VE CARACAS SLUM UPGRADE

Resumo*

The Caracas Slum-Upgrading Project aims to improve quality of life for the inhabitants of a selected number of barrios in Caracas, Venezuela, by developing and implementing a community-driven, sustainable, and replicable infrastructure improvement program. The project has three components. The first, urban upgrading, finances the design and execution of Communities Neighborhood Improvement Plans (NIP) and includes designing and executing pedestrian...

* Os resumos dos projetos são tirados do PAD, SAR ou PGD e talvez não reflitam com exatidão a natureza atual do projeto

Ver mais

Objetivo de Desenvolvimento

The objective of the Project is to improve the quality of life of the inhabitants of a selected number of barrios (representing 15 percent of total barrio population) in the Metropolitan Area of Caracas (MAC), through the development and implementation of a community driven, sustainable and replicable infrastructure improvement program.The objective remains unchanged, although with the partial loan cancellation the number of direct beneficiaries is 40% of what was originally projected.

Chave Detalhes

Projeto Detalhes

  • P040174

  • Closed

  • Taimur Samad

  • N/A

  • Venezuela, República Bolivariana da

  • 10 de agosto de 1998

  • (conforme apresentação da Diretoria Executiva)

    22 de outubro de 1998

  • 21 de dezembro de 1999

  • US$ 60.70 milhões

  • B

  • 15 de janeiro de 2013

  • 30 de junho de 2006

  • BANK APPROVED

  • Notes

Finanças

Plano De Financiamento (US$ Milhões)

Não há dados disponíveis
Financiador Compromissos
International Bank for Reconstruction and Development 60.70

Financiamento total do projeto (US$ milhões)

Linha de produtos BIRD/AID
Compromisso do BIRD 60.70
Compromissos da AID N/A
Compromisso do BIRD + AID 60.70
Instrumento de empréstimo
Montante do subsídio N/A
Custo total do projeto** 152.90

Resumo da situação do financiamento do Banco Mundial (em US$ milhões) em 28 de fevereiro de 2025

Baixar:
Não há dados disponíveis
Financiador Data Da Aprovação Data De Encerramento Principal Desembolsado Pagamentos Juros, Custos E Taxas

Atividade financeira detalhada em 28 de fevereiro de 2025

Baixar:
Não há dados disponíveis
Período Financiador Tipo De Transção Montante (US$)

Footnotes

Ratings

CLASSIFICAÇÕES DA IMPLEMENTAÇÃO

Name Review Date
Procurement Satisfactory 2006-05-16
Overall Safeguards Rating Satisfactory 2006-05-16
Financial Management Satisfactory 2006-05-16
Overall Implementation Progress (IP) Satisfactory 2006-05-16
Progress towards achievement of PDO Satisfactory 2006-05-16
Counterpart Funding Moderately Satisfactory 2006-05-16
Project Management Satisfactory 2006-05-16
Monitoring and Evaluation Satisfactory 2006-05-16

CLASSIFICAÇÕES DAS CONCLUSÕES

INDICADORRELATÓRIO SOBRE A CONCLUSÃO E RESULTADOS DA IMPLEMENTAÇÃO: 03-30-2007
ResultadosModerately Satisfactory
Risco para o resultado de desenvolvimentoModest
Desempenho do Banco MundialModerately Satisfactory
Desempenho do mutuárioModerately Satisfactory
Desempenho do governoModerately Satisfactory
Entidade ExecutoraModerately Satisfactory

CLASSIFICAÇÕES DA AVALIAÇÃO INDEPENDENTE

INDICADORREVISÃO DA RCI: 06-20-2007RELATÓRIO SOBRE AVALIAÇÃO DO DESEMPENHO DO PROJETO:
Classificação De ResultadosModerately Satisfactory N/a
Risco Para O Resultado De DesenvolvimentoModerateN/a
Desempenho Do Banco MundialModerately SatisfactoryN/a
Desempenho Do MutuárioModerately SatisfactoryN/a
Desempenho Do GovernoModerately SatisfactoryN/a
Entidade ExecutoraModerately SatisfactoryN/a
Qualidade Da RciSatisfactoryN/a
Qualidade M&eModestN/a

Estrutura de Resultados

Não há dados disponíveis