Skip to Main Navigation

AF Irrigation Restoration and Development Project

Development Objective

Improve access to irrigation in targeted areas and strengthen capacity for water resources management.

Key Details

Project Details

  • P122235

  • Active

  • Sana Kh.H. Agha Al Nimer , Mir Ahmad, Francois Onimus

  • Islamic Republic of Afghanistan,Ministry of Energy and Water (MEW)

  • Afghanistan

  • October 4, 2010

  • (as of board presentation)

    April 28, 2011

  • June 15, 2011

  • US$ 148.70 million

  • Ministry of Energy and Water (MEW)

  • South Asia

  • 2011

  • US$ 146.20 million

  • A

  • February 1, 2022

  • June 30, 2025

  • BANK APPROVED

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
Borrower/Recipient 2.50
Afghanistan Resilience Trust Fund 48.40
IDA Grant 97.80

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment N/A
IDA Commitment 97.80
IBRD + IDA Commitment 97.80
Lending Instrument
Grant Amount 48.40
Total Project Cost** 148.70

Summary Status of World Bank Financing (US$ Millions) as of February 28, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of February 28, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)
Aug 13, 2020 IDA-H6810 Loan Disb 1,029,080.60
Aug 29, 2016 IDA-H6810 Loan Disb 772,820.30
Dec 19, 2016 IDA-H6810 Loan Disb 607,326.56
Apr 19, 2017 IDA-H6810 Loan Disb 33,952.50
Jun 21, 2017 IDA-H6810 Loan Disb 682,161.10
Mar 23, 2016 IDA-H6810 Loan Disb 1,877,710.40
Mar 30, 2016 IDA-H6810 Loan Disb 480,529.44
Nov 15, 2016 IDA-H6810 Loan Disb 969,790.60
May 2, 2016 IDA-H6810 Loan Disb 355,693.10
Nov 30, 2016 IDA-H6810 Loan Disb 348,166.06
Jun 13, 2016 IDA-H6810 Loan Disb 273,080.28
Sep 26, 2016 IDA-H6810 Loan Disb 1,562,671.00
Dec 13, 2016 IDA-H6810 Loan Disb 1,212,852.80
May 31, 2016 IDA-H6810 Loan Disb 964,829.94
Oct 5, 2016 IDA-H6810 Loan Disb 1,438,029.40
Nov 28, 2016 IDA-H6810 Loan Disb 1,111,864.50
Jun 29, 2016 IDA-H6810 Loan Disb 342,305.25
Jun 29, 2016 IDA-H6810 Loan Disb 130,440.23
Jun 22, 2016 IDA-H6810 Loan Disb 1,610,505.00
Dec 28, 2016 IDA-H6810 Loan Disb 475,463.66
Jan 25, 2017 IDA-H6810 Loan Disb 906,006.80
Jun 29, 2015 IDA-H6810 Loan Disb 2,339,790.00
Jun 29, 2015 IDA-H6810 Loan Disb 61,875.27
May 6, 2015 IDA-H6810 Loan Disb 927,592.20
Aug 4, 2015 IDA-H6810 Loan Disb 282,364.53
May 26, 2015 IDA-H6810 Loan Disb 456,572.78
Jun 23, 2015 IDA-H6810 Loan Disb 439,314.88
Jun 8, 2015 IDA-H6810 Loan Disb 689,609.44
Dec 30, 2015 IDA-H6810 Loan Disb 904,286.10
Oct 6, 2015 IDA-H6810 Loan Disb 435,973.88
Oct 21, 2015 IDA-H6810 Loan Disb 286,530.53
Dec 16, 2015 IDA-H6810 Loan Disb 364,774.20
Apr 28, 2011 IDA-H6810 Loan Commitment 97,800,000.00
Aug 27, 2021 IDA-H6810 Loan Disb -190,672.30
Nov 24, 2020 IDA-H6810 Loan Disb 3,750.46
Nov 24, 2020 IDA-H6810 Loan Disb 1,000,000.00
Jun 29, 2021 IDA-H6810 Loan Disb 222,561.02
Jun 25, 2020 IDA-H6810 Loan Cancel 2,000,072.50
Jun 24, 2020 IDA-H6810 Loan Disb 257,185.05
Dec 7, 2015 IDA-H6810 Loan Disb 700,484.70
Sep 15, 2015 IDA-H6810 Loan Disb 1,302,255.90
Nov 30, 2015 IDA-H6810 Loan Disb 1,610,505.00
Apr 26, 2016 IDA-H6810 Loan Disb 1,448,252.00
Apr 21, 2014 IDA-H6810 Loan Disb 2,984,091.00
Apr 15, 2014 IDA-H6810 Loan Disb 503,638.10
May 6, 2014 IDA-H6810 Loan Disb 1,188,822.80
Jun 30, 2014 IDA-H6810 Loan Disb 740,196.20
Jun 30, 2014 IDA-H6810 Loan Disb 164,381.80
Jun 10, 2014 IDA-H6810 Loan Disb 563,418.94
Dec 29, 2014 IDA-H6810 Loan Disb 2,339,790.00
Aug 18, 2014 IDA-H6810 Loan Disb 356,279.70
Sep 2, 2014 IDA-H6810 Loan Disb 215,248.20
Oct 21, 2014 IDA-H6810 Loan Disb 380,980.12
Jan 22, 2015 IDA-H6810 Loan Disb 1,032,752.75
Nov 18, 2014 IDA-H6810 Loan Disb 1,287,194.10
Jan 5, 2015 IDA-H6810 Loan Disb 361,720.84
Aug 5, 2013 IDA-H6810 Loan Disb 652,519.50
Dec 3, 2014 IDA-H6810 Loan Disb 1,614,298.90
Sep 3, 2013 IDA-H6810 Loan Disb 469,886.10
Nov 6, 2013 IDA-H6810 Loan Disb 1,756,242.00
Dec 3, 2013 IDA-H6810 Loan Disb 60,479.41
Nov 18, 2013 IDA-H6810 Loan Disb 995,028.56
Dec 2, 2013 IDA-H6810 Loan Disb 166,264.20
Feb 4, 2014 IDA-H6810 Loan Disb 2,923,023.20
Dec 11, 2013 IDA-H6810 Loan Disb 2,984,090.00
Dec 21, 2017 IDA-H6810 Loan Disb 2,884,848.80

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Progress towards achievement of PDO Satisfactory 2020-06-23
Counterpart Funding Satisfactory 2020-06-23
Financial Management Satisfactory 2020-06-23
Overall Implementation Progress (IP) Moderately Satisfactory 2020-06-23
Project Management Moderately Satisfactory 2020-06-23
Monitoring and Evaluation Moderately Satisfactory 2020-06-23
Procurement Moderately Satisfactory 2020-06-23

COMPLETION RATINGS

INDICATORIMPLEMENTATION COMPLETION & RESULTS REPORT: 01-12-2022
OutcomesSubstantial
Risk to Development Outcome
Bank PerformanceModerately Satisfactory
Borrower Performance
Government Performance
Implementing Agency

INDEPENDENT EVALUATION RATINGS

INDICATORICR REVIEW: PROJECT PERFORMANCE ASSESSMENT REPORT:
Outcome RatingSatisfactory N/a
Risk To Development OutcomeN/a
Bank PerformanceModerately SatisfactoryN/a
Borrower PerformanceN/a
Government PerformanceNot RatedN/a
Implementing AgencyN/a
Icr QualitySubstantialN/a
M&e QualityModestN/a

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • Water Disaster Risk Management Plan (including flood/drought forecasting and early warning systems), two basin development plans, and the river bank protection plan for the Panju-Amu river preparedValueNoNoYes
    DateJanuary 31, 2012December 31, 2020March 23, 2016
    Comment
  • Dams which have undergone dam safety reviewValue0.0010.003.00
    DateMarch 21, 2012December 31, 2020March 26, 2014
    Comment
  • Water users provided with irrigation and drainage services - female (number)Value0.00302072.00200000.00
    DateMarch 31, 2011December 31, 2020December 31, 2015
    Comment
  • Area provided with irrigation and drainage services â?? Improved (ha)Value75000.00284391.00215000.00
    DateMarch 31, 2011December 31, 2020December 31, 2015
    Comment
  • Female beneficiariesValue100000.0052.000.00
    DateJanuary 31, 2012March 31, 2018
    Comment
  • Area provided with irrigation and drainage services - New (ha)Value75000.00284391.00215000.00
    DateMarch 31, 2011December 31, 2020December 31, 2015
    Comment
  • Water users provided with new/improved irrigation and drainage services (number)Value0.00580908.00385000.00
    DateMarch 31, 2011December 31, 2020December 31, 2015
    Comment
  • Mirabs strengthenedValue0.00215.00212.00
    DateDecember 31, 2015December 31, 2020February 15, 2016
    Comment
  • Area provided with irrigation and drainage services (ha)Value75000.00284391.00215000.00
    DateMarch 31, 2011December 31, 2020December 31, 2015
    Comment
  • Direct project beneficiariesValue100000.00611484.00400000.00
    DateJanuary 31, 2012December 31, 2020December 31, 2015
    Comment

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • Mandate for irrigation between MAIL and MEW clarifiedValueNoYesYes
    DateApril 5, 2016December 31, 2020April 5, 2016
    Comment
  • Irrigation canal rehabiliotatedValue0.002667.00900.00
    DateMarch 31, 2011December 31, 2020February 15, 2016
    Comment
  • Dams having undergone minor dam safety worksValue0.002.002.00
    DateDecember 31, 2015December 31, 2020February 15, 2016
    Comment
  • Transboundary water unit established at MEWValueNoYesYes
    DateMarch 31, 2011December 31, 2020March 23, 2015
    Comment
  • Government staff trained on topics related to river bank protection, dam planning and management, water resources management and development (of which female)Value5.00100.0030.00
    DateDecember 31, 2015December 31, 2020February 15, 2016
    Comment
  • River bank protected from erosionValue0.0045.8126.30
    DateDecember 31, 2015December 31, 2020February 15, 2016
    Comment
  • Dam safety and O&M guidelines and manuals preparedValue0.001.000.00
    DateDecember 31, 2015December 31, 2020February 15, 2016
    Comment
  • Hydromet/weather /snow measurement stations installedValue127.00216.00230.00
    DateMarch 31, 2011December 31, 2020February 15, 2016
    Comment