Punjab Cities Program

Resumo*

The development objective of the Punjab Cities Program for Pakistan is to strengthen the performance of participating urban local governments in urban management and service delivery.The proposed Punjab Cities Program (PCP) is aligned with the World Bank Group’s Pakistan Country Partnership Strategy (CPS) FY15-20.The operation is expected to contribute to the Bank’s overarching goals of ending extreme poverty and promoting shared prosperity by delivering...

* Os resumos dos projetos são tirados do PAD, SAR ou PGD e talvez não reflitam com exatidão a natureza atual do projeto

Ver mais

Objetivo de Desenvolvimento

The objective of the Operation is to strengthen the performance of participating urban local governments in urban management and service delivery.

Chave Detalhes

Projeto Detalhes

  • P156972

  • Active

  • Shahnaz Arshad

  • Economic Affairs Division

  • Madagascar

  • 25 de janeiro de 2018

  • (conforme apresentação da Diretoria Executiva)

    25 de maio de 2018

  • 29 de maio de 2018

  • US$ 236.00 milhões

  • Punjab Municipal Development Funds Company,Planning and Development Board, Government of Punjab,Local Government and Community Development Department

  • Middle East, North Africa, Afghanistan, and Pakistan

  • 2018

  • US$ 200.00 milhões

  • B

  • Não aplicável

  • 29 de agosto de 2025

  • No

  • BANK APPROVED

  • 31 de maio de 2024

  • Notes

Finanças

Plano De Financiamento (US$ Milhões)

Não há dados disponíveis
Financiador Compromissos
IDA Credit 200.00
Borrower/Recipient 7.00

Financiamento total do projeto (US$ milhões)

Linha de produtos BIRD/AID
Compromisso do BIRD N/A
Compromissos da AID 200.00
Compromisso do BIRD + AID 200.00
Instrumento de empréstimo
Montante do subsídio N/A
Custo total do projeto** 236.00

Resumo da situação do financiamento do Banco Mundial (em US$ milhões) em 31 de julho de 2025

Baixar:
Não há dados disponíveis
Financiador Data Da Aprovação Data De Encerramento Principal Desembolsado Pagamentos Juros, Custos E Taxas

Atividade financeira detalhada em 31 de julho de 2025

Baixar:
Não há dados disponíveis
Período Financiador Tipo De Transção Montante (US$)

Footnotes

Ratings

CLASSIFICAÇÕES DA IMPLEMENTAÇÃO

Name Review Date
Progress towards achievement of PDO Satisfactory 2025-06-27
Monitoring and Evaluation Satisfactory 2025-06-27
Overall Implementation Progress (IP) Satisfactory 2025-06-27

CLASSIFICAÇÕES DAS CONCLUSÕES

Não há dados disponíveis

CLASSIFICAÇÕES DA AVALIAÇÃO INDEPENDENTE

Não há dados disponíveis

Estrutura de Resultados

INDICADORES DO OBJETIVO DE DESENVOLVIMENTO DO PROJETO

INDICADORLINHA DE REFERÊNCIAATUALALVO
  • Score in the APA for achievement of institutional performance measures, averaged across all MCs that qualify.Valor0.0060.0070.00
    Data29 de maio de 201819 de junho de 202328 de junho de 2024
    Comentário
  • People living in targeted cities benefiting from municipal service delivery infrastructure created or rehabilitated under the Program.Valor0.005398334.001000000.00
    Data29 de maio de 201815 de maio de 202428 de junho de 2024
    Comentário
  • PDO Indicator 2.a. Of which female (Supplemental)Valor0.0049.0050.00
    Data29 de maio de 201815 de maio de 202428 de junho de 2024
    Comentário

INDICADORES DE RESULTADOS INTERMEDIÁRIOS

INDICADORLINHA DE REFERÊNCIAATUALALVO
  • MCs with the full set of enhanced e-governance systems operationalized.Valor8.0016.0016.00
    Data29 de maio de 201815 de maio de 202428 de junho de 2024
    Comentário
  • MCs with Infrastructure Maps updated under the Program.Valor0.0016.0010.00
    Data29 de maio de 201815 de maio de 202428 de junho de 2024
    Comentário
  • MCs with IDAMPs developed and adopted, ensuring consultation with women groups.Valor0.0016.005.00
    Data29 de maio de 201815 de maio de 202428 de junho de 2024
    Comentário
  • MCs with at least 10% increase in OSRs.Valor0.0016.005.00
    Data29 de maio de 201815 de maio de 202428 de junho de 2024
    Comentário
  • Annual performance assessment of Program MCs conducted on time.ValorNo APAs conductedAPA for the current FY is ongoing.APAs conducted per annual schedule.
    Data29 de maio de 201815 de maio de 202428 de junho de 2024
    Comentário
  • MCs with timely audits conducted of annual financial statements and no adverse or disclaimed audit opinion.Valor0.0016.0016.00
    Data29 de maio de 201815 de maio de 202428 de junho de 2024
    Comentário
  • Percentage of local infrastructure targets as set out in the annual work plans delivered by MCs utilizing Program funds.Valor0.000.0080.00
    Data29 de maio de 201815 de maio de 202428 de junho de 2024
    Comentário
  • Percentage of infrastructure contracts with gender responsive working conditionsValor0.00100.0080.00
    Data29 de maio de 201815 de maio de 202428 de junho de 2024
    Comentário
  • MCs that execute at least 80 percent of their annual O&M budget.Valor0.000.0010.00
    Data29 de maio de 201815 de maio de 202428 de junho de 2024
    Comentário
  • IR Indicator 1.1.a. Performance Management System (Supplemental)Valor8.0016.0016.00
    Data29 de maio de 201815 de maio de 202428 de junho de 2024
    Comentário
  • IR Indicator 1.1.b. Computerized Financial Management System (Supplemental)Valor8.0016.0016.00
    Data29 de maio de 201815 de maio de 202428 de junho de 2024
    Comentário
  • IR Indicator 1.1.c. Complaint Tracking System (Supplemental)Valor8.0016.0016.00