Earthquake Recovery and Public Health Preparedness Project

Resumo*

The development objective of Earthquake Recovery and Public Health Preparedness Project is to assist Croatia with earthquake reconstruction efforts in Zagreb and the surrounding areas, improve institutional capacity for reconstruction, and strengthen national systems for public health preparedness. This project has three components. 1) The first component, Earthquake Recovery and Reconstruction, has the following sub-components: (i) Immediate Public...

* Os resumos dos projetos são tirados do PAD, SAR ou PGD e talvez não reflitam com exatidão a natureza atual do projeto

Ver mais

Objetivo de Desenvolvimento

The Project Development Objective (PDO) is to assist Croatia with earthquake reconstruction efforts in Zagreb and the surrounding areas, improve institutional capacity for reconstruction, and strengthen national systems for public health preparedness.

Chave Detalhes

Projeto Detalhes

  • P173998

  • Active

  • Zuzana Stanton-Geddes , Sema Sumer, Salih Erdurmus

  • Republic of Croatia

  • Croácia

  • 21 de maio de 2020

  • (conforme apresentação da Diretoria Executiva)

    26 de junho de 2020

  • 16 de dezembro de 2020

  • US$ 200.00 milhões

  • Ministry of Health,Ministry of Construction and Physical Planning and State Assets

  • Europa e Ásia Central

  • 2020

  • US$ 200.00 milhões

  • N/A

  • Substantial

  • 30 de junho de 2027

  • Yes

  • BANK APPROVED

  • 29 de maio de 2024

  • Notes

Finanças

Plano De Financiamento (US$ Milhões)

Não há dados disponíveis
Financiador Compromissos
International Bank for Reconstruction and Development 200.00

Financiamento total do projeto (US$ milhões)

Linha de produtos BIRD/AID
Compromisso do BIRD 200.00
Compromissos da AID N/A
Compromisso do BIRD + AID 200.00
Instrumento de empréstimo
Montante do subsídio N/A
Custo total do projeto** 200.00

Resumo da situação do financiamento do Banco Mundial (em US$ milhões) em 30 de abril de 2025

Baixar:
Não há dados disponíveis
Financiador Data Da Aprovação Data De Encerramento Principal Desembolsado Pagamentos Juros, Custos E Taxas

Atividade financeira detalhada em 30 de abril de 2025

Baixar:
Não há dados disponíveis
Período Financiador Tipo De Transção Montante (US$)

Footnotes

Ratings

CLASSIFICAÇÕES DA IMPLEMENTAÇÃO

Name Review Date
Procurement Satisfactory 2024-12-06
Project Management Satisfactory 2024-12-06
Overall Implementation Progress (IP) Satisfactory 2024-12-06
Financial Management Satisfactory 2024-12-06
Progress towards achievement of PDO Moderately Satisfactory 2024-12-06
Monitoring and Evaluation Satisfactory 2024-12-06

CLASSIFICAÇÕES DAS CONCLUSÕES

Não há dados disponíveis

CLASSIFICAÇÕES DA AVALIAÇÃO INDEPENDENTE

Não há dados disponíveis

Estrutura de Resultados

INDICADORES DO OBJETIVO DE DESENVOLVIMENTO DO PROJETO

INDICADORLINHA DE REFERÊNCIAATUALALVO
  • Rehabilitated or reconstructed health and education buildings with restored operational capacity and higher seismic performanceValor0.000.00100.00
    Data16 de junho de 202020 de março de 202416 de junho de 2024
    Comentário
  • Reported suspected cases of a selected health condition (a selected tracer condition) reported and investigated per approved protocol (disaggregated by gender)Valor0.00100.0080.00
    Data16 de junho de 202020 de março de 202416 de junho de 2024
    Comentário
  • Buildings which have benefited from debris removal and/or repairValor0.000.0035.00
    Data25 de junho de 202020 de março de 202425 de junho de 2024
    Comentário
  • Croatia has developed policy options for the design of a financial support program for housing reconstructionValorNoNoYes
    Data25 de junho de 202020 de março de 202425 de junho de 2024
    Comentário

INDICADORES DE RESULTADOS INTERMEDIÁRIOS

INDICADORLINHA DE REFERÊNCIAATUALALVO
  • Designs for rehabilitation or reconstruction of health and education buildings completedValor0.00100.00100.00
    Data9 de junho de 202020 de março de 202416 de junho de 2024
    Comentário
  • Grievances responded to in the stipulated timeValor0.00100.00100.00
    Data16 de junho de 202020 de março de 202416 de junho de 2024
    Comentário
  • Health and education buildings rehabilitated or reconstructed that have gender-responsive and universal access design featuresValor0.000.0010.00
    Data16 de junho de 202020 de março de 202416 de junho de 2024
    Comentário
  • Institutional coordination mechanism operational and key technical capacity in engineering, procurement and contract management in placeValorNoNoYes
    Data16 de junho de 202020 de março de 202416 de junho de 2024
    Comentário
  • Technical recommendations for the design of a housing reconstruction program developedValorNoNoYes
    Data9 de junho de 202020 de março de 202416 de junho de 2024
    Comentário
  • National guidelines for surveillance system updated including 15 health conditionsValor0.006.0015.00
    Data16 de junho de 202020 de março de 202417 de junho de 2024
    Comentário
  • People reached through informative community meetingsValor0.00756.002500.00
    Data9 de junho de 202020 de março de 202416 de junho de 2024
    Comentário
  • Sentinel sites for respiratory viruses providing quarterly reportsValor0.001.003.00
    Data16 de junho de 202020 de março de 202417 de junho de 2024
    Comentário
  • Assessments of the surveillance system conductedValor0.000.002.00
    Data9 de junho de 202020 de março de 202417 de junho de 2024
    Comentário
  • Percentage of which femaleValor0.000.0035.00
    Data
    Comentário
  • Beneficiaries satisfied with rehabilitated or reconstruction health and education buildings (disaggregated by gender)Valor0.000.0070.00
    Data16 de junho de 202020 de março de 202417 de junho de 2024
    Comentário
  • Surveillance sites established for the surveillance of gender-related violence or domestic violence, with data collection disaggregated by genderValor0.000.003.00
    Data16 de junho de 202020 de março de 202417 de junho de 2024
    Comentário