Demonstration of alternatives to Chlordane and Mirex in Termite Control Project

Resumo*

The Demonstration of Alternatives to Chlordane and Mirex in Termite Control GEF Project aims to mitigate environmental and health risks in China associated with chlordane and mirex in termite control by (1) demonstrating the elimination of their use through the introduction of integrated pest management in selected areas, and (2) preparing a national replication program for complete phase-out of chlordane and mirex. The project has six components:...

* Os resumos dos projetos são tirados do PAD, SAR ou PGD e talvez não reflitam com exatidão a natureza atual do projeto

Ver mais

Objetivo de Desenvolvimento

Project development objective is to (i) mitigate environmental and health risks associated with chlordane and mirex in termite control by (a) demonstrating the elimination of their use through the introduction of integrated pest management in selected areas, and preparing a national replication program for complete phase-out of chlordane and mirex in China (by 2014).

Chave Detalhes

Projeto Detalhes

  • P082992

  • Closed

  • Qing Wang

  • N/A

  • China

  • 10 de setembro de 2003

  • (conforme apresentação da Diretoria Executiva)

    29 de junho de 2006

  • 15 de dezembro de 2006

  • US$ 14.36 milhões

  • A

  • Não aplicável

  • 31 de dezembro de 2011

  • BANK APPROVED

  • 15 de janeiro de 2013

  • Notes

Finanças

Plano De Financiamento (US$ Milhões)

Não há dados disponíveis
Financiador Compromissos
Global Environment Facility (GEF) 14.36
Borrower/Recipient 13.34

Financiamento total do projeto (US$ milhões)

Linha de produtos BIRD/AID
Compromisso do BIRD N/A
Compromissos da AID N/A
Compromisso do BIRD + AID N/A
Instrumento de empréstimo
Montante do subsídio 14.36
Custo total do projeto** 27.70

Resumo da situação do financiamento do Banco Mundial (em US$ milhões) em 30 de abril de 2025

Baixar:
Não há dados disponíveis
Financiador Data Da Aprovação Data De Encerramento Principal Desembolsado Pagamentos Juros, Custos E Taxas

Atividade financeira detalhada em 30 de abril de 2025

Baixar:
Não há dados disponíveis
Período Financiador Tipo De Transção Montante (US$)

Footnotes

Ratings

CLASSIFICAÇÕES DA IMPLEMENTAÇÃO

Name Review Date
Counterpart Funding Satisfactory 2012-06-11
Summary Global Objective Rating Satisfactory 2012-06-11
Financial Management Satisfactory 2012-06-11
Overall Implementation Progress (IP) Satisfactory 2012-06-11
Procurement Satisfactory 2012-06-11
Project Management Satisfactory 2012-06-11
Monitoring and Evaluation Moderately Satisfactory 2012-06-11

CLASSIFICAÇÕES DAS CONCLUSÕES

INDICADORRELATÓRIO SOBRE A CONCLUSÃO E RESULTADOS DA IMPLEMENTAÇÃO: 06-23-2012
ResultadosModerately Satisfactory
Risco para o resultado de desenvolvimentoModest
Desempenho do Banco MundialModerately Satisfactory
Desempenho do mutuárioSubstantial
Desempenho do governoSubstantial
Entidade ExecutoraSubstantial

CLASSIFICAÇÕES DA AVALIAÇÃO INDEPENDENTE

INDICADORREVISÃO DA RCI: 02-24-2014RELATÓRIO SOBRE AVALIAÇÃO DO DESEMPENHO DO PROJETO:
Classificação De ResultadosModerately Satisfactory N/a
Risco Para O Resultado De DesenvolvimentoNegligible To LowN/a
Desempenho Do Banco MundialModerately SatisfactoryN/a
Desempenho Do MutuárioSatisfactoryN/a
Desempenho Do GovernoSatisfactoryN/a
Entidade ExecutoraSatisfactoryN/a
Qualidade Da RciExemplaryN/a
Qualidade M&eModestN/a

Estrutura de Resultados

INDICADORES DO OBJETIVO DE DESENVOLVIMENTO DO PROJETO

INDICADORLINHA DE REFERÊNCIAATUALALVO

INDICADORES DE RESULTADOS INTERMEDIÁRIOS

INDICADORLINHA DE REFERÊNCIAATUALALVO
  • The project team at CIO and provincial PIUs adequately staffed, trained and equipped.Valor0% - no project teams in placeAll CIO and PIUs staffed.
    Data1 de junho de 200631 de outubro de 200831 de dezembro de 2008
    ComentárioEntire Project teams established -- staffed, trained and equipped at full capacity.
  • Chief technical advisor (CTA), national technical advisor (NTA), and technical experts recruited.Valor0% - no technical advisory staff in place100%CTA, NTA and technical advisors recruited
    Data1 de junho de 200631 de outubro de 200831 de dezembro de 2007
    Comentário
  • Semi-annual Provincial Steering Group (PSG) meetings conducted in each demonstration area.Valor0% - no PSG meetings100% completed.All PSG meetings take place as scheduled (or ad ho
    Data1 de junho de 200630 de dezembro de 201131 de dezembro de 2010
    ComentárioAchieved. The provincial PIUs organized PSG meetings as needed to review project progress and address issues incurred.
  • National and provincial policy and regulatory documents reviewed, revised as necessary, or issued in respect to national and provincial construction codes.Valor0% - no policies reviewed or revised100% completed.100% of documents reviewed, revised and some of th
    Data1 de junho de 200630 de dezembro de 201131 de dezembro de 2010
    ComentárioAchieved. A total of six national-level policies and 25 provincial-level policies were revised or newly formulated.
  • The IPM Operation and Training Manual disseminated.Valor0% -- no IPM operation and training manual100% - IPM manual completed and disseminated in al
    Data1 de junho de 200630 de abril de 200831 de dezembro de 2007
    ComentárioIPM manual completed and disseminated in all three demonstration provinces.
  • IPM training conducted to train at least: 3 managerial personnel of each termite station; about 100 research personnel; 3 trainers from each city level station; and 10 termite control operators.Valor0% -- no IPM training100% completedAll IPM training completed
    Data1 de junho de 200630 de dezembro de 201131 de dezembro de 2010
    ComentárioAchieved. A total of 94 training workshops on IPM concepts and techniques were held for 5,754 management staff andtechnicians/operators on termite prevention and control.
  • Revised indicator: 694,105 in-ground bait systems procured and installed, 67,895 in-ground bait systems procured for maintenance beyond the project life in the three demonstration provinces.Valor0% - no bait system installed100% of revised target completed.400,000 in-ground bait systems installed
    Data1 de junho de 200630 de dezembro de 201131 de dezembro de 2010
    ComentárioRevised target achieved. The target was revised by an amendment to the GA in December 2010.
  • Revised indicator: 151,500 above-ground stations installed for remedial treatment of buildings in the three demonstration provinces.Valor0% - no bait system installed100% of revised target completed.500,000 above-ground bait systems installed
    Data1 de junho de 200630 de dezembro de 201131 de dezembro de 2010
    ComentárioRevised target achieved. The target was revised by an amendment to the GA in December 2010.
  • Use of 150 metric tons (MT) of C/M for termite control in the demonstration area is eliminated.Valor0% - no reduction in C/M use100% reduction in C/M use in the three provinces (
    Data1 de junho de 200617 de maio de 200931 de dezembro de 2010
    ComentárioConsumption of C/M was banned on May 17, 2009.
  • Integrated termite management website established and ready for public use.Valor0% no websiteWebsite fully established and operational.
    Data1 de junho de 200631 de outubro de 200831 de dezembro de 2008
    ComentárioThe website is established and under operation.
  • Production of C/M reduced permanently from 450 MT to 300 MT.Valor450 MT of chlordane and mirex production300 MT of chlordane and mirex production
    Data1 de junho de 200617 de maio de 200931 de dezembro de 2009
    ComentárioProduction of C/M was banned on May 17, 2009.
  • Revised indicator: Contaminated facilities, equipment and waste from two manufacturing sites removed.Valor0%. Production facilities not closed yet and are100% of revised targets completed.100%
    Data1 de junho de 200630 de dezembro de 201131 de dezembro de 2009
    ComentárioThis indicator is revised according to the GA amendment in Dec. 2010.Revised targets achieved. Contaminated facilities, equipment and waste from two sites were removed.Liyang Guanghua decided not to participate in the project because it does not think compensation from the ODS grant (for thephaseout of CTC used in the production of C&M) is sufficient for re-building the entire plant, even though the POPs project wouldfinance the plant dismantling and cleanup. A new site (Liyang Xinhai) has been selected. Site cleanup was completed in May 2011.And one more site was selected for cleanup under the project. The project GA was amended in Dec. 2010 to reflect this change.
  • Revised indicator: Hazardous waste from two plant closures properly disposed.Valor0% - no waste disposal100% of revised targets completed.100% of hazardous waste disposed.
    Data1 de junho de 200630 de dezembro de 201131 de dezembro de 2009
    ComentárioThis indicator is revised according to the GA amendment in Dec. 2010.Revised targets achieved. Hazardous waste was disposed from two plants (Liyang Xinhai and Changshu Fengjiang).
  • Liyang Company owner compensated for lost profit and workers compensated in accordance with local rules and regulations. per Grant AgreementValor0% compensation program completedNot completed.Full compensation completed for plant owner and wo
    Data1 de junho de 200631 de dezembro de 201131 de dezembro de 2009
    ComentárioLiyang Guanghua decided not to participate in the project as it considered compensation not sufficient for re-building its plant.Liyang Xinhai was selected replacing Liyang Guanghua. C/M production in Liyang Guanghua was closed as requested by the Ban.
  • Workshop on monitoring and evaluation conducted.Valor0% - no workshop100% completed100% - workshop conducted
    Data1 de junho de 200630 de dezembro de 201131 de dezembro de 2010
    ComentárioAchieved. The workshop on monitoring and evaluation conducted in Sept. 15-17, 2008 during the World Bank mission. Another M&Eworkshop held in late December 2011 focusing on preparation of completion reports by PIUs and other stakeholders.
  • Adequate project management information produced and semi-annual financial management reports (FMRs) producedValor0% - no FMRs100% completedFMRs with required information to be prepared ever
    Data1 de junho de 200631 de dezembro de 201131 de dezembro de 2010
    ComentárioAchieved. All management information and FMRs produced regularly.
  • Four annual implementation review meetings conducted.Valor0% - no annual reviews100% completedFour annual reviews completed
    Data1 de junho de 200630 de dezembro de 201131 de dezembro de 2010
    ComentárioAchieved. Review meetings conducted several times a year.
  • Computerized Management Information System (MIS) established.Valor0% - no MIS100% completedMIS developed and installed in participating Termi
    Data1 de junho de 200630 de dezembro de 201131 de dezembro de 2010
    ComentárioAchieved. MIS installed and functional in all participating Termite Control Stations.
  • National workshop for preparation of the NRP conducted.Valor0% - no replication program workshopWorkshop completed
    Data1 de junho de 200630 de abril de 200831 de dezembro de 2008
    ComentárioA workshop was held in October 2007.
  • NRP finalized and submitted to GEF CEO for approvalValor0% - no national replication programThe NRP preparation was completed, but not submittReplication program completed and submitted to GEF
    Data1 de junho de 200630 de dezembro de 201131 de dezembro de 2010
    ComentárioPartially achieved. There was project cost savings by Dec. 2010 under the project, it was agreed to cancel submission of the NRPtoGEF for seeking financing. China decided to include the NRP in its 12th Five Year Plan for termite control.
  • Eight EIAs prepared for the closure of the remaining eight C/M producers.Valor0% - no EIAs for the remaining eight C/M manufactuAll 8 EIA finalized
    Data1 de junho de 200630 de abril de 201030 de abril de 2010
    ComentárioEIAs for 8 C/M producers have been completed. One site was selected base on the EIAs for the remaining eight C/M producers toreplace Liyang Guanhua. Another site was selected also based on these EIAs.
  • National and global dissemination workshop conducted for the project.Valor0% - no dissemination workshopsnot completedworkshop completed
    Data1 de junho de 200630 de dezembro de 201131 de dezembro de 2010
    ComentárioNot achieved. FECO decided to hold this workshop in June 2012 by using its counterpart funding.
  • No use of chlordane and mirex by the termite control professionals in the demonstration area.Valor150.000.000.00
    Data31 de dezembro de 200117 de maio de 200931 de dezembro de 2010
    Comentário150 MT of chlordane and mirex in the three provinces.production and consumption of chlordane and mirex have been banned in China since May 2009Complete phaseout of chlordane and mirex in the three demonstration provinces.
  • New Indicator: 41,250 monitoring-dusting systems installed during the project life in five newly-added project provinces, 4,125 monitoring-dusting systems procured for maintenance beyond the project.Valor0100% completed41,250 monitoring-dusting systems installed.
    Data1 de janeiro de 201131 de dezembro de 201131 de dezembro de 2011
    ComentárioAchieved. The piloting results for termite prevention and control is promising.