Financier | Commitments |
---|---|
IDA Credit | 56.57 |
International Bank for Reconstruction and Development | 1443.43 |
P181032
Closed
Xiaodong Wang , Surbhi Goyal, Dhruv Sharma
India
April 18, 2023
(as of board presentation)
June 29, 2023
November 28, 2023
US$ 0.00 million
Ministry of New and Renewable Energy
2023
US$ 1500.00 million
N/A
November 10, 2023
December 31, 2023
BANK APPROVED
Financier | Commitments |
---|---|
IDA Credit | 56.57 |
International Bank for Reconstruction and Development | 1443.43 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | 1443.43 |
IDA Commitment | 56.57 |
IBRD + IDA Commitment | 1500.00 |
Lending Instrument | |
---|---|
Grant Amount | N/A |
Total Project Cost** | N/A |
Period | Financier | Transaction Type | Amount (US$) |
---|---|---|---|
Dec 20, 2023 | IDA-73750 | Loan Disb | 56,428,576.00 |
Dec 20, 2023 | IBRD-95740 | Loan Disb | 1,439,821,440.00 |
Nov 28, 2023 | IBRD-95740 | Fee Charges | 3,608,575.00 |
Nov 28, 2023 | IBRD-95740 | Loan Disb | 3,608,575.00 |
Nov 28, 2023 | IDA-73750 | Fee Charges | 141,425.00 |
May 15, 2024 | IDA-73750 | Int Charges | 1,496,942.80 |
May 15, 2024 | IBRD-95740 | Int Charges | 38,195,724.00 |
Jun 29, 2023 | IDA-73750 | Loan Commitment | 56,570,000.00 |
Jun 29, 2023 | IBRD-95740 | Loan Commitment | 1,443,430,020.00 |
Nov 28, 2023 | IDA-73750 | Loan Disb | 141,425.00 |
Name | Review | Date |
---|---|---|
Program Management | Satisfactory | 2023-09-29 |
Progress towards achievement of PDO | Satisfactory | 2023-09-29 |
Monitoring and Evaluation | Satisfactory | 2023-09-29 |
Overall Implementation Progress (IP) | Satisfactory | 2023-09-29 |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Domestic electrolyzer manufacturing capacity incentivized | Value | 0.00 | 0.00 | 3.00 |
Date | June 30, 2023 | September 8, 2023 | June 30, 2026 | |
Comment |
Number of additional green hydrogen safety standards notified | Value | 0.00 | 0.00 | 10.00 |
Date | June 30, 2023 | September 8, 2023 | June 30, 2026 | |
Comment |
Share of renewable energy in power consumption | Value | 25.00 | 25.00 | 33.00 |
Date | June 30, 2023 | September 8, 2023 | June 30, 2026 | |
Comment |
Share of solar/wind with/through energy storage in total power consumption | Value | 0.00 | 0.00 | 2.00 |
Date | June 30, 2023 | September 8, 2023 | June 30, 2026 | |
Comment |
Additional bids for renewable energy capacity issued | Value | 0.00 | 0.00 | 75.00 |
Date | June 30, 2023 | September 8, 2023 | June 30, 2026 | |
Comment |
Greenhouse gas emissions avoided | Value | 0.00 | 0.00 | 40000000.00 |
Date | June 30, 2023 | September 8, 2023 | June 30, 2026 | |
Comment |
Offshore wind sites awarded | Value | 0.00 | 0.00 | 4.00 |
Date | June 30, 2023 | September 8, 2023 | June 30, 2026 | |
Comment |
Capacity for domestic manufacturing of high-efficiency solar photovoltaic cells and modules added | Value | 0.00 | 0.00 | 48.00 |
Date | June 30, 2023 | September 8, 2023 | June 30, 2026 | |
Comment |
Launch of national carbon market | Value | No | No | Yes |
Date | June 30, 2023 | September 8, 2023 | June 30, 2026 | |
Comment |
Increase in issuance of cumulative onshore green debt securities | Value | 0.00 | 0.00 | 30.00 |
Date | June 30, 2023 | September 8, 2023 | June 30, 2026 | |
Comment |
Sovereign green bonds issued | Value | 2.30 | 2.30 | 6.00 |
Date | June 30, 2023 | September 8, 2023 | June 30, 2026 | |
Comment |
Green hydrogen production capacity incentivized | Value | 0.00 | 0.00 | 3000000.00 |
Date | June 30, 2023 | September 8, 2023 | June 30, 2026 | |
Comment |