Sindh Water and Agriculture Transformation Project (SWAT)

Resumo*

The development objective of the Sindh Water and Agriculture Transformation (SWAT) Project for Pakistan is to increase agricultural water productivity in selected farmers’ organization command areas, improve integrated water resources management (IWRM), and contribute to restoring crop production by small and medium‐sized farmers affected by the 2022 floods. The project comprises of six components. The first component, water resources management establishes...

* Os resumos dos projetos são tirados do PAD, SAR ou PGD e talvez não reflitam com exatidão a natureza atual do projeto

Ver mais

Objetivo de Desenvolvimento

To increase agricultural water productivity in Selected Farmers' Organization command areas, improve integrated water resources management, and contribute to restoring crop production by small and medium-sized farmers affected by the 2022 floods.

Chave Detalhes

Projeto Detalhes

  • P167596

  • Active

  • Greg Browder , Olivier Durand, Francois Onimus

  • Islamic Republic of Pakistan

  • Madagascar

  • 17 de junho de 2021

  • (conforme apresentação da Diretoria Executiva)

    19 de dezembro de 2022

  • 10 de janeiro de 2023

  • US$ 320.00 milhões

  • Province of Sindh

  • Sul da Ásia

  • 2023

  • US$ 292.00 milhões

  • A

  • Não aplicável

  • 31 de dezembro de 2028

  • Yes

  • BANK APPROVED

  • 11 de janeiro de 2024

  • Notes

Finanças

Plano De Financiamento (US$ Milhões)

Não há dados disponíveis
Financiador Compromissos
IDA Credit 292.00
Local Govts. (Prov., District, City) of Borrowing Country 28.00

Financiamento total do projeto (US$ milhões)

Linha de produtos BIRD/AID
Compromisso do BIRD N/A
Compromissos da AID 292.00
Compromisso do BIRD + AID 292.00
Instrumento de empréstimo
Montante do subsídio N/A
Custo total do projeto** 320.00

Resumo da situação do financiamento do Banco Mundial (em US$ milhões) em 30 de abril de 2025

Baixar:
Não há dados disponíveis
Financiador Data Da Aprovação Data De Encerramento Principal Desembolsado Pagamentos Juros, Custos E Taxas

Atividade financeira detalhada em 30 de abril de 2025

Baixar:
Não há dados disponíveis
Período Financiador Tipo De Transção Montante (US$)

Footnotes

Ratings

CLASSIFICAÇÕES DA IMPLEMENTAÇÃO

Name Review Date
Progress towards achievement of PDO Moderately Satisfactory 2024-12-20
Monitoring and Evaluation Satisfactory 2024-12-20
Overall Implementation Progress (IP) Moderately Satisfactory 2024-12-20
Procurement Moderately Satisfactory 2024-12-20
Project Management Moderately Satisfactory 2024-12-20
Financial Management Moderately Satisfactory 2024-12-20

CLASSIFICAÇÕES DAS CONCLUSÕES

Não há dados disponíveis

CLASSIFICAÇÕES DA AVALIAÇÃO INDEPENDENTE

Não há dados disponíveis

Estrutura de Resultados

INDICADORES DO OBJETIVO DE DESENVOLVIMENTO DO PROJETO

INDICADORLINHA DE REFERÊNCIAATUALALVO
  • FO subprojects in which agricultural surface water productivity increases by at least 20 percentValor0.000.0012.00
    Data1 de outubro de 20221 de dezembro de 202329 de dezembro de 2028
    Comentário
  • FO subprojects where the AWB delivers the agreed upon water volumes in compliance with FO-AWB Water Service agreementsValor0.000.0012.00
    Data1 de outubro de 20221 de dezembro de 202329 de dezembro de 2028
    Comentário
  • Farmers who receive cash transfers and resume agricultural production in 2023Valor0.00234855.00800000.00
    Data1 de outubro de 20221 de dezembro de 202317 de abril de 2023
    Comentário
  • Acres of water thrifty crops supported through the smart subsidy schemeValor0.000.0080000.00
    Data1 de outubro de 20221 de dezembro de 202329 de dezembro de 2028
    Comentário
  • Sindh Strategic Water Plan approved by the Sindh Water Resources CommissionValorNoNoYes
    Data1 de outubro de 20221 de dezembro de 202330 de junho de 2028
    Comentário

INDICADORES DE RESULTADOS INTERMEDIÁRIOS

INDICADORLINHA DE REFERÊNCIAATUALALVO
  • Draft water bill submitted to Sindh Provincial Assembly by the Sindh Law and Parliamentary Affairs DepartmentValorNoNoYes
    Data1 de outubro de 20221 de dezembro de 202330 de junho de 2027
    Comentário
  • Acres supported with improved on-farm water management measuresValor0.000.00110000.00
    Data1 de outubro de 20221 de dezembro de 202313 de abril de 2029
    Comentário
  • Water pricing reform study completed and Abiana rates increased by the Sindh Irrigation DepartmentValorNoNoYes
    Data1 de dezembro de 20221 de dezembro de 202330 de junho de 2026
    Comentário
  • Sindh Food Department Wheat Strategic Reserve Monitoring System functionalValorNoNoYes
    Data1 de outubro de 20221 de dezembro de 202329 de dezembro de 2028
    Comentário
  • Irrigation Department Transformed into Irrigation and Water Resources DepartmentValorNoNoYes
    Data1 de outubro de 20221 de dezembro de 202330 de junho de 2028
    Comentário
  • Preparation studies for Right Bank investments completedValorNoNoYes
    Data1 de outubro de 20221 de dezembro de 202330 de junho de 2027
    Comentário
  • New policy on Sindh agriculture research and extension adopted by the Sindh CabinetValorNoNoYes
    Data1 de outubro de 20221 de dezembro de 202330 de junho de 2026
    Comentário
  • Functional Hydro-Agro Informatics Program establishedValorNoNoYes
    Data1 de outubro de 20221 de dezembro de 202329 de dezembro de 2028
    Comentário
  • Farmers satisfied with development/implementation of Area Development PlanValor0.000.0070.00
    Data1 de outubro de 20221 de dezembro de 202329 de dezembro de 2028
    Comentário
  • Akram Wah Canal physical works completedValor0.000.00100.00
    Data1 de outubro de 20221 de dezembro de 202330 de junho de 2028
    Comentário
  • Sindh Crop and Market Monitoring System ImprovedValorNoNoYes
    Data1 de outubro de 20221 de dezembro de 202313 de abril de 2029
    Comentário
  • Representation of women in leadership increased in agriculture and water resources management organizationsValorNoNoYes
    Data1 de outubro de 20221 de dezembro de 202329 de dezembro de 2028
    Comentário
  • Groundwater actively managed in conjunction with surface water supplies in at least 2 pilot FOsValorNoNoYes
    Data1 de outubro de 20221 de dezembro de 202329 de dezembro de 2028
    Comentário
  • Waterlogging and Salinity management capacity strengthenedValorNoNoYes
    Data1 de outubro de 20221 de dezembro de 202330 de junho de 2028
    Comentário
  • Target FOs with at least two women on the boardValor0.000.000.00
    Data
    Comentário
  • Acres of applied research activitiesValor0.000.008.00
    Data
    Comentário
  • Target WCAs with at least two women on the boardValor0.000.000.00
    Data
    Comentário
  • Labs rehabilitatedValor0.0010.008.00
    Data
    Comentário
  • Target AWBs with at least two women on the boardValor0.000.000.00
    Data
    Comentário
  • Farmers and agricultural small and medium enterprises supported to enhance value chain for high value water thrifty cropsValor0.000.002100.00
    Data1 de outubro de 20221 de dezembro de 202313 de abril de 2029
    Comentário
  • Farmers trainedValor0.000.0080000.00
    Data1 de outubro de 20221 de dezembro de 202313 de abril de 2029
    Comentário
  • of which femaleValor0.000.0010500.00
    Data1 de outubro de 20221 de dezembro de 202313 de abril de 2029
    Comentário
  • Agriculture Extension offices rehabilitedValor0.000.0015.00
    Data1 de outubro de 20221 de dezembro de 202330 de junho de 2026
    Comentário