Financier | Commitments |
---|---|
IDA Credit | 50.00 |
IDA Credit | 50.00 |
Borrower/Recipient | 27.00 |
Borrower/Recipient | 27.00 |
FRANCE: Govt. of [MOFA and AFD (C2D)] | 33.00 |
FRANCE: Govt. of [MOFA and AFD (C2D)] | 33.00 |
P181537
Active
Sabine Beddies , Fatou Dieng, Jonas Parby
GOVERNMENT OF SENEGAL,GOVERNMENT OF SENEGAL
December 21, 2023
(as of board presentation)
June 21, 2024
N/A
US$ 75.00 million
Municipal Development Agency,Municipal Development Agency
2024
US$ 83.00 million
N/A
N/A
December 31, 2026
No
BANK APPROVED
July 14, 2024
Financier | Commitments |
---|---|
IDA Credit | 50.00 |
IDA Credit | 50.00 |
Borrower/Recipient | 27.00 |
Borrower/Recipient | 27.00 |
FRANCE: Govt. of [MOFA and AFD (C2D)] | 33.00 |
FRANCE: Govt. of [MOFA and AFD (C2D)] | 33.00 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | N/A |
IDA Commitment | 50.00 |
IBRD + IDA Commitment | 50.00 |
Lending Instrument | |
---|---|
Grant Amount | 33.00 |
Total Project Cost** | 75.00 |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Modalities for repartition of State transfers FECT/ FDD to LGs for investment/ recurrent spending & repartition of LVATF reformed and applied in timely resource transfer to LGs | Value | Modalities for repartition of State transfers to L | DLR 1.5a Timely transfer before March 31 of said y | DLR 1.8a: Decree reforming the FECT Special window |
Date | January 8, 2018 | April 4, 2024 | December 31, 2026 | |
Comment |
Increase in local taxation revenues in the Principle Urban Center LGs | Value | 0.00 | 23.87 | 40.00 |
Date | January 8, 2018 | December 4, 2023 | June 30, 2024 | |
Comment |
State-financed intergovernmental capital and recurrent grants (FECT and FDD) to LGs (amount in billion of FCFA) | Value | 42.00 | 88.00 | 98.00 |
Date | January 8, 2018 | April 4, 2024 | December 31, 2026 | |
Comment |
Urban LGs that satisfied the annual Minimum Mandatory Conditions (MMC) | Value | 0.00 | 82.26 | 80.00 |
Date | January 8, 2018 | April 4, 2024 | December 31, 2026 | |
Comment |
Principal Urban Center LGs that have executed their annual investment plans (AIPs) on schedule in terms of expenditures | Value | 0.00 | 10.52 | 50.00 |
Date | January 8, 2018 | April 4, 2024 | December 31, 2026 | |
Comment |
Deployment of the National Determined Contribution (NDC) at the LG level | Value | No LG standards on implementation of Senegal's NDC | No LG standards on NDC implementation | DLR?8.8a: 30% of 124 PACASEN LGs have adopted a cl |
Date | April 5, 2024 | April 5, 2024 | December 31, 2026 | |
Comment |
Modalities for repartition of State transfers FECT/ FDD to LGs for investment/ recurrent spending & repartition of LVATF reformed and applied in timely resource transfer to LGs | Value | Modalities for repartition of State transfers to L | DLR 1.5a Timely transfer before March 31 of said y | DLR 1.8a: Decree reforming the FECT Special window |
Date | January 8, 2018 | April 4, 2024 | December 31, 2026 | |
Comment |
Increase in local taxation revenues in the Principle Urban Center LGs | Value | 0.00 | 23.87 | 40.00 |
Date | January 8, 2018 | December 4, 2023 | June 30, 2024 | |
Comment |
State-financed intergovernmental capital and recurrent grants (FECT and FDD) to LGs (amount in billion of FCFA) | Value | 42.00 | 88.00 | 98.00 |
Date | January 8, 2018 | April 4, 2024 | December 31, 2026 | |
Comment |
Urban LGs that satisfied the annual Minimum Mandatory Conditions (MMC) | Value | 0.00 | 82.26 | 80.00 |
Date | January 8, 2018 | April 4, 2024 | December 31, 2026 | |
Comment |
Principal Urban Center LGs that have executed their annual investment plans (AIPs) on schedule in terms of expenditures | Value | 0.00 | 10.52 | 50.00 |
Date | January 8, 2018 | April 4, 2024 | December 31, 2026 | |
Comment |
Deployment of the National Determined Contribution (NDC) at the LG level | Value | No LG standards on implementation of Senegal's NDC | No LG standards on NDC implementation | DLR?8.8a: 30% of 124 PACASEN LGs have adopted a cl |
Date | April 5, 2024 | April 5, 2024 | December 31, 2026 | |
Comment |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
1.1: Functional review of the Intergovernmental Transfer System | Value | No review of intergovernmental transfer system | Roll-out of Strategy for the sustainability of the | |
Date | January 8, 2018 | December 4, 2023 | December 31, 2026 | |
Comment |
2.1 Urban LGs having received at least 3 training modules (including 1 CC module) identified in their annual capacity development plans | Value | 0.00 | 74.00 | 100.00 |
Date | January 8, 2018 | December 4, 2023 | December 31, 2026 | |
Comment |
1.2: Urban LGs with a functioning Local Fiscal Commission | Value | 1.00 | 107.00 | 115.00 |
Date | January 8, 2018 | December 4, 2023 | June 30, 2024 | |
Comment |
2.2: Proportion of Urban LGs that received at least 80 percent of the Territorial Coaching support identified in their Annual Capacity Building Plans | Value | 0.00 | 86.29 | 95.00 |
Date | January 8, 2018 | December 4, 2023 | June 30, 2024 | |
Comment |
1.3: Reduction in time taken for payment of investment expenditures from the Program Special Account | Value | 5.00 | 2.00 | 2.00 |
Date | January 8, 2018 | December 4, 2023 | June 30, 2024 | |
Comment |
2.2: Information on fiscal transfers and LG performance in year N-1 is publicly accessible by March 31 in year N | Value | No | Yes | Yes |
Date | January 8, 2018 | December 4, 2023 | December 31, 2026 | |
Comment |
2.3: Principal Urban Center LGs that satisfied the annual Performance Indicators (PIs) | Value | 0.00 | 57.89 | 70.00 |
Date | January 8, 2018 | April 5, 2024 | December 31, 2026 | |
Comment |
2.4 Women at national level in leadership position developing the LG standards to deploy the National Determined Contribution (NDC)at the LG level | Value | 0.00 | 0.00 | 33.00 |
Date | April 5, 2024 | April 5, 2024 | December 31, 2026 | |
Comment |
1.2 Local property tax assessments in the Principal Urban Center LGs | Value | 39.00 | 39.00 | 49.00 |
Date | April 5, 2024 | April 5, 2024 | December 31, 2026 | |
Comment |
2.5 Urban LGs that received a minimum of coaching, incl on climate change, identified in their Annual Capacity Building Plans (Percentage) | Value | No climate change capacity building for LGs | No climate change capacity building for LGs | DLR 10.8.a: 90% of 124 PACASEN CTs have received a |
Date | April 4, 2024 | April 4, 2024 | December 31, 2026 | |
Comment |
1.1: Functional review of the Intergovernmental Transfer System | Value | No review of intergovernmental transfer system | Roll-out of Strategy for the sustainability of the | |
Date | January 8, 2018 | December 4, 2023 | December 31, 2026 | |
Comment |
2.1 Urban LGs having received at least 3 training modules (including 1 CC module) identified in their annual capacity development plans | Value | 0.00 | 74.00 | 100.00 |
Date | January 8, 2018 | December 4, 2023 | December 31, 2026 | |
Comment |
1.2: Urban LGs with a functioning Local Fiscal Commission | Value | 1.00 | 107.00 | 115.00 |
Date | January 8, 2018 | December 4, 2023 | June 30, 2024 | |
Comment |
2.2: Proportion of Urban LGs that received at least 80 percent of the Territorial Coaching support identified in their Annual Capacity Building Plans | Value | 0.00 | 86.29 | 95.00 |
Date | January 8, 2018 | December 4, 2023 | June 30, 2024 | |
Comment |
1.3: Reduction in time taken for payment of investment expenditures from the Program Special Account | Value | 5.00 | 2.00 | 2.00 |
Date | January 8, 2018 | December 4, 2023 | June 30, 2024 | |
Comment |
2.2: Information on fiscal transfers and LG performance in year N-1 is publicly accessible by March 31 in year N | Value | No | Yes | Yes |
Date | January 8, 2018 | December 4, 2023 | December 31, 2026 | |
Comment |
2.3: Principal Urban Center LGs that satisfied the annual Performance Indicators (PIs) | Value | 0.00 | 57.89 | 70.00 |
Date | January 8, 2018 | April 5, 2024 | December 31, 2026 | |
Comment |
2.4 Women at national level in leadership position developing the LG standards to deploy the National Determined Contribution (NDC)at the LG level | Value | 0.00 | 0.00 | 33.00 |
Date | April 5, 2024 | April 5, 2024 | December 31, 2026 | |
Comment |
1.2 Local property tax assessments in the Principal Urban Center LGs | Value | 39.00 | 39.00 | 49.00 |
Date | April 5, 2024 | April 5, 2024 | December 31, 2026 | |
Comment |
2.5 Urban LGs that received a minimum of coaching, incl on climate change, identified in their Annual Capacity Building Plans (Percentage) | Value | No climate change capacity building for LGs | No climate change capacity building for LGs | DLR 10.8.a: 90% of 124 PACASEN CTs have received a |
Date | April 4, 2024 | April 4, 2024 | December 31, 2026 | |
Comment |