Financier | Commitments |
---|---|
IBRD Guarantee | 12.00 |
P181434
Active
Bahodir Amonov , Philip Lam, Joern Huenteler
Ministry of Economy and Finance
March 31, 2021
(as of board presentation)
January 3, 2024
N/A
US$ 435.00 million
National Electric Grid of Uzbekistan (NEGU) Joint Stock Company
2024
US$ 0.00 million
N/A
December 19, 2024
December 31, 2025
BANK APPROVED
Financier | Commitments |
---|---|
IBRD Guarantee | 12.00 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | N/A |
IDA Commitment | N/A |
IBRD + IDA Commitment | N/A |
Lending Instrument | |
---|---|
Grant Amount | N/A |
Total Project Cost** | 435.00 |
Period | Financier | Transaction Type | Amount (US$) |
---|---|---|---|
Jul 31, 2024 | IBRD-G4120 | Loan Cancel | 2,747,430.00 |
Jan 3, 2024 | IBRD-G4120 | Loan Commitment | 12,000,000.00 |
Name | Review | Date |
---|---|---|
Progress towards achievement of PDO | Satisfactory | 2024-06-24 |
Monitoring and Evaluation | Satisfactory | 2024-06-24 |
Overall Implementation Progress (IP) | Satisfactory | 2024-06-24 |
Project Management | Satisfactory | 2024-06-24 |
Procurement | Satisfactory | 2024-06-24 |
Financial Management | Satisfactory | 2024-06-24 |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Electricity supplied by the Solar PV plant into the grid (renewable/solar) | Value | 0.00 | 0.00 | 586000.00 |
Date | June 19, 2024 | June 19, 2024 | December 31, 2025 | |
Comment |
BESS capacity available to provide grid services and electricity backup into the grid | Value | 0.00 | 0.00 | 63.00 |
Date | June 19, 2024 | June 19, 2024 | December 31, 2025 | |
Comment |
Private capital mobilized (equity/debt) | Value | 0.00 | 0.00 | 132000000.00 |
Date | June 19, 2024 | June 19, 2024 | December 31, 2025 | |
Comment |
Greenhouse gas emissions avoided | Value | 0.00 | 0.00 | 68359.00 |
Date | June 19, 2024 | June 19, 2024 | December 31, 2025 | |
Comment |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Physical implementation progress in solar PV plant | Value | 0.00 | 0.00 | 100.00 |
Date | June 19, 2024 | June 19, 2024 | December 31, 2025 | |
Comment |
Physical implementation progress in BESS | Value | 0.00 | 0.00 | 100.00 |
Date | June 19, 2024 | June 19, 2024 | December 31, 2025 | |
Comment |
PV plant commissioning completed | Value | No | No | Yes |
Date | June 19, 2024 | June 19, 2024 | December 31, 2025 | |
Comment |
BESS commissioning completed | Value | No | No | Yes |
Date | June 19, 2024 | December 31, 2025 | December 31, 2025 | |
Comment |