Türkiye Earthquake Recovery and Reconstruction Project

Abstract*

The development objective of the Earthquake Recovery and Reconstruction Project for Türkiye is to restore access to essential municipal and health services and resilient housing in selected provinces affected by the February 2023 earthquakes in Türkiye. The project comprises of four components. The first component, restoration of municipal infrastructure and services will finance civil works (including demolition as applicable), goods, consulting...

* The project abstract is drawn from the PAD, SAR or PGD and may not accurately reflect the project's current nature

Show More

Development Objective

The Project Development Objective is to restore access to essential municipal and health services and resilient housing in selected provinces affected by the February 2023 earthquakes in Türkiye.

Key Details

Project Details

  • P180849

  • Active

  • Alanna Simpson , Sema Sumer, Salih Erdurmus, Yondela Silimela

  • Republic of Türkiye

  • Turkiye

  • May 9, 2023

  • (as of board presentation)

    June 27, 2023

  • October 26, 2023

  • US$ 1000.00 million

  • Iller Bankasi Anonim Sirketi,Ministry of Health,Ministry of Environment, Urbanization, and Climate Change

  • Europe and Central Asia

  • 2023

  • US$ 1000.00 million

  • N/A

  • April 16, 2024

  • June 30, 2028

  • Yes

  • BANK APPROVED

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
International Bank for Reconstruction and Development 1000.00

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment 1000.00
IDA Commitment N/A
IBRD + IDA Commitment 1000.00
Lending Instrument
Grant Amount N/A
Total Project Cost** 1000.00

Summary Status of World Bank Financing (US$ Millions) as of February 28, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of February 28, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)
Apr 15, 2024 IBRD-95800 Int Charges 716,514.56
Apr 15, 2024 IBRD-95800 Int Charges 1,070,482.40
Apr 18, 2024 IBRD-95800 Loan Disb 160,904.30
Apr 18, 2024 IBRD-95800 Loan Disb 160,904.30
Apr 18, 2024 IBRD-95800 Loan Disb 160,904.30
Apr 5, 2024 IBRD-95800 Loan Disb 17,196,422.00
Apr 19, 2024 IBRD-95800 Loan Disb 160,172.98
May 8, 2024 IBRD-95800 Loan Disb 159,806.73
May 8, 2024 IBRD-95800 Loan Disb 159,806.73
Jun 27, 2023 IBRD-95800 Loan Commitment 1,000,000,000.00
Jun 24, 2024 IBRD-95800 Loan Disb 29,692,622.00
Jun 7, 2024 IBRD-95800 Loan Disb 160,242.81
Jun 27, 2024 IBRD-95800 Loan Disb 3,382,929.20
May 3, 2024 IBRD-95800 Loan Disb 6,639,681.50
Jun 7, 2024 IBRD-95800 Loan Disb 160,242.81
Jul 11, 2024 IBRD-95800 Loan Disb 160,480.78
Jul 11, 2024 IBRD-95800 Loan Disb 160,480.77
Jun 6, 2024 IBRD-95800 Loan Disb 23,927,200.00
Feb 2, 2024 IBRD-95800 Loan Disb 8,447,438.00
Feb 2, 2024 IBRD-95800 Loan Disb 8,707,200.00
Aug 13, 2024 IBRD-95800 Loan Disb 160,021.98
Aug 13, 2024 IBRD-95800 Loan Disb 160,021.98
Jun 10, 2024 IBRD-95800 Loan Disb 48,316,500.00
Nov 6, 2023 IBRD-95800 Fee Charges 2,447,424.00
Nov 30, 2023 IBRD-95800 Loan Disb 21,832,000.00
Jun 11, 2024 IBRD-95800 Loan Disb 16,111,500.00
Dec 27, 2023 IBRD-95800 Loan Disb 11,059,000.00

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Project Management Satisfactory 2025-02-25
Overall Implementation Progress (IP) Satisfactory 2025-02-25
Progress towards achievement of PDO Satisfactory 2025-02-25
Monitoring and Evaluation Satisfactory 2025-02-25
Procurement Satisfactory 2025-02-25
Progress towards achievement of PDO Satisfactory 2025-02-25
Procurement Satisfactory 2025-02-25
Financial Management Satisfactory 2025-02-25
Monitoring and Evaluation Satisfactory 2025-02-25
Overall Implementation Progress (IP) Satisfactory 2025-02-25
Project Management Satisfactory 2025-02-25
Financial Management Satisfactory 2025-02-25

COMPLETION RATINGS

No data available.

INDEPENDENT EVALUATION RATINGS

No data available.

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • People provided with restored access to municipal infrastructure and services with improved climate and disaster resilience under the ProjectValue0.000.006200.00
    DateJune 29, 2023March 13, 2024September 29, 2028
    Comment
  • People provided with access to restored essential health services under the ProjectValue0.000.332528.00
    DateJune 30, 2023March 15, 2024September 29, 2028
    Comment
  • People benefiting from disaster and climate resilient, and energy efficient rural housing and village infrastructure reconstructed under the Project.Value0.000.007000.00
    DateJune 30, 2023March 13, 2024June 30, 2027
    Comment
  • Of which womenValue0.000.0049.70
    Date
    Comment
  • Of which womenValue0.000.0049.70
    Date
    Comment
  • Of which womenValue0.000.0049.70
    Date
    Comment

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • Pregnant women receiving antenatal care from a qualified providerValue62.000.0070.00
    DateJune 30, 2023September 15, 2023September 29, 2028
    Comment
  • Beneficiaries who report that the Project has established effective engagement processesValue0.000.0090.00
    DateJune 30, 2023March 13, 2024September 29, 2028
    Comment
  • Of which womenValue0.000.0025.00
    Date
    Comment
  • Municipal water supply, sewerage, storm water, and/or road network infrastructure rehabilitated or reconstructed with improved resilienceValue0.000.00600.00
    DateJune 30, 2023March 13, 2024September 29, 2028
    Comment
  • People benefiting from primary care mobile health units within the scope of the ProjectValue0.000.001800.00
    DateJune 30, 2023September 15, 2023September 29, 2028
    Comment
  • Rural residential and livelihood units reconstructed in compliance with climate/disaster resilient and energy efficient design standardsValue0.000.002000.00
    DateJune 30, 2023March 13, 2024September 29, 2028
    Comment
  • Grievances addressed by ILBANK in accordance with the stipulated service standardsValue0.000.0095.00
    DateJune 30, 2023March 13, 2024September 29, 2028
    Comment
  • Municipal water and wastewater treatment and solid waste facilities and/or bridges and junctions rehabilitated or reconstructed with improved resilienceValue0.000.0020.00
    DateJune 30, 2023March 13, 2024September 29, 2028
    Comment
  • Water samples analyzed in the field by the mobile water analysis laboratoryValue0.000.003200.00
    DateJune 30, 2023March 13, 2024September 29, 2028
    Comment
  • Villages benefiting from climate and disaster resilient infrastructure rehabilitation or reconstructionValue0.000.0045.00
    DateJune 30, 2023March 13, 2024September 29, 2028
    Comment
  • Grievances addressed by MoH in accordance with the stipulated service standardsValue0.000.0095.00
    DateJune 30, 2023March 13, 2024September 29, 2028
    Comment
  • Local authorities provided with municipal service vehicles and/ or equipmentValue0.000.0060.00
    DateJune 30, 2023March 13, 2024September 29, 2028
    Comment
  • Patients benefiting from Physical Therapy Rehabilitation (PTR) centersValue0.000.0050000.00
    DateJune 30, 2023September 15, 2023June 30, 2028
    Comment
  • AFAD and MoEUCC post disaster housing support processes, systems or programs reviewed and improvedValueNoYesYes
    DateJune 30, 2023March 13, 2024September 29, 2028
    Comment
  • Grievances addressed by MoEUCC in accordance with the stipulated service standardsValue0.000.0095.00
    DateJune 30, 2023March 13, 2024September 29, 2028
    Comment
  • Municipal service buildings (fire stations) repaired or reconstructed with climate/disaster resilient and energy efficient design standards and/or equipped with emergency response equipmentValue0.000.0020.00
    DateJune 30, 2023March 13, 2024September 29, 2028
    Comment