Vietnam Renewable Energy Development Project

Overview

NOTICE AT-A-GLANCE

  • P103238

  • Vietnam Renewable Energy Development Project

  • Viet Nam

  • OP00031042

  • Invitation for Bids

  • Published

  • 03/TB-NMNN

  • International Competitive Bidding

  • English

  • Jan 21, 2015

CONTACT INFORMATION

  • Nam Mo & Nam Non Hydropower Joint Stock Company

  • Dao Duy Tan

  • No.7, 61A1 alley, Duy Tan Road, Hung Dung ward

  • Vinh

  • Viet Nam

  • Viet Nam

  • 84 38 3503 666

Details

Invitation for Bids

SOCIALISTREPUBLIC OF VIETNAM

RENEWABLEENERGY DEVELOPMENT PROJECT

Supply, Installation, Testing and Commissioning of Electro-Mechanical Equipment and Technical Services

Ban Ang Hydropower Plant

 

 

Date:  20th January 2015            

Credit No: Cr.4564-VN                     

IFB No: 03/TB-NMNN                      

 

1.         The Socialist Republic of Vietnam has received a credit from the International Development Association (IDA) in various currencies towards the cost of Renewable Energy Development Project.  It is intended that part of the proceeds of this loan will be applied to eligible payments under the contract for Supply, Installation, Testing and Commissioning of Electro-Mechanical Equipment and Technical Services, Ban Ang Hydropower Plant.

 

2.         The Nam Mo & Nam Non Hydropower Joint Stock Company now invites sealed bids from eligible bidders for the Supply, Installation, Testing and Commissioning of Electro-Mechanical Equipment and Technical Services and construction and completion of the Facilities of Ban Ang Hydropower Plant briefly described below:

-          Two hydro-generating units, Bulb type turbine, capacity of 2 x 8.5 MW

-          Auxiliary mechanical equipments

-          Electrical and control equipments

The Time for Operational Acceptance of twogenerating units shall be six hundred ninety (690) days.

3.         Bidding will be conducted using the International CompetitiveBidding (ICB) procedures specified in the World Bank's Guidelines: Procurement of Goods, works, and Non-Consulting services under IBRD and IDA Credit and Grant by World Bank Borrowers, January 2011, and is open to all Bidders from Eligible Source Countries as defined in the Guidelines.

4.         Interested eligible bidders may obtain further information from and inspect the bidding documents at the office of from 9:00am 15th January 2015 until 9.00am of 6th  March 2015:

Nam Mo & Nam Non Hydropower Joint Stock Company

No.7, 61A1 alley, Duy Tan Road, Hung Dung ward, Vinh city, Nghe An province, Vietnam

Mr.      Dao Duy Tan

Tel:      +84 38 3503 666

Fax:     +84 38 3564 068

Email:  thuyatd2@gmail.com

 

5.         A complete set of bidding documents may be purchased by interested bidders on the submission of a written application to the above and upon payment of a non-refundable fee of one million Vietnamese Dong (VND 1,000,000).

6.         Bids must be delivered to the above office on or before 9:00am 6th March, 2015 and must be accompanied by a security of one hundred fifty thousand Unites States Dollar (USD 150,000) or VND 3,000,000,000 or anequivalent amount of freely convertible currency

7.         Bids will be opened in the presence of bidders' representatives who choose to attend at 9:30am  6th March 2015 at the above-mentioned offices.