Financier | Commitments |
---|---|
Global Financing Facility | 10.10 |
IDA Credit | 60.00 |
P504281
Active
Tseganeh Guracha , Ronald Gomez Suarez
Ministry of Finance
February 29, 2024
(as of board presentation)
January 16, 2025
June 23, 2025
US$ 0.00 million
Ministry of Health
2025
US$ 70.10 million
N/A
Moderate
June 30, 2029
Yes
BANK APPROVED
April 14, 2025
Financier | Commitments |
---|---|
Global Financing Facility | 10.10 |
IDA Credit | 60.00 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | N/A |
IDA Commitment | 60.00 |
IBRD + IDA Commitment | 60.00 |
Lending Instrument | |
---|---|
Grant Amount | 10.10 |
Total Project Cost** | N/A |
Name | Review | Date |
---|---|---|
Progress towards achievement of PDO | Satisfactory | 2025-06-09 |
Project Management | Satisfactory | 2025-06-09 |
Financial Management | Satisfactory | 2025-06-09 |
Monitoring and Evaluation | Satisfactory | 2025-06-09 |
Procurement | Satisfactory | 2025-06-09 |
Overall Implementation Progress (IP) | Satisfactory | 2025-06-09 |