Financier | Commitments |
---|---|
International Bank for Reconstruction and Development | 173.50 |
P505208
Active
Roger Coma Cunill , Florian Kitt
Azerenerji OJSC
May 9, 2024
(as of board presentation)
March 27, 2025
N/A
US$ 0.00 million
Azerenerji OJSC
2025
US$ 173.50 million
N/A
Substantial
October 31, 2029
Yes
BANK APPROVED
July 10, 2025
Financier | Commitments |
---|---|
International Bank for Reconstruction and Development | 173.50 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | 173.50 |
IDA Commitment | N/A |
IBRD + IDA Commitment | 173.50 |
Lending Instrument | |
---|---|
Grant Amount | N/A |
Total Project Cost** | N/A |
Name | Review | Date |
---|---|---|
Procurement | Satisfactory | 2025-06-27 |
Progress towards achievement of PDO | Satisfactory | 2025-06-27 |
Project Management | Satisfactory | 2025-06-27 |
Financial Management | Satisfactory | 2025-06-27 |
Monitoring and Evaluation | Satisfactory | 2025-06-27 |
Overall Implementation Progress (IP) | Satisfactory | 2025-06-27 |