Financier | Commitments |
---|---|
Energy Sector Management Assistance Program | 2.00 |
IDA Credit | 14.00 |
Regional Program on Central Asia - Energy & Water Developmen | 2.60 |
P181086
Active
Maksudjon Safarov , Hazuki Terada
Kyrgyz Republic
May 19, 2023
(as of board presentation)
October 31, 2023
March 11, 2024
US$ 5.00 million
Ministry of Energy
2024
US$ 18.60 million
N/A
May 15, 2024
December 31, 2027
Yes
BANK APPROVED
Financier | Commitments |
---|---|
Energy Sector Management Assistance Program | 2.00 |
IDA Credit | 14.00 |
Regional Program on Central Asia - Energy & Water Developmen | 2.60 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | N/A |
IDA Commitment | 14.00 |
IBRD + IDA Commitment | 14.00 |
Lending Instrument | |
---|---|
Grant Amount | 4.60 |
Total Project Cost** | 5.00 |
Period | Financier | Transaction Type | Amount (US$) |
---|---|---|---|
Jul 11, 2024 | IDA-76010 | Loan Commitment | 11,000,000.00 |
Oct 31, 2023 | IDA-74220 | Loan Commitment | 3,000,000.00 |
Name | Review | Date |
---|---|---|
Progress towards achievement of PDO | Satisfactory | 2025-03-11 |
Monitoring and Evaluation | Satisfactory | 2025-03-11 |
Overall Implementation Progress (IP) | Satisfactory | 2025-03-11 |
Procurement | Satisfactory | 2025-03-11 |
Project Management | Satisfactory | 2025-03-11 |
Financial Management | Moderately Satisfactory | 2025-03-11 |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
The environmental and social instruments of the Kambarata 1 HPP comply with the World Bank’s requirements and international standards | Value | No | No | Yes |
Date | May 10, 2023 | January 31, 2024 | December 31, 2027 | |
Comment |
The Government adopts a macroeconomically sustainable and financially viable plan for Kambarata 1 HPP project | Value | No | No | Yes |
Date | May 10, 2023 | January 31, 2024 | December 31, 2027 | |
Comment |
An updated technical feasibility study is completed with quality acceptable to the panels of experts and the World Bank | Value | No | No | Yes |
Date | May 10, 2023 | January 31, 2024 | December 31, 2027 | |
Comment |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
International consultant for feasibility updating is procured | Value | No | No | Yes |
Date | May 10, 2023 | January 31, 2024 | December 31, 2027 | |
Comment |
International consultant is procured to update/prepare safeguards instruments | Value | No | No | Yes |
Date | May 10, 2023 | January 31, 2024 | December 31, 2027 | |
Comment |
Consultants are employed to carry our additional financial assessments and studies and advise on a creditable financing plan | Value | No | No | Yes |
Date | May 10, 2023 | January 31, 2024 | December 31, 2027 | |
Comment |
Increase in the number of women taking on permanent jobs at EPP at technical and managerial levels | Value | 10.00 | 0.00 | 15.00 |
Date | May 10, 2023 | January 31, 2024 | December 31, 2027 | |
Comment |
A panel of experts for dam safety is employed | Value | No | No | Yes |
Date | May 10, 2023 | January 31, 2024 | December 31, 2027 | |
Comment |
A panel of environmental and social experts is established to provide independent advice and guidance | Value | No | No | Yes |
Date | May 10, 2023 | January 31, 2024 | December 31, 2027 | |
Comment |
Workshops and training are conducted to share knowledge/experience on large hydropower financing and contractual arrangements | Value | 0.00 | 0.00 | 5.00 |
Date | May 10, 2023 | January 31, 2024 | December 31, 2027 | |
Comment |
Complaints received which are responded and resolved within the specified timeframe | Value | 70.00 | 0.00 | 90.00 |
Date | May 10, 2023 | January 31, 2024 | December 31, 2027 | |
Comment |
Potential generation capacity of hydropower to be added based on results of the project | Value | 0.00 | 0.00 | 1860.00 |
Date | May 10, 2023 | January 31, 2024 | December 31, 2027 | |
Comment |
Number of EPP, MoE and other stakeholder staff trained | Value | 0.00 | 0.00 | 90.00 |
Date | May 10, 2023 | January 31, 2024 | December 31, 2027 | |
Comment |
A benefit sharing mechanism for Kambarata 1 is developed | Value | No | No | Yes |
Date | May 10, 2023 | January 31, 2024 | December 31, 2027 | |
Comment |