Financier | Commitments |
---|---|
International Bank for Reconstruction and Development | 28.50 |
Lebanon Financing Facility | 5.50 |
P181155
Active
Rima Koteiche
The Lebanese Republic
June 12, 2023
(as of board presentation)
February 14, 2024
October 15, 2024
US$ 50.00 million
Minister of Finance
2024
US$ 34.00 million
N/A
May 22, 2023
March 31, 2027
Yes
BANK APPROVED
Financier | Commitments |
---|---|
International Bank for Reconstruction and Development | 28.50 |
Lebanon Financing Facility | 5.50 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | 28.50 |
IDA Commitment | N/A |
IBRD + IDA Commitment | 28.50 |
Lending Instrument | |
---|---|
Grant Amount | 5.50 |
Total Project Cost** | 50.00 |
Period | Financier | Transaction Type | Amount (US$) |
---|---|---|---|
Feb 14, 2024 | IBRD-96440 | Loan Commitment | 28,500,000.00 |
Name | Review | Date |
---|---|---|
Progress towards achievement of PDO | Moderately Satisfactory | 2024-12-06 |
Financial Management | Moderately Satisfactory | 2024-12-06 |
Monitoring and Evaluation | Moderately Satisfactory | 2024-12-06 |
Overall Implementation Progress (IP) | Moderately Satisfactory | 2024-12-06 |
Procurement | Moderately Satisfactory | 2024-12-06 |
Project Management | Moderately Satisfactory | 2024-12-06 |