Improving Resilience and Emergency Response Project

Resumo*

The development objective of Improving Resilience and Emergency Response Project for Romania is to enhance the resilience of Romanian Police Facilities that are critical to respond to Emergency Situations and disasters and to strengthen the institutional capacities for emergency preparedness and response. This project has three components. 1) The first component, Enhance the Resilience of Selected Romanian Police Infrastructure to be Used in Disaster...

* Os resumos dos projetos são tirados do PAD, SAR ou PGD e talvez não reflitam com exatidão a natureza atual do projeto

Ver mais

Objetivo de Desenvolvimento

The proposed Project Development Objective (PDO) is to enhance the resilience of Romanian Police Facilities that are critical to respond to Emergency Situations and disasters and to strengthen the institutional capacities for emergency preparedness and response.

Chave Detalhes

Projeto Detalhes

  • P168119

  • Active

  • Tuo Shi , Guillermo Siercke

  • Romania (through its Ministry of Public Finance)

  • Romênia

  • 25 de outubro de 2018

  • (conforme apresentação da Diretoria Executiva)

    29 de maio de 2019

  • 8 de julho de 2020

  • US$ 57.00 milhões

  • Ministry of Internal Affairs (General Inspectorate of Romanian Police)

  • Europa e Ásia Central

  • 2019

  • US$ 57.00 milhões

  • B

  • 13 de novembro de 2023

  • 31 de dezembro de 2026

  • No

  • BANK APPROVED

  • Notes

Finanças

Plano De Financiamento (US$ Milhões)

Não há dados disponíveis
Financiador Compromissos
International Bank for Reconstruction and Development 57.00

Financiamento total do projeto (US$ milhões)

Linha de produtos BIRD/AID
Compromisso do BIRD 57.00
Compromissos da AID N/A
Compromisso do BIRD + AID 57.00
Instrumento de empréstimo
Montante do subsídio N/A
Custo total do projeto** 57.00

Resumo da situação do financiamento do Banco Mundial (em US$ milhões) em 28 de fevereiro de 2025

Baixar:
Não há dados disponíveis
Financiador Data Da Aprovação Data De Encerramento Principal Desembolsado Pagamentos Juros, Custos E Taxas

Atividade financeira detalhada em 28 de fevereiro de 2025

Baixar:
Não há dados disponíveis
Período Financiador Tipo De Transção Montante (US$)

Footnotes

Ratings

CLASSIFICAÇÕES DA IMPLEMENTAÇÃO

Name Review Date
Procurement Moderately Satisfactory 2024-11-20
Monitoring and Evaluation Satisfactory 2024-11-20
Overall Implementation Progress (IP) Moderately Satisfactory 2024-11-20
Progress towards achievement of PDO Moderately Satisfactory 2024-11-20
Financial Management Satisfactory 2024-11-20
Project Management Moderately Satisfactory 2024-11-20

CLASSIFICAÇÕES DAS CONCLUSÕES

Não há dados disponíveis

CLASSIFICAÇÕES DA AVALIAÇÃO INDEPENDENTE

Não há dados disponíveis

Estrutura de Resultados

INDICADORES DO OBJETIVO DE DESENVOLVIMENTO DO PROJETO

INDICADORLINHA DE REFERÊNCIAATUALALVO
  • Police personnel with access to resilient emergency response buildingsValor0.000.003160.00
    Data25 de abril de 201930 de outubro de 202325 de abril de 2025
    Comentário
  • Direct project beneficiaries served by Police personnel in resilient emergency response buildingsValor0.000.003452600.00
    Data25 de abril de 201930 de outubro de 202325 de abril de 2025
    Comentário
  • Capacity to reduce vulnerability of emergency response infrastructure in the long term enhancedValorNo existing strategyNo existing strategyStrategy adopted
    Data25 de abril de 201930 de outubro de 202325 de abril de 2025
    Comentário
  • Share of trained Police personnel with newly acquired skills and emergency response equipment participating in operational interventionsValor0.000.00100.00
    Data25 de abril de 201930 de outubro de 202325 de abril de 2025
    Comentário
  • Of which femaleValor0.000.0020.00
    Data25 de abril de 201930 de outubro de 202325 de abril de 2025
    Comentário

INDICADORES DE RESULTADOS INTERMEDIÁRIOS

INDICADORLINHA DE REFERÊNCIAATUALALVO
  • Technical designs completedValor0.005.0037.00
    Data25 de abril de 201930 de outubro de 202325 de abril de 2025
    Comentário
  • Police personnel with access to new emergency response equipmentValor0.000.00855.00
    Data25 de abril de 201930 de outubro de 202325 de abril de 2025
    Comentário
  • Institutional capacity in place for project implementationValorNoYesYes
    Data25 de abril de 201930 de outubro de 202325 de abril de 2025
    Comentário
  • Emergency response buildings which have been reconstructed with enhanced resilienceValor0.000.0010.00
    Data25 de abril de 201930 de outubro de 202325 de abril de 2025
    Comentário
  • Police personnel who have received training in emergency responseValor0.000.00200.00
    Data25 de abril de 201930 de outubro de 202325 de abril de 2025
    Comentário
  • Grievances responded to within stipulated timeValor0.000.00100.00
    Data25 de abril de 201930 de outubro de 202325 de abril de 2025
    Comentário
  • Emergency response buildings which have been retrofitted to enhance resilienceValor0.000.0017.00
    Data25 de abril de 201930 de outubro de 202325 de abril de 2025
    Comentário
  • Communities reached through informative community meetingsValor0.004.0015.00
    Data25 de abril de 201930 de outubro de 202325 de abril de 2025
    Comentário
  • Reconstructed or retrofitted emergency response buildings which have added or enhanced gender responsive design featuresValor0.000.00100.00
    Data25 de abril de 201930 de outubro de 202325 de abril de 2025
    Comentário
  • Reconstructed or retrofitted emergency response buildings which have design features for universal accessValor0.000.0030.00
    Data25 de abril de 201930 de outubro de 202325 de abril de 2025
    Comentário