Financier | Commitments |
---|---|
International Bank for Reconstruction and Development | 100.00 |
P180587
Closed
Sanja Madzarevic-Sujster
The Republic of North Macedonia
September 19, 2023
(as of board presentation)
December 15, 2023
December 18, 2023
US$ 0.00 million
Ministry of Finance
2024
US$ 100.00 million
N/A
May 16, 2023
June 30, 2024
BANK APPROVED
Financier | Commitments |
---|---|
International Bank for Reconstruction and Development | 100.00 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | 100.00 |
IDA Commitment | N/A |
IBRD + IDA Commitment | 100.00 |
Lending Instrument | |
---|---|
Grant Amount | N/A |
Total Project Cost** | N/A |
Period | Financier | Transaction Type | Amount (US$) |
---|---|---|---|
Dec 15, 2023 | IBRD-96230 | Loan Commitment | 100,000,000.00 |
Jun 15, 2024 | IBRD-96230 | Int Charges | 2,148,891.00 |
Dec 22, 2023 | IBRD-96230 | Loan Disb | 103,165,320.00 |
Dec 18, 2023 | IBRD-96230 | Loan Disb | 255,874.69 |
Dec 18, 2023 | IBRD-96230 | Fee Charges | 255,874.69 |
Name | Review | Date |
---|---|---|
Monitoring and Evaluation | Satisfactory | 2024-10-31 |
Progress towards achievement of PDO | Moderately Satisfactory | 2024-10-31 |
Overall Implementation Progress (IP) | Moderately Satisfactory | 2024-10-31 |
Program Management | Satisfactory | 2024-10-31 |