Skip to Main Navigation

Regional Climate Resilience Program for Eastern and Southern Africa 1 Project (RCRP1)

Resumo*

This Additional Financing (AF) of the Regional Climate Resilience Program (RCRP-1) (P180171) concerns the scaling up of activities in Comoros and Madagascar, two of the participating countries of the parent project. In Comoros, the AF finances infrastructure works that are being prepared under the parent project, on flood risk management and coastal protection measures. In Madagascar, the AF finances the preparation of critical studies for a new storage...

* Os resumos dos projetos são tirados do PAD, SAR ou PGD e talvez não reflitam com exatidão a natureza atual do projeto

Ver mais

Objetivo de Desenvolvimento

To improve the management of water-related climate impacts in Eastern and Southern Africa, and, in case of an Eligible Crisis or Emergency, to respond promptly and effectively to it.

Chave Detalhes

Projeto Detalhes

  • P180171

  • Active

  • Laura Bonzanigo , Arati Belle, Deo-Marcel Niyungeko, Pierre Boulenger, Juan Casanova Anoll

  • Republic of South Sudan,Union of Comoros,Southern African Development Community,Republic of Mozambique,Republic of Madagascar,Eastern Nile Technical Regional Office

  • Eastern and Southern Africa

  • 30 de novembro de 2022

  • (conforme apresentação da Diretoria Executiva)

    24 de maio de 2023

  • 31 de julho de 2023

  • US$ 250.00 milhões

  • Ministry of Water Resources and Irrigation,Ministry of Land-Use and Urban Planning,Southern African Development Community,Agence Routiere,Ministry of Public Works, Housing, and Water Resources,Cellule de Prévention et Gestion des Urgences (CPGU),Eastern Nile Technical Regional Office (ENTRO)

  • Eastern and Southern Africa

  • 2023

  • US$ 382.40 milhões

  • N/A

  • High

  • 29 de dezembro de 2028

  • Yes

  • BANK APPROVED

  • 19 de fevereiro de 2024

  • Notes

Finanças

Plano De Financiamento (US$ Milhões)

Não há dados disponíveis
Financiador Compromissos
IDA Credit 28.00
IDA Grant 354.40

Financiamento total do projeto (US$ milhões)

Linha de produtos BIRD/AID
Compromisso do BIRD N/A
Compromissos da AID 382.40
Compromisso do BIRD + AID 382.40
Instrumento de empréstimo
Montante do subsídio N/A
Custo total do projeto** 250.00

Resumo da situação do financiamento do Banco Mundial (em US$ milhões) em 30 de abril de 2025

Baixar:
Não há dados disponíveis
Financiador Data Da Aprovação Data De Encerramento Principal Desembolsado Pagamentos Juros, Custos E Taxas

Atividade financeira detalhada em 30 de abril de 2025

Baixar:
Não há dados disponíveis
Período Financiador Tipo De Transção Montante (US$)

Footnotes

Ratings

CLASSIFICAÇÕES DA IMPLEMENTAÇÃO

Name Review Date
Procurement Moderately Satisfactory 2025-03-03
Financial Management Moderately Satisfactory 2025-03-03
Procurement Moderately Satisfactory 2025-03-03
Project Management Satisfactory 2025-03-03
Progress towards achievement of PDO Satisfactory 2025-03-03
Project Management Satisfactory 2025-03-03
Monitoring and Evaluation Satisfactory 2025-03-03
Overall Implementation Progress (IP) Moderately Satisfactory 2025-03-03
Financial Management Moderately Satisfactory 2025-03-03
Progress towards achievement of PDO Satisfactory 2025-03-03
Overall Implementation Progress (IP) Moderately Satisfactory 2025-03-03
Monitoring and Evaluation Satisfactory 2025-03-03

CLASSIFICAÇÕES DAS CONCLUSÕES

Não há dados disponíveis

CLASSIFICAÇÕES DA AVALIAÇÃO INDEPENDENTE

Não há dados disponíveis

Estrutura de Resultados

INDICADORES DO OBJETIVO DE DESENVOLVIMENTO DO PROJETO

INDICADORLINHA DE REFERÊNCIAATUALALVO
  • Of which refugeesValor0.000.0070000.00
    Data3 de julho de 20238 de fevereiro de 202429 de dezembro de 2028
    Comentário
  • Of which Internally Displaced PeopleValor0.000.0056000.00
    Data3 de julho de 20238 de fevereiro de 202429 de dezembro de 2028
    Comentário
  • ComorosValor0.000.00150000.00
    Data3 de julho de 20238 de fevereiro de 202429 de dezembro de 2028
    Comentário
  • People with increased protection to climate shocks (% of which women, % of which refugees, % of which IDPs)Valor0.000.001000000.00
    Data3 de julho de 20238 de fevereiro de 202429 de dezembro de 2028
    Comentário
  • Regional knowledge sharing events organized to support regional integration on water-related climate impactsValor0.000.0010.00
    Data3 de julho de 20238 de fevereiro de 202429 de dezembro de 2028
    Comentário
  • Land area benefiting from increased flood protectionValor0.000.00500000.00
    Data3 de julho de 20238 de fevereiro de 202429 de dezembro de 2028
    Comentário
  • % of which in transboundary basinsValor0.000.00100.00
    Data3 de julho de 20238 de fevereiro de 202429 de dezembro de 2028
    Comentário
  • South SudanValor0.000.00400000.00
    Data3 de julho de 20238 de fevereiro de 202429 de dezembro de 2028
    Comentário
  • MozambiqueValor0.000.00100000.00
    Data3 de julho de 20238 de fevereiro de 202429 de dezembro de 2028
    Comentário
  • Improved regional information systems in use for decision making related to droughts, flood and/or cyclonesValor0.000.001.00
    Data3 de julho de 20238 de fevereiro de 202429 de dezembro de 2028
    Comentário
  • Mechanism for climate resilient maintenance of hydraulic assets developed and/or adopted as part of the project, including plans for financingValor0.000.004.00
    Data5 de junho de 20238 de fevereiro de 202429 de dezembro de 2028
    Comentário
  • People covered with adaptive social protection or information campaigns addressing water related climate risksValor0.000.00630000.00
    Data3 de julho de 20238 de fevereiro de 202429 de dezembro de 2028
    Comentário
  • Of which womenValor0.000.00315000.00
    Data3 de julho de 20238 de fevereiro de 202429 de dezembro de 2028
    Comentário
  • MozambiqueValor0.000.00200000.00
    Data3 de julho de 20238 de fevereiro de 202429 de dezembro de 2028
    Comentário
  • South SudanValor0.000.00280000.00
    Data3 de julho de 20238 de fevereiro de 202429 de dezembro de 2028
    Comentário

INDICADORES DE RESULTADOS INTERMEDIÁRIOS

INDICADORLINHA DE REFERÊNCIAATUALALVO
  • Hydromet stations constructed and/or rehabilitated under the project and functioningValor0.000.00105.00
    Data3 de julho de 20238 de fevereiro de 202429 de dezembro de 2028
    Comentário
  • Bidding documents for priority climate resilient infrastructure investments completed under the project and ready to be launchedValor0.000.0022.00
    Data3 de julho de 20238 de fevereiro de 202429 de dezembro de 2028
    Comentário
  • Change in percentage of sampled women reporting increased preparedness to floods/droughts relative to percentage sampled menValor0.000.0010.00
    Data5 de junho de 20238 de fevereiro de 202428 de dezembro de 2028
    Comentário
  • Grievances that have been satisfactorily resolved at the GRM-level (% submitted by women, % submitted by refugees)Valor0.000.0090.00
    Data3 de julho de 20238 de fevereiro de 202429 de dezembro de 2028
    Comentário
  • MozambiqueValor0.000.0010.00
    Data5 de junho de 20238 de fevereiro de 202428 de dezembro de 2028
    Comentário
  • MadagascarValor0.000.004.00
    Data3 de julho de 20238 de fevereiro de 202429 de dezembro de 2028
    Comentário
  • ComorosValor0.000.003.00
    Data3 de julho de 20238 de fevereiro de 202429 de dezembro de 2028
    Comentário
  • South SudanValor0.000.0010.00
    Data5 de junho de 20238 de fevereiro de 202428 de dezembro de 2028
    Comentário
  • MozambiqueValor0.000.006.00
    Data3 de julho de 20238 de fevereiro de 202429 de dezembro de 2028
    Comentário
  • MadagascarValor0.000.0025.00
    Data3 de julho de 20238 de fevereiro de 202429 de dezembro de 2028
    Comentário
  • Manuals/maps developed for climate sensitive/informed social protection programs approved at the technical levelValor0.000.003.00
    Data30 de junho de 20238 de fevereiro de 202429 de dezembro de 2028
    Comentário
  • MozambiqueValor0.000.0050.00
    Data3 de julho de 20238 de fevereiro de 202429 de dezembro de 2028
    Comentário
  • South SudanValor0.000.0010.00
    Data3 de julho de 20238 de fevereiro de 202429 de dezembro de 2028
    Comentário
  • Multidimensional analysis of adaptive social protection systems producedValor0.000.003.00
    Data3 de julho de 20238 de fevereiro de 202429 de dezembro de 2028
    Comentário
  • South SudanValor0.000.0027.00
    Data3 de julho de 20238 de fevereiro de 202429 de dezembro de 2028
    Comentário
  • ComorosValor0.000.002.00
    Data3 de julho de 20238 de fevereiro de 202429 de dezembro de 2028
    Comentário
  • MadagascarValor0.000.001.00
    Data3 de julho de 20238 de fevereiro de 202429 de dezembro de 2028
    Comentário
  • Improved regional capacity for accessing climate and disasters fundsValorNoNoYes
    Data3 de julho de 20238 de fevereiro de 202429 de dezembro de 2028
    Comentário
  • Manuals/regulations for climate resilient structures developed, approved, adopted or implemented as part of the projectValor0.000.0011.00
    Data3 de julho de 20238 de fevereiro de 202429 de dezembro de 2028
    Comentário
  • MadagascarValor0.000.002.00
    Data3 de julho de 20238 de fevereiro de 202428 de dezembro de 2029
    Comentário
  • ComorosValor0.000.001.00
    Data5 de junho de 20238 de fevereiro de 202428 de dezembro de 2028
    Comentário
  • MozambiqueValor0.000.001.00
    Data3 de julho de 20238 de fevereiro de 202429 de dezembro de 2028
    Comentário
  • MozambiqueValor0.000.003.00
    Data3 de julho de 20238 de fevereiro de 202429 de dezembro de 2028
    Comentário
  • South SudanValor0.000.005.00
    Data3 de julho de 20238 de fevereiro de 202429 de dezembro de 2028
    Comentário
  • ComorosValor0.000.001.00
    Data3 de julho de 20238 de fevereiro de 202429 de dezembro de 2028
    Comentário
  • State and county officials trained on management of flood protection structuresValor0.000.00350.00
    Data3 de julho de 20238 de fevereiro de 202429 de dezembro de 2028
    Comentário
  • MadagascarValor0.000.00150.00
    Data3 de julho de 20238 de fevereiro de 202429 de dezembro de 2028
    Comentário
  • MozambiqueValor0.000.0050.00
    Data3 de julho de 20238 de fevereiro de 202429 de dezembro de 2028
    Comentário
  • South SudanValor0.000.00100.00
    Data5 de junho de 20238 de fevereiro de 202428 de dezembro de 2028
    Comentário
  • ComorosValor0.000.0050.00
    Data3 de julho de 20238 de fevereiro de 202429 de dezembro de 2028
    Comentário
  • Community-level associations established and/or trained on the management of flood protection structuresValor0.000.0010.00
    Data3 de julho de 20238 de fevereiro de 202429 de dezembro de 2028
    Comentário
  • MozambiqueValor0.000.005.00
    Data3 de julho de 20238 de fevereiro de 202429 de dezembro de 2028
    Comentário
  • South SudanValor0.000.005.00
    Data5 de junho de 20238 de fevereiro de 202428 de dezembro de 2028
    Comentário
  • Flood protection infrastructure constructed and/or rehabilitated under the projectValor0.000.00195.00
    Data3 de julho de 20238 de fevereiro de 202429 de dezembro de 2028
    Comentário
  • MozambiqueValor0.000.0080.00
    Data3 de julho de 20238 de fevereiro de 202429 de dezembro de 2028
    Comentário
  • South SudanValor0.000.00115.00
    Data3 de julho de 20238 de fevereiro de 202429 de dezembro de 2028
    Comentário
  • Critical water retention and storage infrastructure with improved safety for managing drought and floodsValor0.000.00300240000.00
    Data3 de julho de 20238 de fevereiro de 202429 de dezembro de 2028
    Comentário
  • MozambiqueValor0.000.00300000000.00
    Data3 de julho de 20238 de fevereiro de 202429 de dezembro de 2028
    Comentário
  • South SudanValor0.000.00240000.00
    Data3 de julho de 20238 de fevereiro de 202429 de dezembro de 2028
    Comentário
  • Women’s share of leadership and technical positions in institutions governing water resource management (percentage change)Valor0.000.005.00
    Data5 de junho de 20238 de fevereiro de 202428 de dezembro de 2028
    Comentário