Financier | Commitments |
---|---|
IDA Credit | 50.00 |
Borrower/Recipient | 0.60 |
P148974
Closed
Mehmet Ozlu
N/A
April 2, 2014
(as of board presentation)
May 29, 2014
N/A
US$ 50.60 million
N/A
2014
US$ 50.00 million
B
June 24, 2014
N/A
Yes
BANK APPROVED
Financier | Commitments |
---|---|
IDA Credit | 50.00 |
Borrower/Recipient | 0.60 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | N/A |
IDA Commitment | 50.00 |
IBRD + IDA Commitment | 50.00 |
Lending Instrument | |
---|---|
Grant Amount | N/A |
Total Project Cost** | 50.60 |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Roads in good and fair condition as a share of total classified roads | Value | 36.00 | 27.00 | 69.00 |
Date | April 30, 2010 | February 28, 2014 | December 31, 2015 | |
Comment | 155 km | 429 km | 296 km |
Number of people in urban areas provided with access to all-season roads within a 500 meter range under the project | Value | 498152.00 | 1799671.00 | 736307.00 |
Date | April 30, 2010 | February 28, 2014 | December 31, 2015 | |
Comment | 21% | 65% | 33% |
Waste disposed at landfills as percent of total waste generated in LGAs | Value | 0.00 | 55.00 | 60.00 |
Date | April 30, 2010 | February 28, 2014 | December 31, 2017 | |
Comment |
People with access to improved bus stations, terminals or lorry stands (number) | Value | 0.00 | 603817.00 | 974000.00 |
Date | April 30, 2010 | February 28, 2014 | December 31, 2017 | |
Comment |
Female beneficiaries | Value | 0.00 | 49.00 | 49.00 |
Date | April 30, 2010 | February 28, 2014 | December 31, 2017 | |
Comment |
Non-rural roads rehabilitated or constructed to paved standard (km) | Value | 0.00 | 123.00 | 152.00 |
Date | June 30, 2009 | February 28, 2014 | December 31, 2017 | |
Comment |
Direct project beneficiaries | Value | 0.00 | 620837.00 | 1483000.00 |
Date | April 30, 2010 | February 28, 2014 | December 31, 2017 | |
Comment |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Roads rehabilitated, Non-rural | Value | 0.00 | 123.00 | 141.00 |
Date | April 30, 2010 | February 28, 2014 | December 31, 2015 | |
Comment |
Drainage constructed/rehabilitated | Value | 0.00 | 15.10 | 19.00 |
Date | April 30, 2010 | February 28, 2014 | December 31, 2017 | |
Comment |
Waste collection points constructed or rehabilitated (number) | Value | 0.00 | 259.00 | 250.00 |
Date | April 30, 2010 | February 28, 2014 | December 31, 2017 | |
Comment |
Number of landfills and cells constructed or improved | Value | 0.00 | 3.00 | 5.00 |
Date | April 30, 2010 | February 28, 2014 | December 31, 2017 | |
Comment | 0 cubic meters | 4 cells | 15 cells |
Bus stations, terminals or lorry stands constructed or improved (number, capacity) | Value | 0.00 | 6.00 | 12.00 |
Date | April 30, 2010 | February 28, 2014 | December 31, 2017 | |
Comment | 660 vehicles | 1100 vehicles |
LGAs with up-to-date strategic urban development plans (number) | Value | 0.00 | 3.00 | 7.00 |
Date | April 30, 2010 | February 28, 2014 | December 31, 2017 | |
Comment |
Up-to-date property valuations (number, and % of all properties in LGAs) | Value | 45000.00 | 135715.00 | 470000.00 |
Date | April 30, 2010 | February 28, 2014 | December 31, 2017 | |
Comment | 10% | 30% | 100% |
Amount of property tax collected, and as percentage of property taxes billed (Billion Tanzanian Shillings, %) | Value | 1.00 | 0.00 | 4.50 |
Date | April 30, 2010 | February 28, 2014 | December 31, 2017 | |
Comment | 35% | 65% | 75% |
Increase in own-source revenue over base year | Value | 0.00 | 67.00 | 60.00 |
Date | April 30, 2010 | February 28, 2014 | December 31, 2017 | |
Comment |
Amount spent on operation and maintenance as percent of total municipal expenditure (%) | Value | 8.00 | 17.00 | 20.00 |
Date | April 30, 2010 | February 28, 2014 | December 31, 2017 | |
Comment |
Amount spent / annual budget for maintenance of road infrastructure | Value | 80.00 | 86.00 | 95.00 |
Date | April 30, 2010 | February 28, 2014 | December 31, 2015 | |
Comment |
Percent of O&M cost for solid waste management recovered from direct fees and charges | Value | 0.00 | 30.00 | 20.00 |
Date | April 30, 2010 | February 28, 2014 | December 31, 2017 | |
Comment |
Progress in preparing General Planning Schemes in LGAs | Value | 0.00 | 0.00 | 100.00 |
Date | July 1, 2014 | December 31, 2017 | ||
Comment |
Percent of O&M cost for bus stations, terminals or lorry stands recovered from direct fees and charges | Value | 0.00 | 85.00 | 70.00 |
Date | April 30, 2010 | February 28, 2014 | December 31, 2017 | |
Comment |