West Africa Regional Electricity Market Program (WA-REMP) MPA Phase 1 - Mauritania Transmission Corridor Project

Abstract*

The proposed operation, Mauritania Transmission Corridor, is part of Phase 1 of the WA-REMP MPA. It will include critical national level investments to support the reinforcement of the national grid for increased regional trade, and enable faster deployment of renewable energy as well as expansion of energy access in underserved areas. West Africa Regional Electricity Market Program (WA-REMP) is a Multi-Phase Programmatic Approach (MPA) operation...

* The project abstract is drawn from the PAD, SAR or PGD and may not accurately reflect the project's current nature

Show More

Development Objective

The Project Development Objective is to scale up renewable energy deployment, increase access to electricity, and expand Mauritania's electricity export capacity.

Key Details

Project Details

  • P505173

  • Active

  • Tamaro Kane , Frederic Verdol, Manaf Touati

  • Islamic Republic of Mauritania

  • Mauritania

  • May 24, 2024

  • (as of board presentation)

    January 24, 2025

  • N/A

  • US$ 465.00 million

  • N/A

  • N/A

  • January 31, 2030

  • Yes

  • BANK APPROVED

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
JAPAN: Japan International Cooperation Agency (JICA) 30.00
African Development Bank 115.00
EC: European Investment Bank 120.00
IDA Credit 129.00
FRANCE: Govt. of [MOFA and AFD (C2D)] 71.00

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment N/A
IDA Commitment 129.00
IBRD + IDA Commitment 129.00
Lending Instrument
Grant Amount 336.00
Total Project Cost** N/A

Summary Status of World Bank Financing (US$ Millions) as of March 31, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of March 31, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)

Footnotes

Ratings

IMPLEMENTATION RATINGS

No data available.

COMPLETION RATINGS

No data available.

INDEPENDENT EVALUATION RATINGS

No data available.

Results Framework

No data available.