Technical Assistance for Kambarata 1 Hydropower Plant Project

Development Objective

To assess the Kambarata 1 hydropower plant project’s technical feasibility, enhance its environmental and social sustainability, and strengthen its financial and commercial frameworks.

Key Details

Project Details

  • P505544

  • Active

  • N/A

  • Kyrgyz Republic

  • April 7, 2024

  • (as of board presentation)

    July 11, 2024

  • N/A

  • US$ 16.60 million

  • N/A

  • N/A

  • N/A

  • Yes

  • BANK APPROVED

  • P181086

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
Energy Sector Management Assistance Program 0.00
Asian Infrastructure Investment Bank 3.00
IDA Credit 11.00
Regional Program on Central Asia - Energy & Water Developmen 2.60

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment N/A
IDA Commitment 11.00
IBRD + IDA Commitment 11.00
Lending Instrument
Grant Amount 5.60
Total Project Cost** 5.00

Summary Status of World Bank Financing (US$ Millions) as of March 31, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of March 31, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)

Footnotes

Ratings

IMPLEMENTATION RATINGS

No data available.

COMPLETION RATINGS

No data available.

INDEPENDENT EVALUATION RATINGS

No data available.