Financiador | Compromissos |
---|---|
Borrower/Recipient | 30.20 |
IDA Credit | 60.00 |
International Bank for Reconstruction and Development | 32.80 |
P083742
Closed
Fabrizio Bresciani
N/A
6 de janeiro de 2004
(conforme apresentação da Diretoria Executiva)
13 de fevereiro de 2007
28 de junho de 2007
US$ 123.00 milhões
N/A
2007
US$ 92.80 milhões
B
Não aplicável
30 de junho de 2013
BANK APPROVED
13 de fevereiro de 2013
Financiador | Compromissos |
---|---|
Borrower/Recipient | 30.20 |
IDA Credit | 60.00 |
International Bank for Reconstruction and Development | 32.80 |
Linha de produtos | BIRD/AID |
---|---|
Compromisso do BIRD | 32.80 |
Compromissos da AID | 60.00 |
Compromisso do BIRD + AID | 92.80 |
Instrumento de empréstimo | |
---|---|
Montante do subsídio | N/A |
Custo total do projeto** | 123.00 |
Name | Review | Date |
---|---|---|
Overall Safeguards Rating | Moderately Satisfactory | 2013-08-03 |
Financial Management | Moderately Satisfactory | 2013-08-03 |
Counterpart Funding | Moderately Satisfactory | 2013-08-03 |
Overall Implementation Progress (IP) | Moderately Satisfactory | 2013-08-03 |
Overall Safeguards Rating | Moderately Satisfactory | 2013-08-03 |
Progress towards achievement of PDO | Moderately Unsatisfactory | 2013-08-03 |
Procurement | Moderately Satisfactory | 2013-08-03 |
Project Management | Moderately Unsatisfactory | 2013-08-03 |
Monitoring and Evaluation | Moderately Unsatisfactory | 2013-08-03 |
INDICADOR | RELATÓRIO SOBRE A CONCLUSÃO E RESULTADOS DA IMPLEMENTAÇÃO: 12-30-2013 |
---|---|
Resultados | Moderately Unsatisfactory |
Risco para o resultado de desenvolvimento | Substantial |
Desempenho do Banco Mundial | Moderately Unsatisfactory |
Desempenho do mutuário | Moderately Unsatisfactory |
Desempenho do governo | Moderately Satisfactory |
Entidade Executora | Moderately Unsatisfactory |
INDICADOR | REVISÃO DA RCI: 08-27-2014 | RELATÓRIO SOBRE AVALIAÇÃO DO DESEMPENHO DO PROJETO: |
---|---|---|
Classificação De Resultados | Moderately Unsatisfactory | N/a |
Risco Para O Resultado De Desenvolvimento | Significant | N/a |
Desempenho Do Banco Mundial | Moderately Unsatisfactory | N/a |
Desempenho Do Mutuário | Moderately Unsatisfactory | N/a |
Desempenho Do Governo | Moderately Satisfactory | N/a |
Entidade Executora | Moderately Unsatisfactory | N/a |
Qualidade Da Rci | Satisfactory | N/a |
Qualidade M&e | Negligible | N/a |
INDICADOR | LINHA DE REFERÊNCIA | ATUAL | ALVO |
---|
Number and types of services provided to Farmer Organization (FO) members | Valor | 0.00 | 3672.00 | 5000.00 |
Data | 12 de novembro de 2008 | 31 de dezembro de 2012 | 30 de junho de 2012 | |
Comentário | No updates provided so far by the CPMU. Previous value is reported. | The CPMU is conducting an impact assessment study. |
Percentage of farmers benefiting from ePetani and other information and communication technology (ICT) services | Valor | 0.00 | 68.10 | 30.00 |
Data | 12 de novembro de 2008 | 31 de dezembro de 2012 | 31 de dezembro de 2012 | |
Comentário | No updates provided so far by the CPMU. Previous value is reported. | The CPMU is conducting an impact assessment study. |
Percentage of members of participating FOs with improved household expenditure rates | Valor | 0.00 | 0.00 | 70.00 |
Data | 12 de novembro de 2008 | 31 de dezembro de 2012 | 31 de dezembro de 2012 | |
Comentário | Data collected through the 2012 Beneficiary Impact Assessment Survey is still being encoded. The 2011 BIA could not be used due topoor quality of the data. | The CPMU is conducting an impact assessment study. |
Number of joint activities / ventures with private sector established by FOs under the Project | Valor | 0.00 | 811.00 | 2400.00 |
Data | 12 de novembro de 2008 | 31 de dezembro de 2012 | 30 de junho de 2012 | |
Comentário | No updates provided so far by the CPMU. Previous value is reported. | The CPMU is conducting an impact assessment study. |
Number of technology packages developed by AIATs that are used in FMAs | Valor | 0.00 | 18.00 | 25.00 |
Data | 12 de novembro de 2008 | 31 de dezembro de 2012 | 31 de dezembro de 2012 | |
Comentário | No updates provided so far by the CPMU. Previous value is reported. | The CPMU is conducting an impact assessment study. |
INDICADOR | LINHA DE REFERÊNCIA | ATUAL | ALVO |
---|
Number of collaborative activities in technology development and dissemination between AIAT and other research institutions/ services /providers (private sector, universities, NGO, local government) | Valor | 0.00 | 9.00 | 40.00 |
Data | 31 de dezembro de 2012 | 31 de dezembro de 2012 | ||
Comentário | No updates provided so far by the CPMU. Previous value is reported. | The CPMU is conducting an impact assessment study. |
Percentage of AIAT technology packages that are adopted in FMAs are fine tuned in collaboration with the participating farmer groups | Valor | 0.00 | 78.60 | 60.00 |
Data | 31 de dezembro de 2012 | 31 de dezembro de 2012 | ||
Comentário | No updates provided so far by the CPMU. Previous value is reported. | The CPMU is conducting an impact assessment study. |
Satisfaction levels from beneficiaries regarding improved R&D services | Valor | 0.00 | 37.09 | 70.00 |
Data | 12 de novembro de 2008 | 31 de dezembro de 2012 | 31 de dezembro de 2012 | |
Comentário | No updates provided so far by the CPMU. Previous value is reported. | The CPMU is conducting an impact assessment study. |
Participation rate of participating FO members in planning and decision making meetings | Valor | 0.00 | 82.00 | 60.00 |
Data | 31 de dezembro de 2012 | 31 de dezembro de 2012 | ||
Comentário | No updates provided so far by the CPMU. Previous value is reported. | The CPMU is conducting an impact assessment study. |
Percentage of FMA activities where experts from universities, research organizations and private sector participate as resource persons | Valor | 0.00 | 30.30 | 30.00 |
Data | 31 de dezembro de 2012 | 31 de dezembro de 2012 | ||
Comentário | No updates provided so far by the CPMU. Previous value is reported. | The CPMU is conducting an impact assessment study. |
Percentage of participating FOs assessed to have sound financial and procurement management practices | Valor | 0.00 | 43.10 | 80.00 |
Data | 12 de novembro de 2008 | 31 de dezembro de 2012 | 31 de dezembro de 2012 | |
Comentário | No updates provided so far by the CPMU. Previous value is reported. | The CPMU is conducting an impact assessment study. |
Percentage of participating FOs with members availing information and services of ePetani and KIS | Valor | 0.00 | 50.67 | 70.00 |
Data | 12 de novembro de 2008 | 31 de dezembro de 2012 | 31 de dezembro de 2012 | |
Comentário | No updates provided so far by the CPMU. Previous value is reported. | The CPMU is conducting an impact assessment study. |
Percentage satisfaction levels from beneficiaries regarding improved extension service - skills of staff as well as facilities and access | Valor | 0.00 | 75.60 | 80.00 |
Data | 31 de dezembro de 2012 | 31 de dezembro de 2012 | ||
Comentário | No updates provided so far by the CPMU. Previous value is reported. | The CPMU is conducting an impact assessment study. |
Percentage of participating FO members that participate in planning and decision making that are women or poor | Valor | 0.00 | 86.80 | 30.00 |
Data | 31 de dezembro de 2012 | 30 de junho de 2012 | ||
Comentário | No updates provided so far by the CPMU. Previous value is reported. | The CPMU is conducting an impact assessment study. |