Burundi - Emergency Energy Project from IDA CRW

Download to Excel:
DESCRIPTION NOTICE TYPE STATUS PUBLISHED DATE
Contract AwardContract AwardPublishedJanuary 17, 2014
Étude d’Audit énergétique des installations de transport et distribution de l’énergie électrique ainsi que des stations de pompage d’eau potable de la REGIDESO.Contract AwardPublishedNovember 27, 2013
Contract AwardContract AwardPublishedAugust 23, 2013
Contract AwardContract AwardPublishedAugust 23, 2013
Contract AwardContract AwardPublishedAugust 23, 2013
FOURNITURE DE 2400 TONNES METRIQUES DE GASOIL A LA CENTRALE THERMIQUE DE 5MW DE LA REGIDESO A BUJUMBURA.Contract AwardPublishedApril 26, 2013
Travaux d’installation (remplacement) de 15 000 compteurs électriques à prépaiement dans le Réseau Electrique de la ville de Bujumbura / Burundi.Invitation for BidsPublishedApril 19, 2013
APPEL A LA MANIFESTATION D’INTERET POUR LA REALISATION DU RAPPORT D’ACHEVEMENT DU PURSE.Request for Expression of InterestPublishedApril 1, 2013
ETUDES D’AUDIT ENERGETIQUE DES INSTALLATIONS DE TRANSPORT ET DISTRIBUTION DE L’ENERGIE ELECTRIQUE AINSI QUE DES STATIONS DE POMPAGE D’EAU POTABLE DE LA REGIDESO AU BURUNDI.Request for Expression of InterestPublishedDecember 26, 2012
Contract AwardContract AwardPublishedDecember 18, 2012
Contract AwardContract AwardPublishedDecember 17, 2012
MARCHE DE FOURNITURE DE 2 400 TONNES METRIQUES DE GASOIL POUR LA CENTRALE THERMIQUE DE 5MW / REGIDESO / BUJUMBURA.Invitation for BidsPublishedNovember 20, 2012
ÉTUDE D’IMPACT ENVIRONNEMENTAL ET SOCIAL ET PLAN D’ACTION ET DE REINSTALLATION DES AMENAGEMENTS HYDROELECTRIQUES JIJI ET MULEMBWE, DE LA LIGNE 110KV D’EVACUATION DE L’ENERGIE SUR BUJUMBURA ET DU RESEAU SECONDAIRE.Request for Expression of InterestPublishedNovember 18, 2012
MARCHE DE FOURNITURE DE 2 400 TONNES METRIQUES DE GASOIL POUR LA CENTRALE THERMIQUE DE 5MW / REGIDESO / BUJUMBURA.Invitation for BidsPublishedNovember 18, 2012
APPEL A LA MANIFESTATION D’INTERET POUR LA REALISATION DU RAPPORT D’EVALUATION A MI-PARCOURS DU PURSE ( RELANCE ).Request for Expression of InterestPublishedNovember 9, 2012
APPEL A LA MANIFESTATION D’INTERET POUR LA REALISATION DU RAPPORT D’EVALUATION A MI-PARCOURS DU PURSE.Request for Expression of InterestPublishedOctober 4, 2012
SURVEILLANCE DES TRAVAUX D’INSTALLATION ET DE MISE EN SERVICE D’UNE CENTRALE THERMIQUE DE 5 MW A BUJUMBURA AU BURUNDI.Request for Expression of InterestPublishedAugust 7, 2012
AUDIT FINANCIER DU PMIEE ET DU PURSE POUR LES EXERCICES 2011, 2012 ET 2013.Contract AwardPublishedJune 21, 2012
TRAVAUX DE REHABILITATION DES CENTRALES HYDROELECTRIQUES DE RWEGURA ET NYEMANGA.Contract AwardPublishedMay 24, 2012
APPEL A MANIFESTATION D’INTERET POUR L’APPUI AU SUIVI-EVALUATION ENVIRONNEMENTAL ET SOCIAL.Request for Expression of InterestPublishedMay 24, 2012