Skip to Main Navigation

Barbados – Beryl Emergency Response and Recovery Project

Abstract*

B. Project Components Project activities will focus on supporting recovery and reconstruction in the wake of Hurricane Beryl while strengthening the country’s resilience to future disasters, including and building capacity for disaster preparedness and response capacity. The project is organized in four components: Component 1: Immediate Recovery from a hurricane (US$43.5 million of which retroactive financing up to US$5.32 million). This component...

* The project abstract is drawn from the PAD, SAR or PGD and may not accurately reflect the project's current nature

Show More

Development Objective

To: (i) restore disaster-affected targeted sectors; (ii) enhance climate-resilient infrastructure; and (iii) strengthen emergency preparedness and response capacity.

Key Details

Project Details

  • P507190

  • Active

  • Naraya Carrasco , Alexander Agosti

  • Barbados

  • Barbados

  • October 17, 2024

  • (as of board presentation)

    November 21, 2024

  • N/A

  • US$ 0.00 million

  • Ministry of Environment and National Beautification, Blue and Green Economy

  • Latin America and Caribbean

  • 2025

  • US$ 54.00 million

  • N/A

  • Substantial

  • December 31, 2030

  • TBD

  • BANK APPROVED

  • March 12, 2025

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
International Bank for Reconstruction and Development 54.00

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment 54.00
IDA Commitment N/A
IBRD + IDA Commitment 54.00
Lending Instrument
Grant Amount N/A
Total Project Cost** N/A

Summary Status of World Bank Financing (US$ Millions) as of April 30, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of April 30, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Progress towards achievement of PDO Satisfactory 2025-04-11
Monitoring and Evaluation Satisfactory 2025-04-11
Overall Implementation Progress (IP) Satisfactory 2025-04-11
Project Management Satisfactory 2025-04-11
Financial Management Moderately Satisfactory 2025-04-11
Procurement Moderately Satisfactory 2025-04-11

COMPLETION RATINGS

No data available.

INDEPENDENT EVALUATION RATINGS

No data available.

Results Framework

No data available.