Financier | Commitments |
---|---|
IDA Credit | 187.00 |
P181166
Active
Eric Lancelot , Rohan Shah
The Republic of Honduras
December 23, 2023
(as of board presentation)
December 17, 2024
N/A
US$ 150.00 million
Secretariat of Infrastructure and Transport (SIT)
2025
US$ 187.00 million
N/A
High
December 31, 2031
TBD
BANK APPROVED
June 2, 2023
Financier | Commitments |
---|---|
IDA Credit | 187.00 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | N/A |
IDA Commitment | 187.00 |
IBRD + IDA Commitment | 187.00 |
Lending Instrument | |
---|---|
Grant Amount | N/A |
Total Project Cost** | 150.00 |
Name | Review | Date |
---|---|---|
Progress towards achievement of PDO | Satisfactory | 2025-03-17 |
Financial Management | Satisfactory | 2025-03-17 |
Monitoring and Evaluation | Satisfactory | 2025-03-17 |
Overall Implementation Progress (IP) | Satisfactory | 2025-03-17 |
Procurement | Satisfactory | 2025-03-17 |
Project Management | Satisfactory | 2025-03-17 |