Financier | Commitments |
---|---|
International Bank for Reconstruction and Development | 200.00 |
Local Govts. (Prov., District, City) of Borrowing Country | 50.00 |
P505590
Active
Eric Lancelot , Carlos Bellas Lamas
State of Mato Grosso do Sul
July 12, 2024
(as of board presentation)
April 10, 2025
N/A
US$ 0.00 million
Escritório de Parcerias Estratégicas do Governo do Estado de Mato Grosso do Sul
2025
US$ 200.00 million
N/A
Moderate
March 31, 2034
Yes
BANK APPROVED
April 14, 2025
Financier | Commitments |
---|---|
International Bank for Reconstruction and Development | 200.00 |
Local Govts. (Prov., District, City) of Borrowing Country | 50.00 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | 200.00 |
IDA Commitment | N/A |
IBRD + IDA Commitment | 200.00 |
Lending Instrument | |
---|---|
Grant Amount | N/A |
Total Project Cost** | N/A |
Name | Review | Date |
---|---|---|
Progress towards achievement of PDO | Satisfactory | 2025-07-16 |
Counterpart Funding | Satisfactory | 2025-07-16 |
Monitoring and Evaluation | Satisfactory | 2025-07-16 |
Overall Implementation Progress (IP) | Satisfactory | 2025-07-16 |
Procurement | Satisfactory | 2025-07-16 |
Financial Management | Satisfactory | 2025-07-16 |
Project Management | Satisfactory | 2025-07-16 |