Project for Strengthening Public Financial Management

Resumo*

The objective of the Strengthening Public Financial Management Project for Micronesia is to improve tax administration and the completeness, reliability and timeliness of financial reports of the National and State Governments. The project has 5 components. 1. Strengthening the public financial management environment component will strengthen the Public Financial Management (PFM) environment by ensuring that the legal and regulatory framework and...

* Os resumos dos projetos são tirados do PAD, SAR ou PGD e talvez não reflitam com exatidão a natureza atual do projeto

Ver mais

Objetivo de Desenvolvimento

The objective of the project is to improve tax administration and the completeness, reliability and timeliness of financial reports of the National and State Governments.

Chave Detalhes

Projeto Detalhes

  • P161969

  • Active

  • Bonnie Sirois , Elena Georgieva-Andonovska, Pike Aye

  • The Federated States of Micronesia

  • Micronésia, Federação dos Estados da

  • 1 de outubro de 2017

  • (conforme apresentação da Diretoria Executiva)

    30 de maio de 2018

  • 1 de outubro de 2018

  • US$ 11.50 milhões

  • Department of Finance and Administration

  • Leste Asiático e Pacífico

  • 2018

  • US$ 11.00 milhões

  • B

  • 19 de abril de 2024

  • 25 de agosto de 2025

  • Yes

  • BANK APPROVED

  • Notes

Finanças

Plano De Financiamento (US$ Milhões)

Não há dados disponíveis
Financiador Compromissos
Borrower/Recipient 0.50
IDA Grant 11.00

Financiamento total do projeto (US$ milhões)

Linha de produtos BIRD/AID
Compromisso do BIRD N/A
Compromissos da AID 11.00
Compromisso do BIRD + AID 11.00
Instrumento de empréstimo
Montante do subsídio N/A
Custo total do projeto** 11.50

Resumo da situação do financiamento do Banco Mundial (em US$ milhões) em 31 de março de 2025

Baixar:
Não há dados disponíveis
Financiador Data Da Aprovação Data De Encerramento Principal Desembolsado Pagamentos Juros, Custos E Taxas

Atividade financeira detalhada em 31 de março de 2025

Baixar:
Não há dados disponíveis
Período Financiador Tipo De Transção Montante (US$)

Footnotes

Ratings

CLASSIFICAÇÕES DA IMPLEMENTAÇÃO

Name Review Date
Overall Safeguards Rating Satisfactory 2024-12-27
Procurement Moderately Satisfactory 2024-12-27
Progress towards achievement of PDO Moderately Satisfactory 2024-12-27
Financial Management Satisfactory 2024-12-27
Monitoring and Evaluation Satisfactory 2024-12-27
Overall Implementation Progress (IP) Moderately Satisfactory 2024-12-27
Project Management Moderately Satisfactory 2024-12-27

CLASSIFICAÇÕES DAS CONCLUSÕES

Não há dados disponíveis

CLASSIFICAÇÕES DA AVALIAÇÃO INDEPENDENTE

Não há dados disponíveis

Estrutura de Resultados

INDICADORES DO OBJETIVO DE DESENVOLVIMENTO DO PROJETO

INDICADORLINHA DE REFERÊNCIAATUALALVO
  • PDO-1: In-year budget reports prepared and published by National and all four State governmentsValorIn-year budget reports not prepared and not publisNot yetIn-year budget reports prepared and cleared for pu
    Data29 de junho de 201815 de março de 202430 de setembro de 2024
    Comentário
  • PDO-2: Revenue Management System installed and in use by CTA for improved revenue accountingValor“C” score in 2016 self-assessment for PI-20.3Year 1 and 2 targets achieved. Year 3 target in prCriteria for “B” score of PI-20.3 met
    Data29 de junho de 201815 de março de 202430 de setembro de 2024
    Comentário
  • PDO-3: New FMIS used by all five govts for recording and reporting budget, revenue and expenditureValorFundWare accounting system being phased outNot yetNew FMIS used for preparation of budget for FY2024
    Data29 de junho de 201815 de março de 202430 de setembro de 2024
    Comentário

INDICADORES DE RESULTADOS INTERMEDIÁRIOS

INDICADORLINHA DE REFERÊNCIAATUALALVO
  • IR-1: New chart of accounts for all govts for better management, financial and statistical reportingValor"C" score in 2016 self-assessment. Functional clasYear 1 and 2 targets met.“A” score criteria for PI-4 met
    Data29 de junho de 201815 de março de 202430 de setembro de 2024
    Comentário
  • IR-3: Financial data integrity maintained to meet “B” score for PI-27Valor“B+” score for PI-27 in 2016 self-assessmentNo changeCriteria for "B" score for PI-27 fully met
    Data29 de junho de 201815 de março de 202430 de setembro de 2024
    Comentário
  • IR-4: Taxpayer accounting in Customs and Tax Administration (CTA) automatedValorNo RMS in placeYear 1 and 2 target met.Year 3 and 4 targets in prAll modules of RMS implemented and in use
    Data29 de junho de 201815 de março de 202430 de setembro de 2024
    Comentário
  • IR-5: Competency framework specifying minimum skillsets adopted and used for all PFM related jobsValorNo competencies defined for PFM related rolesY1 target partially complete, pending gender analyCompetency framework specifying minimum skillsets
    Data29 de junho de 201815 de março de 202430 de setembro de 2024
    Comentário
  • IR-2: Procedures Manuals updated with detailed guidance for all five governmentsValorOperations Procedure not covering all required areNot yetProcedures Manuals in place with detailed guidance
    Data29 de junho de 201815 de março de 202430 de setembro de 2024
    Comentário
  • IR-6: External training program partnerships for PFM related certification and degree coursesValorNo external training program partnerships in placeTarget has been met.Four (4) external training program partnerships fo
    Data29 de junho de 201815 de março de 202430 de setembro de 2024
    Comentário
  • IR-7: Number of staff completing external training programs in PFM related disciplinesValor0.0021.0050.00
    Data29 de junho de 201815 de março de 202430 de setembro de 2024
    Comentário
  • Of which femaleValor0.000.000.00
    Data
    Comentário
  • IR-8: Gender-sensitive communication conducted for the project for awareness and building ownershipValorNo communication strategy; regular updates and infNot yetDoFA website enhanced and regularly updated with i
    Data29 de junho de 201815 de março de 202430 de setembro de 2024
    Comentário
  • IR-9: Transparency and citizen engagement in budget preparation and execution by National governmentValorDoFA website exists but does not provide platform Yr.1 target achieved.DoFA website includes functionality to capture cit
    Data30 de abril de 201815 de março de 202430 de setembro de 2024
    Comentário