Second Lao Environment and Social Project (Additional Financing to the Protected Area and Wildlife Project)

Development Objective

The revised PDO and the revised Global Environment Objective (GEO) are to help strengthen selected environmental protection management systems, specifically for protected areas conservation, enforcement of wildlife laws and environmental assessment management.

Key Details

Project Details

  • P152066

  • Closed

  • Jean-Michel Pavy , Ngozi Obi Malife, Manoly Sisavanh

  • N/A

  • US$ 15.00 million

  • B

  • Not Applicable

  • June 30, 2023

  • TBD

  • BANK APPROVED

  • P128393

  • July 16, 2024

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
IDA Credit 15.00
Borrower/Recipient 1.60

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment N/A
IDA Commitment 15.00
IBRD + IDA Commitment 15.00
Lending Instrument
Grant Amount N/A
Total Project Cost** 16.60

Summary Status of World Bank Financing (US$ Millions) as of June 30, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of June 30, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)

Footnotes

Ratings

IMPLEMENTATION RATINGS

No data available.

COMPLETION RATINGS

No data available.

INDEPENDENT EVALUATION RATINGS

No data available.

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • Percentage increase of a score of functional capacity of Sub-project delivery agencies (SDA) and of the Environment Protection Fund(EPF)Value0.000.0020.00
    DateSeptember 30, 2014June 30, 2021
    Comment
  • Projects registered in environment impact Category 1 that have up-to-date compliance monitoring report published in the DESIA websiteValue0.000.0045.00
    DateSeptember 30, 2014June 30, 2021
    CommentUnit is % and not NumberAverage hydro, transport, road
  • Villages organizations within, or adjacent to, PAs supported by the Project that meet the terms of a conservation agreementValue0.000.00140.00
    DateSeptember 30, 2014June 30, 2021
    Comment
  • Hydro power sectorValue0.000.0060.00
    DateSeptember 30, 2014June 30, 2021
    CommentUnit is % and not Number
  • Mining sectorValue0.000.0040.00
    DateSeptember 30, 2014June 30, 2021
    CommentUnit is % and not Number
  • Road sectorValue0.000.0040.00
    DateSeptember 30, 2014June 30, 2021
    CommentUnit is % and not Number
  • International illegal trade information reports submitted by DOFI to international LE or monitoring agencies, such as TRAFFIC, INTERPOL, ASEAN-WEN, CITESValue0.000.005.00
    DateOctober 1, 2013September 30, 2014June 30, 2021
    Comment
  • Aggregate index of functional capacity of selected protected area & wildlife management institutions (annual)Value17.0017.0033.00
    DateDecember 31, 2013September 30, 2014June 30, 2021
    Comment
  • Nam Et-Phou Louey National Protected Area (NEPL MU)Value24.0024.0036.00
    DateOctober 1, 2013September 30, 2014June 30, 2021
    Comment
  • Watershed Mgmt Protection Authority (WMPA)Value28.0028.0040.00
    DateDecember 31, 2013September 30, 2014June 30, 2021
    Comment
  • Lao Wildlife Enforcement Network (WEN)Value6.006.0036.00
    DateDecember 31, 2013September 30, 2014June 30, 2021
    Comment
  • Dept of Forest Resources Mgmt (DFRM)Value12.0012.0022.00
    DateDecember 31, 2013September 30, 2014June 30, 2021
    Comment

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • Wildlife and threat measuredValue0.00170000.00350000.00
    DateOctober 1, 2013September 30, 2014June 30, 2021
    Comment
  • Gross forest loss rate measuredValue0.000.00336000.00
    DateOctober 1, 2013September 30, 2014June 30, 2021
    Comment
  • In NNT NPAValue0.00438000.00438000.00
    DateOctober 1, 2013September 30, 2014June 30, 2021
    Comment
  • In NEPL NPAValue0.00420000.00420000.00
    DateOctober 1, 2013September 30, 2014June 30, 2021
    Comment
  • In Houaphan ProvinceValue24.0024.0040.00
    DateOctober 1, 2013September 30, 2014June 30, 2021
    Comment
  • In Boulikhamxay ProvinceValue0.000.0040.00
    DateOctober 1, 2013September 30, 2014September 30, 2020
    Comment
  • In Khammouanne ProvinceValue24.0024.0040.00
    DateOctober 1, 2013September 30, 2014September 30, 2020
    Comment
  • HydroValue10.000.0050.00
    DateSeptember 30, 2014June 30, 2021
    Comment
  • MiningValue0.000.0050.00
    DateJune 30, 2021
    Comment
  • RoadValue0.000.0050.00
    DateJune 30, 2021
    Comment
  • Funds mobilized originating from (a) public sources and (b) private sources remitted to EPFValue800.001000.001600.00
    DateSeptember 30, 2013September 30, 2014June 30, 2021
    Comment
  • EPFO staff positions initially funded by the Project which are funded by EPF own fundsValue0.000.008.00
    DateSeptember 30, 2014June 30, 2021
    Comment
  • Public sourceValue350.00350.00700.00
    DateSeptember 30, 2013September 30, 2014June 30, 2021
    Comment
  • Private sourcesValue450.00650.00900.00
    DateSeptember 30, 2013September 30, 2014June 30, 2021
    Comment
  • Areas brought under enhanced biodiversity protection (ha)Value858000.00858000.00128000.00
    DateOctober 1, 2013September 30, 2014September 30, 2020
    Comment
  • Direct project beneficiariesValue0.000.001040.00
    DateOctober 1, 2013September 30, 2014June 30, 2021
    Commentas measured by additional staff of public and partner institutions having completed basic adaptive training
  • Wildlife trafficking cases recorded in the IMS by POFI in eligible provincesValue29.0029.0059.00
    DateJanuary 1, 2014September 30, 2014June 30, 2021
    Comment
  • Indicator of gradual development of a national system plan for conservation and protection forests development and managementValue0.000.0012.00
    DateOctober 1, 2013September 30, 2014June 30, 2021
    Comment
  • Projects in environment impact Cat 1 and Cat 2 in the provinces targeted by the Project who have a valid Environment Compliance Certificate (ECC)Value0.000.0050.00
    DateOctober 1, 2013September 30, 2014June 30, 2021
    CommentAverage hydro, mining, road
  • Direct project beneficiary recipient of livelihood or conservation grants (of which women or womens' organizations (cum, '000)Value0.000.0036.00
    DateOctober 1, 2013September 30, 2014June 30, 2021
    Comment
  • Trend of proportion of household income from non-timber forest product (wild fish, wildlife, bamboo shoots, etc.)Value0.000.000.00
    DateNovember 22, 2013September 30, 2014September 30, 2020
    Comment
  • Villages that (a) have an approved PLUP, (b) have signed a NPA Conservation Agreement, (b) where a functional PES mechanism is in place.Value0.000.00105.00
    DateOctober 1, 2013September 30, 2014September 30, 2020
    Comment
  • Area within PAs where (a) the status of the population of selected mammals and threat (b) gross forest loss rate are measuredValue0.000.00686000.00
    DateOctober 1, 2013September 30, 2014September 30, 2020
    Comment
  • Area where gross forest loss rate in NPAs is measuredValue0.00858000.00858000.00
    DateOctober 1, 2013September 30, 2014June 30, 2021
    Comment
  • Number of POFI patrols and inspections that include wildlife crimes (of which in border areas or to control international trade)Value0.000.00120.00
    DateOctober 1, 2013September 30, 2014June 30, 2021
    Comment
  • Value0.002.003.00
    DateOctober 1, 2013September 30, 2014September 30, 2020
    Comment
  • “Deliverables” proposed in the Project Annual Work Plan (AWP) completed each yearValue50.0080.00100.00
    DateOctober 1, 2013September 30, 2014June 30, 2021
    Comment
  • Score of management effectiveness (annual) for NNT watershedValue35.0035.0050.00
    DateOctober 1, 2013May 9, 2014September 30, 2020
    Comment
  • Score of management effectiveness (annual) for NEPLValue38.0040.0053.00
    DateOctober 1, 2013May 9, 2014September 30, 2020
    Comment
  • Female beneficiariesValue0.000.0020.00
    DateOctober 1, 2013September 30, 2014June 30, 2021
    Comment
  • DOFI CentralValue3.003.0011.00
    DateJanuary 1, 2014September 30, 2014June 30, 2021
    Comment
  • Bolikhamxay Province POFIValue14.0014.0022.00
    DateJanuary 1, 2014September 30, 2014June 30, 2021
    Comment
  • Houaphan Province POFIValue7.007.0014.00
    DateJanuary 1, 2014September 30, 2014June 30, 2021
    Comment
  • Khammouanne province POFIValue5.005.0012.00
    DateJanuary 1, 2014September 30, 2014June 30, 2021
    Comment
  • Direct project beneficiary recipients - NNT watershedValue0.000.0013.00
    DateOctober 1, 2013September 30, 2014June 30, 2021
    Comment
  • Direct project beneficiary recipients - NEPLValue0.000.0016.00
    DateOctober 1, 2013September 30, 2014June 30, 2021
    Comment
  • In NNT NPAValue0.000.0065.00
    DateOctober 1, 2013September 30, 2014June 30, 2021
    Comment
  • In NEPL NPAValue0.000.0040.00
    DateOctober 1, 2013September 30, 2014June 30, 2021
    Comment