Liberia Electricity Sector Strengthening and Access Project (LESSAP) Phase 2

Abstract*

The investments proposed under the second phase of the LESSAP MPA will help address the poor operational and commercial performance of LEC leading to a financial turnaround of LEC as well as the low access to electricity to allow for achieving universal access to electricity within a reasonable timeframe. These include rehabilitation and expansion of the electricity infrastructure and systems, enhancement of LEC financial performance, off-grid electrification...

* The project abstract is drawn from the PAD, SAR or PGD and may not accurately reflect the project's current nature

Show More

Development Objective

The PDO is to expand the access to electricity services and enhance the operational performance of the Liberia Electricity Corporation (LEC).

Key Details

Project Details

  • P180498

  • Active

  • Mohammad Saqib , Omar Sherif

  • Republic of Liberia

  • Liberia

  • May 14, 2024

  • (as of board presentation)

    June 24, 2024

  • December 10, 2024

  • US$ 0.00 million

  • Liberia Electricity Corporation,Rural and Renewable Energy Agency

  • Western and Central Africa

  • 2024

  • US$ 50.00 million

  • N/A

  • June 24, 2024

  • June 30, 2029

  • Yes

  • BANK APPROVED

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
IDA Credit 45.00
Energy Sector Management Assistance Program 5.00

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment N/A
IDA Commitment 45.00
IBRD + IDA Commitment 45.00
Lending Instrument
Grant Amount 5.00
Total Project Cost** N/A

Summary Status of World Bank Financing (US$ Millions) as of March 31, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of March 31, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)
Jun 24, 2024 IDA-76120 Loan Commitment 45,000,000.00

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Monitoring and Evaluation Satisfactory 2024-10-28
Overall Implementation Progress (IP) Satisfactory 2024-10-28
Progress towards achievement of PDO Satisfactory 2024-10-28
Procurement Satisfactory 2024-10-28
Project Management Satisfactory 2024-10-28
Financial Management Satisfactory 2024-10-28

COMPLETION RATINGS

No data available.

INDEPENDENT EVALUATION RATINGS

No data available.

Results Framework

No data available.