Rural Electrification and Transmission Project

Abstract*

The main development objectives of the Rural Electrification and Transmission Project are to improve power sector efficiency and reliability, while reducing electricity supply costs, improve standards of living and foster economic growth in rural areas, by expanding rural electricity supplies, and, strengthen electricity institutions, the regulatory framework, and the "enabling environment" for sector commercialization and privatization. The transmission...

* The project abstract is drawn from the PAD, SAR or PGD and may not accurately reflect the project's current nature

Show More

Development Objective

The main development objectives of the project are to: (a) improve power sector efficiency and realiability and reduce electricity supply costs; (b) improve standards of living and foster economic growth in rural areas by expanding rural electricity supplies; and (c) strengthen electricity institutions, the regulatory framework and the 'enabling environment' for sector commercialization and privatization.

Key Details

Project Details

  • P064844

  • Closed

  • Veasna Bun

  • N/A

  • Cambodia

  • June 28, 2000

  • (as of board presentation)

    December 16, 2003

  • March 29, 2005

  • US$ 40.00 million

  • B

  • Not Applicable

  • January 31, 2012

  • BANK APPROVED

  • January 15, 2013

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
IDA Credit 40.00
Borrower/Recipient 6.33
Foreign Private Commercial Sources (unidentified) 21.59

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment N/A
IDA Commitment 40.00
IBRD + IDA Commitment 40.00
Lending Instrument
Grant Amount N/A
Total Project Cost** 67.92

Summary Status of World Bank Financing (US$ Millions) as of April 30, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of April 30, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)
Jun 15, 2024 IDA-38400 Loan Repay 610,691.50
Jun 15, 2024 IDA-38400 Int Charges 9,165.62
Jun 15, 2024 IDA-38400 Int Charges 9,165.62
Jun 15, 2024 IDA-38400 Int Charges 90,928.78
Jun 15, 2024 IDA-38400 Int Charges 90,928.78
Dec 17, 2013 IDA-38400 Int Charges 1,509.83
Dec 17, 2013 IDA-38400 Int Charges 1,509.83
Dec 17, 2013 IDA-38400 Int Charges 132,953.12
Dec 17, 2013 IDA-38400 Int Charges 132,953.12
Dec 15, 2014 IDA-38400 Loan Repay 127,703.14
Dec 15, 2014 IDA-38400 Loan Repay 208,240.33
Dec 15, 2014 IDA-38400 Int Charges 125,728.67
Dec 15, 2014 IDA-38400 Int Charges 125,728.67
Dec 15, 2014 IDA-38400 Loan Repay 2,719.60
Jun 15, 2014 IDA-38400 Int Charges 132,675.84
Jun 15, 2014 IDA-38400 Loan Repay 356,768.94
Jun 15, 2014 IDA-38400 Int Charges 1,112.47
Jun 15, 2014 IDA-38400 Int Charges 861.96
Jun 15, 2014 IDA-38400 Int Charges 861.96
Jun 15, 2014 IDA-38400 Int Charges 1,112.47
Jun 15, 2014 IDA-38400 Int Charges 132,675.84
Jun 15, 2015 IDA-38400 Int Charges 109,530.76
Jun 15, 2015 IDA-38400 Int Charges 109,530.76
Jun 15, 2015 IDA-38400 Loan Repay 74,915.05
Jun 15, 2015 IDA-38400 Loan Repay 7,292.91
Jun 15, 2015 IDA-38400 Loan Repay 243,248.23
Dec 15, 2015 IDA-38400 Int Charges 117,493.68
Dec 15, 2015 IDA-38400 Int Charges 117,493.68
Dec 15, 2015 IDA-38400 Int Charges 9,998.58
Dec 15, 2015 IDA-38400 Int Charges 9,998.58
Dec 15, 2015 IDA-38400 Loan Repay 318,590.72
Dec 15, 2015 IDA-38400 Loan Repay 4,415.96
Jun 15, 2016 IDA-38400 Int Charges 117,119.80
Jun 15, 2016 IDA-38400 Int Charges 117,119.80
Jun 15, 2016 IDA-38400 Loan Repay 7,786.11
Jun 15, 2016 IDA-38400 Loan Repay 318,089.53
Jun 16, 2017 IDA-38400 Int Charges 105,804.01
Jun 16, 2017 IDA-38400 Int Charges 105,804.01
Jun 16, 2017 IDA-38400 Loan Repay 307,798.30
Dec 15, 2016 IDA-38400 Int Charges 101,789.64
Dec 15, 2016 IDA-38400 Int Charges 101,789.64
Dec 15, 2016 IDA-38400 Loan Repay 310,481.12
Dec 15, 2016 IDA-38400 Int Charges 8,819.25
Dec 15, 2016 IDA-38400 Int Charges 8,819.25
Dec 15, 2016 IDA-38400 Int Charges 186.18
Dec 15, 2016 IDA-38400 Int Charges 186.18
Jun 15, 2017 IDA-38400 Loan Repay 12,219.01
Dec 15, 2017 IDA-38400 Int Charges 7,166.16
Dec 15, 2017 IDA-38400 Int Charges 7,166.16
Dec 15, 2017 IDA-38400 Loan Repay 112,858.08
Dec 15, 2017 IDA-38400 Loan Repay 214,836.72
Dec 15, 2017 IDA-38400 Int Charges 6.56
Dec 15, 2017 IDA-38400 Int Charges 6.56
Dec 15, 2017 IDA-38400 Int Charges 114,283.57
Dec 15, 2017 IDA-38400 Int Charges 114,283.57
Jun 15, 2018 IDA-38400 Loan Repay 225.51
Jun 15, 2018 IDA-38400 Loan Repay 326,771.75
Jun 15, 2018 IDA-38400 Int Charges 112,814.04
Jun 15, 2018 IDA-38400 Int Charges 112,814.04
Jun 15, 2019 IDA-38400 Loan Repay 314,711.30
Jun 15, 2019 IDA-38400 Int Charges 108,193.53
Jun 15, 2019 IDA-38400 Int Charges 108,193.53
Jun 15, 2019 IDA-38400 Loan Repay 5,862.10
Dec 15, 2018 IDA-38400 Loan Repay 13,518.02
Dec 15, 2018 IDA-38400 Loan Repay 306,049.66
Dec 15, 2018 IDA-38400 Int Charges 109,052.46
Dec 15, 2018 IDA-38400 Int Charges 109,052.46
Jun 15, 2020 IDA-38400 Int Charges 101,520.19
Jun 15, 2020 IDA-38400 Int Charges 101,520.19
Dec 15, 2019 IDA-38400 Loan Repay 318,524.06
Dec 15, 2019 IDA-38400 Int Charges 102,920.79
Dec 15, 2019 IDA-38400 Int Charges 102,920.79
Dec 15, 2019 IDA-38400 Loan Repay 2,225.48
Dec 15, 2020 IDA-38400 Int Charges 4,133.19
Dec 15, 2020 IDA-38400 Int Charges 4,133.19
Dec 15, 2020 IDA-38400 Loan Repay 333,238.03
Dec 15, 2020 IDA-38400 Int Charges 100,510.46
Dec 15, 2020 IDA-38400 Int Charges 100,510.46
Jun 15, 2020 IDA-38400 Int Charges 4,115.21
Jun 15, 2020 IDA-38400 Int Charges 4,115.21
Jun 15, 2020 IDA-38400 Loan Repay 319,651.10
Jun 15, 2022 IDA-38400 Loan Repay 303,913.28
Jun 15, 2022 IDA-38400 Int Charges 97,220.49
Jun 15, 2021 IDA-38400 Int Charges 104,258.43
Jun 15, 2021 IDA-38400 Int Charges 104,258.43
Jun 15, 2021 IDA-38400 Loan Repay 333,513.80
Jun 15, 2021 IDA-38400 Int Charges 8,215.21
Jun 15, 2021 IDA-38400 Int Charges 8,215.21
Dec 15, 2021 IDA-38400 Int Charges 3,202.04
Dec 15, 2021 IDA-38400 Int Charges 3,202.04
Dec 15, 2021 IDA-38400 Loan Repay 323,634.72
Dec 15, 2021 IDA-38400 Int Charges 103,158.58
Dec 15, 2021 IDA-38400 Int Charges 103,158.58
Jun 15, 2022 IDA-38400 Int Charges 97,220.49
Jun 15, 2022 IDA-38400 Loan Repay 4,723.21
Jun 15, 2023 IDA-38400 Int Charges 95,105.95
Jun 15, 2023 IDA-38400 Int Charges 95,105.95
Jun 15, 2023 IDA-38400 Loan Repay 309,287.66
Dec 15, 2022 IDA-38400 Loan Repay 297,864.53
Dec 15, 2022 IDA-38400 Int Charges 79,487.09
Dec 15, 2022 IDA-38400 Int Charges 79,487.09
Dec 15, 2022 IDA-38400 Loan Repay 10,537.87
Dec 15, 2023 IDA-38400 Loan Repay 6,295.41
Dec 15, 2023 IDA-38400 Int Charges 85,052.97
Dec 15, 2023 IDA-38400 Int Charges 85,052.97
Dec 15, 2023 IDA-38400 Loan Repay 304,419.78
Jun 15, 2023 IDA-38400 Int Charges 16,550.52
Jun 15, 2023 IDA-38400 Int Charges 16,550.52
Dec 16, 2003 IDA-38400 Loan Commitment 40,000,000.00

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Overall Safeguards Rating Moderately Satisfactory 2012-02-10
Procurement Moderately Satisfactory 2012-02-10
Project Management Moderately Satisfactory 2012-02-10
Overall Safeguards Rating Moderately Satisfactory 2012-02-10
Progress towards achievement of PDO Moderately Satisfactory 2012-02-10
Financial Management Moderately Satisfactory 2012-02-10
Monitoring and Evaluation Moderately Satisfactory 2012-02-10
Overall Implementation Progress (IP) Moderately Satisfactory 2012-02-10
Counterpart Funding Satisfactory 2012-02-10

COMPLETION RATINGS

INDICATORIMPLEMENTATION COMPLETION & RESULTS REPORT: 09-11-2012
OutcomesModerately Satisfactory
Risk to Development OutcomeSubstantial
Bank PerformanceModerately Satisfactory
Borrower PerformanceModerately Satisfactory
Government PerformanceModerately Satisfactory
Implementing AgencyModerately Satisfactory

INDEPENDENT EVALUATION RATINGS

INDICATORICR REVIEW: 01-27-2014PROJECT PERFORMANCE ASSESSMENT REPORT:
Outcome RatingModerately Satisfactory N/a
Risk To Development OutcomeSignificantN/a
Bank PerformanceModerately SatisfactoryN/a
Borrower PerformanceModerately SatisfactoryN/a
Government PerformanceModerately SatisfactoryN/a
Implementing AgencyModerately SatisfactoryN/a
Icr QualitySatisfactoryN/a
M&e QualitySubstantialN/a

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • Reduction in EDC cost of electricity supplyValueUS$0.155/kWhUS$0.147/kWhUS$0.11/kWh
    DateNovember 30, 2003December 31, 2011January 31, 2012
    CommentEDC’s cost of power supply has not been reduced to the target of US$ 0,11 kWh. However it was slightly reduced from 0.155 US$/kWhat appraisal to US$ 0.147/kWh. This was mainly because the cost of fuel for EDC’s power generation has increased, due to the surgeinoil prices.
  • Reduction in EDC distribution lossesValue14%9.8%14%
    DateNovember 30, 2003December 31, 2011January 31, 2012
    CommentTarget: to maintain EDC's T&D losses at 14%. Target exceeded.
  • Issuance of licenses to all IPPs and REEsValue54.00297.00180.00
    DateNovember 30, 2003December 31, 2011January 31, 2012
    CommentOriginal target exceededSource: Report on Power Sector of the Kingdom of Cambodia. 2010 Edition.Data by end Oct., 2011
  • Industrial consumers switch from self-generation to grid supplyValue0 MW42 MW30 MW
    DateNovember 30, 2003December 31, 2011January 31, 2012
    CommentOriginal target exceededSource: EDC
  • Average off-grid tariff reducedValueUS$0.50/kWhUS$0.51/kWhUS$0.425/kWh
    DateNovember 30, 2003December 31, 2011January 31, 2012
    CommentIt has not been reduced to the target of US$ 0,11 kWh due to the surge in oil prices.
  • Average number of hours of electricity services provided by REEs increasedValue4 hours12 hours8 hours
    DateNovember 30, 2003December 31, 2011January 31, 2012
    Comment159 REEs (53%) provide 24 hours service. Source: Report on Power Sector of the Kingdom of Cambodia. 2010 Edition
  • Number of people (including through rural business and social services) benefit from modern electricity servicesValue0.00503779.00567000.00
    DateNovember 30, 2003December 31, 2011January 31, 2012
    CommentMore people will benefit from modern electricity services as rural household connection continues. Target is likely to be achieved.

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • Number of rural and renewable energy business employees, commercial bank staff, and regulators trained on renewable energy technologies, and participating in the development, financing and regulationValue0.00238.00200.00
    DateNovember 30, 2003December 31, 2011January 31, 2012
    CommentActivity completed. Target exceeded
  • Increase in % of national generation capacity by renewable energyValue0.000.305.00
    DateNovember 30, 2003December 31, 2011January 31, 2012
    CommentThough RETP did not directly finance the renewable energy projects, except installation of SHS of 12,000 systems. The projectfunded the update of the power Master Plan, which has indirectly contributed to development of an existing hydropower of 193 MWinstalledcapacity. This hydropower plant was connected to the national grid in Dec. 2011. It provides about 0.3% generationcapacity in 2011and about 14.8% from 2012 . Source: EDC
  • Additional rural household connectionValue0.0045097.0050000.00
    DateNovember 30, 2003December 31, 2011January 31, 2012
    CommentTarget is almost achieved. Household connections continue.
  • REF sub-grant for off-grid connection by REEsValue0.0050000.0045000.00
    DateNovember 30, 2003December 31, 2011January 31, 2012
    CommentTarget Achieved
  • Solar Home System installationValue0.009857.0012000.00
    DateNovember 30, 2003December 31, 2011January 31, 2012
    CommentData by January 10, 2012 (including 93 systems installed before project restructuring) Installation on-going with goodperspectives of reaching the target by the closing date
  • Increase in number of renewable energy businesses (serving 500 to 1,500 customers)Value0.004.005.00
    DateNovember 30, 2003December 31, 2011January 31, 2012
    CommentTarget is almost achieved. Four companies directly involved in SHS business:(i) Sunlabob – SHS supply and deliverycontractor;(ii) BND Co.Ltd – installation contractor (iii) Kamworks - installation contractor (iv) IED – supervision, SHSmaintenance and collection of re-payment contractor
  • 220kV line and substations operationalValueNon-operationalOperationalOperational
    DateNovember 30, 2003December 31, 2011January 31, 2012
    Comment220 kV line and 3 substations operational since 2009
  • Increase in local commercial lending and other financing for rural electrification and renewable energyValue0.5 US$ Million80 US$ Million15 US$ Million
    DateNovember 30, 2003December 31, 2011January 31, 2012
    CommentThe project was not explicitly designed to support the indicator; however, it financed the Rural Energy Strategy & ImplementationPlan (RESIP) and the Distribution system planning under the Rural electrification Module, which provided a platform for commerciallending for rural electrification. As result, Chinese Ex-Im bank provided US$ 80 million to EDC for rural electrification
  • 115kV network reinforced and constructedValue0 km37 km23 km
    DateNovember 30, 2003December 31, 2011January 31, 2012
    Comment115kV network reinforced and constructed in 2009
  • MV line extensions from WPP and Takeo S/S installedValue0 km168.8 km130 km
    DateNovember 30, 2003December 31, 2011January 31, 2012
    CommentTarget exceeded
  • Feasibility study of mini and village hydropowerValueNo studyStudy completedCompletion of the FS (with 6,850kW is feasible)
    DateNovember 30, 2003December 31, 2011January 31, 2012
    CommentStudy concluded in Nov 2011. It found no mini and village hydropower feasible
  • Sector master plan developed by MIMEValueNo master planMaster plan is being used by EDCMaster plan prepared
    DateNovember 30, 2003December 31, 2011January 31, 2012
    CommentTarget achieved. Sector master plan was prepared in 2006