central rift valley and eastern part of the country to the major load centers and to allow for greater connectivity to the regional hydropower resources. Particularly, the load centers...

* The project abstract is drawn from the PAD, SAR or PGD and may not accurately reflect the project's current nature

Show More

Development Objective

To increase the capacity of Kenya Power System for energy trade and renewable energy integration.

Key Details

Project Details

  • P180465

  • Active

  • Grace Nyaguthii , Jukka-Pekka Strand

  • Republic of Kenya

  • Kenya

  • August 30, 2023

  • (as of board presentation)

    December 26, 2023

  • January 9, 2025

  • US$ 178.50 million

  • Kenya Electricity Generating Company PLC (KenGen),Ministry of Energy & Petroleum (MoEP),Kenya Electricity Transmission Company Limited (KETRACO)

  • Eastern and Southern Africa

  • 2024

  • US$ 202.00 million

  • N/A

  • Moderate

  • June 30, 2029

  • Yes

  • BANK APPROVED

  • July 19, 2023

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
IDA Credit 153.50
Green Climate Fund 48.50

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment N/A
IDA Commitment 153.50
IBRD + IDA Commitment 153.50
Lending Instrument
Grant Amount 48.50
Total Project Cost** 178.50

Summary Status of World Bank Financing (US$ Millions) as of April 30, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of April 30, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)
Dec 26, 2023 IDA-74910 Loan Commitment 153,500,000.00
Dec 26, 2023 TF-C3892 Loan Commitment 45,000,000.00

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Progress towards achievement of PDO Moderately Satisfactory 2024-11-26
Procurement Satisfactory 2024-11-26
Project Management Satisfactory 2024-11-26
Financial Management Satisfactory 2024-11-26
Monitoring and Evaluation Satisfactory 2024-11-26
Overall Implementation Progress (IP) Moderately Satisfactory 2024-11-26

COMPLETION RATINGS

No data available.

INDEPENDENT EVALUATION RATINGS

No data available.

Results Framework