Barwaaqo - Somalia Water for Rural Resilience Project

Resumo*

Somalia has embarked on a journey for the sustainable development of its water resources for its communities. With the support of the World Bank, the Somaliland and Puntland states piloted low cost and conflict deterring water solutions under the Water for Agro-Pastoralist Livelihoods Pilot Project (WALP), a US$2 million pilot that resulted in the building of eight sand dams over the period 2016 to 2018. This investment paved the way for the ongoing...

* Os resumos dos projetos são tirados do PAD, SAR ou PGD e talvez não reflitam com exatidão a natureza atual do projeto

Ver mais

Objetivo de Desenvolvimento

To develop water, agriculture, and environmental services for rural communities in Somalia’s drylands.

Chave Detalhes

Projeto Detalhes

  • P177627

  • Active

  • Raghava Neti , Jeehye Kim, James Otieno

  • Federal Republic of Somalia

  • Somália

  • 29 de março de 2022

  • (conforme apresentação da Diretoria Executiva)

    9 de dezembro de 2022

  • 20 de janeiro de 2023

  • US$ 70.00 milhões

  • Ministry of Planning Investment and Economic Development

  • Eastern and Southern Africa

  • 2023

  • US$ 70.00 milhões

  • N/A

  • Substantial

  • 29 de fevereiro de 2028

  • Yes

  • BANK APPROVED

  • 4 de março de 2024

  • Notes

Finanças

Plano De Financiamento (US$ Milhões)

Não há dados disponíveis
Financiador Compromissos
IDA Grant 70.00

Financiamento total do projeto (US$ milhões)

Linha de produtos BIRD/AID
Compromisso do BIRD N/A
Compromissos da AID 70.00
Compromisso do BIRD + AID 70.00
Instrumento de empréstimo
Montante do subsídio N/A
Custo total do projeto** 70.00

Resumo da situação do financiamento do Banco Mundial (em US$ milhões) em 30 de abril de 2025

Baixar:
Não há dados disponíveis
Financiador Data Da Aprovação Data De Encerramento Principal Desembolsado Pagamentos Juros, Custos E Taxas

Atividade financeira detalhada em 30 de abril de 2025

Baixar:
Não há dados disponíveis
Período Financiador Tipo De Transção Montante (US$)

Footnotes

Ratings

CLASSIFICAÇÕES DA IMPLEMENTAÇÃO

Name Review Date
Procurement Moderately Satisfactory 2025-03-19
Project Management Moderately Satisfactory 2025-03-19
Monitoring and Evaluation Satisfactory 2025-03-19
Overall Implementation Progress (IP) Moderately Satisfactory 2025-03-19
Progress towards achievement of PDO Moderately Satisfactory 2025-03-19
Financial Management Moderately Satisfactory 2025-03-19
Progress towards achievement of PDO Moderately Satisfactory 2025-03-19
Procurement Moderately Satisfactory 2025-03-19
Project Management Moderately Satisfactory 2025-03-19
Financial Management Moderately Satisfactory 2025-03-19
Monitoring and Evaluation Satisfactory 2025-03-19
Overall Implementation Progress (IP) Moderately Satisfactory 2025-03-19

CLASSIFICAÇÕES DAS CONCLUSÕES

Não há dados disponíveis

CLASSIFICAÇÕES DA AVALIAÇÃO INDEPENDENTE

Não há dados disponíveis

Estrutura de Resultados

INDICADORES DO OBJETIVO DE DESENVOLVIMENTO DO PROJETO

INDICADORLINHA DE REFERÊNCIAATUALALVO
  • People provided with access to improved water sourcesValor0.000.00500000.00
    Data15 de fevereiro de 202415 de fevereiro de 202429 de fevereiro de 2028
    Comentário
  • People provided with access to improved water sources - Female (RMS requirement)Valor0.000.000.00
    Data
    Comentário
  • Farmers adopting improved agricultural technologyValor0.00506.00200000.00
    Data30 de junho de 202215 de fevereiro de 202429 de fevereiro de 2028
    Comentário
  • Farmers adopting improved agricultural technology - FemaleValor0.000.000.00
    Data
    Comentário
  • Land area under sustainable landscape management practicesValor0.000.008000.00
    Data30 de junho de 202315 de fevereiro de 202429 de fevereiro de 2028
    Comentário

INDICADORES DE RESULTADOS INTERMEDIÁRIOS

INDICADORLINHA DE REFERÊNCIAATUALALVO
  • Number of institutions providing veterinary services/certifications strengthenedValor0.000.0015.00
    Data30 de junho de 202215 de fevereiro de 202429 de fevereiro de 2028
    Comentário
  • Proportion of contracts awarded to female friendly contractorsValor0.0029.0020.00
    Data26 de julho de 202215 de fevereiro de 202429 de fevereiro de 2028
    Comentário
  • Livestock managers with increased productivityValor0.000.0070.00
    Data2 de janeiro de 202315 de fevereiro de 202429 de fevereiro de 2028
    Comentário
  • Women’s share of leadership positions in Village Development Committees (VDCs)Valor2.002.0020.00
    Data1 de agosto de 202215 de fevereiro de 202429 de fevereiro de 2028
    Comentário
  • Female share of livestock managers with increased productivityValor0.000.000.00
    Data
    Comentário
  • Grievances registered related to delivery of project benefits that are addressedValor0.00100.0075.00
    Data1 de março de 202315 de fevereiro de 202429 de fevereiro de 2028
    Comentário
  • Community Investment Plans DevelopedValor0.000.00150.00
    Data28 de fevereiro de 202315 de fevereiro de 202429 de fevereiro de 2028
    Comentário
  • Number of line Ministry buildings, laboratories and offices constructedValor16.0016.0022.00
    Data28 de fevereiro de 202315 de fevereiro de 202429 de fevereiro de 2028
    Comentário
  • Number of line ministry buildings, laboratories, offices renovatedValor17.0021.0027.00
    Data28 de fevereiro de 202315 de fevereiro de 202429 de fevereiro de 2028
    Comentário
  • Land area under invasive species management techniquesValor0.000.001000.00
    Data2 de janeiro de 202315 de fevereiro de 202429 de fevereiro de 2028
    Comentário
  • Number of functional Farmer Field Schools establishedValor0.000.00150.00
    Data30 de junho de 202315 de fevereiro de 202429 de fevereiro de 2028
    Comentário
  • Efficient and functional web-based Management Information System (MIS)Valor1.000.002.00
    Data13 de abril de 202215 de fevereiro de 202429 de fevereiro de 2028
    Comentário
  • New water points constructed to reduce the risk of water shortages in drought-prone rural areasValor0.000.00100.00
    Data30 de junho de 202315 de fevereiro de 202429 de fevereiro de 2028
    Comentário
  • Agricultural land area with soil and water conservation measuresValor0.000.003000.00
    Data13 de abril de 202215 de fevereiro de 202429 de fevereiro de 2028
    Comentário
  • Number of Animals that received veterinary servicesValor0.00131769.001800000.00
    Data2 de janeiro de 202315 de fevereiro de 202429 de fevereiro de 2028
    Comentário
  • Beneficiaries that feel project investments reflected their needsValor0.000.0070.00
    Data13 de abril de 202215 de fevereiro de 202429 de fevereiro de 2028
    Comentário
  • Existing water points rehabilitated to reduce the risk of water shortages in drought-prone rural areasValor0.003.0050.00
    Data30 de junho de 202315 de fevereiro de 202429 de fevereiro de 2028
    Comentário
  • Forest area restoredValor0.000.00500.00
    Data1 de março de 202315 de fevereiro de 202429 de fevereiro de 2028
    Comentário
  • Number of Community Animal Health workers (CAHWs) trainedValor0.00160.00500.00
    Data2 de janeiro de 202315 de fevereiro de 202429 de fevereiro de 2028
    Comentário
  • Number of government staff gaining capacity to plan and design climate-resilient infrastructureValor0.0094.00175.00
    Data30 de junho de 202215 de fevereiro de 202429 de fevereiro de 2028
    Comentário
  • Project Implementation Units (PIUs) staffedValor4.005.006.00
    Data13 de abril de 202215 de fevereiro de 202429 de fevereiro de 2028
    Comentário
  • Female number of government staff gaining capacity to plan and design climate-resilient infrastructureValor0.000.000.00
    Data
    Comentário
  • Female number of Community Animal Health workers (CAHWs) trainedValor0.000.000.00
    Data
    Comentário
  • Female share of PIU staff, interns & seconded staff at line ministries & other water institutionsValor12.0024.0030.00
    Data28 de fevereiro de 202315 de fevereiro de 202429 de fevereiro de 2028
    Comentário