Uzbekistan Solar and Renewable Energy Storage Project

Abstract*

The development objective of the Solar and Renewable Energy Storage (USRES) Project for Uzbekistan is to increase private sector led renewable energy supply in Uzbekistan. The project comprises of one component, construction, and operation of a 250 MW solar power plant and 63 MW/126 MWh of battery energy storage system (BESS) by Abu Dhabi Future Energy Company PJSC - Masdar at Bukhara site and power purchase by the state-owned off-taker (NEGU) supported...

* The project abstract is drawn from the PAD, SAR or PGD and may not accurately reflect the project's current nature

Show More

Development Objective

The Project Development Objective (PDO) is to increase private sector led renewable energy supply in Uzbekistan.

Key Details

Project Details

  • P181434

  • Active

  • Bahodir Amonov , Philip Lam, Joern Huenteler

  • Ministry of Economy and Finance

  • Uzbekistan

  • March 31, 2021

  • (as of board presentation)

    January 3, 2024

  • N/A

  • US$ 435.00 million

  • National Electric Grid of Uzbekistan (NEGU) Joint Stock Company

  • Europe and Central Asia

  • 2024

  • US$ 0.00 million

  • N/A

  • December 19, 2024

  • December 31, 2025

  • BANK APPROVED

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
IBRD Guarantee 12.00

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment N/A
IDA Commitment N/A
IBRD + IDA Commitment N/A
Lending Instrument
Grant Amount N/A
Total Project Cost** 435.00

Summary Status of World Bank Financing (US$ Millions) as of March 31, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of March 31, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)
Jul 31, 2024 IBRD-G4120 Loan Cancel 2,747,430.00
Jan 3, 2024 IBRD-G4120 Loan Commitment 12,000,000.00

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Progress towards achievement of PDO Satisfactory 2024-06-24
Monitoring and Evaluation Satisfactory 2024-06-24
Overall Implementation Progress (IP) Satisfactory 2024-06-24
Project Management Satisfactory 2024-06-24
Procurement Satisfactory 2024-06-24
Financial Management Satisfactory 2024-06-24

COMPLETION RATINGS

No data available.

INDEPENDENT EVALUATION RATINGS

No data available.

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • Electricity supplied by the Solar PV plant into the grid (renewable/solar)Value0.000.00586000.00
    DateJune 19, 2024June 19, 2024December 31, 2025
    Comment
  • BESS capacity available to provide grid services and electricity backup into the gridValue0.000.0063.00
    DateJune 19, 2024June 19, 2024December 31, 2025
    Comment
  • Private capital mobilized (equity/debt)Value0.000.00132000000.00
    DateJune 19, 2024June 19, 2024December 31, 2025
    Comment
  • Greenhouse gas emissions avoidedValue0.000.0068359.00
    DateJune 19, 2024June 19, 2024December 31, 2025
    Comment

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • Physical implementation progress in solar PV plantValue0.000.00100.00
    DateJune 19, 2024June 19, 2024December 31, 2025
    Comment
  • Physical implementation progress in BESSValue0.000.00100.00
    DateJune 19, 2024June 19, 2024December 31, 2025
    Comment
  • PV plant commissioning completedValueNoNoYes
    DateJune 19, 2024June 19, 2024December 31, 2025
    Comment
  • BESS commissioning completedValueNoNoYes
    DateJune 19, 2024December 31, 2025December 31, 2025
    Comment