Vietnam Power Sector Reform Development Policy Operation

Abstract*

The objective of the First Power Sector Reform Development Policy Operation Program is to support the Government of Vietnam's implementation of a market for electricity generation, restructuring of the power sector and reform of tariffs that will facilitate effective competition, transparency and predictability, encourage timely generation investment, improve system operational reserve, and provide incentives for efficient use of electricity. Vietnam...

* The project abstract is drawn from the PAD, SAR or PGD and may not accurately reflect the project's current nature

Show More

Development Objective

To support the Government of Vietnam's implementation of a market for electricity generation, restructuring of the power sector and reform of tariffs that will facilitate effective competition, transparency and predictability, encourage timely generation investment, improve system operational reserve and provide incentives for efficient use of electricity.

Key Details

Project Details

  • P115874

  • Closed

  • Richard Jeremy Spencer

  • Ministry of Industry and Trade

  • Viet Nam

  • August 18, 2009

  • (as of board presentation)

    April 6, 2010

  • September 23, 2010

  • US$ 311.80 million

  • Electricity Regulatory Authority of Vietnam

  • East Asia and Pacific

  • 2010

  • US$ 311.80 million

  • N/A

  • Not Applicable

  • August 31, 2011

  • BANK APPROVED

  • January 15, 2013

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
International Bank for Reconstruction and Development 200.00
IDA Credit 111.80

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment 200.00
IDA Commitment 111.80
IBRD + IDA Commitment 311.80
Lending Instrument
Grant Amount N/A
Total Project Cost** 311.80

Summary Status of World Bank Financing (US$ Millions) as of July 31, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of July 31, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)
Feb 15, 2023 IBRD-78680 Int Charges 3,799,278.20
Feb 15, 2023 IBRD-78680 Loan Repay 6,900,000.00
Aug 15, 2023 IDA-47110 Int Charges 319,139.44
Aug 15, 2023 IDA-47110 Int Charges 319,139.44
Aug 15, 2023 IDA-47110 Int Charges 1,497,827.90
Aug 15, 2023 IDA-47110 Int Charges 21,126.19
Aug 15, 2023 IDA-47110 Loan Repay 2,431,538.80
Aug 15, 2022 IDA-47110 Int Charges 334,347.47
Aug 15, 2022 IDA-47110 Int Charges 334,347.47
Aug 15, 2022 IDA-47110 Int Charges 1,569,204.20
Aug 15, 2022 IDA-47110 Int Charges 13,397.85
Feb 15, 2022 IBRD-78680 Int Charges 656,665.30
Feb 15, 2022 IBRD-78680 Loan Repay 6,900,000.00
Feb 15, 2022 IDA-47110 Int Charges 364,305.94
Feb 15, 2022 IDA-47110 Int Charges 364,305.94
Feb 15, 2022 IDA-47110 Loan Repay 2,493,497.20
Feb 15, 2022 IDA-47110 Loan Repay 63,035.74
Feb 15, 2022 IDA-47110 Int Charges 1,695,595.10
Aug 15, 2022 IDA-47110 Loan Repay 2,409,711.80
Aug 15, 2022 IBRD-78680 Int Charges 1,057,479.60
Aug 15, 2022 IBRD-78680 Loan Repay 6,900,000.00
Aug 15, 2021 IBRD-78680 Loan Repay 6,900,000.00
Aug 15, 2021 IDA-47110 Int Charges 6,839.88
Aug 15, 2021 IDA-47110 Loan Repay 2,592,138.80
Aug 15, 2021 IDA-47110 Int Charges 1,779,244.00
Aug 15, 2021 IDA-47110 Int Charges 379,100.25
Aug 15, 2021 IDA-47110 Int Charges 379,100.25
Aug 15, 2021 IBRD-78680 Int Charges 708,730.60
Feb 15, 2021 IDA-47110 Int Charges 389,475.28
Feb 15, 2021 IDA-47110 Int Charges 1,820,999.00
Feb 15, 2021 IBRD-78680 Int Charges 858,666.70
Feb 15, 2021 IBRD-78680 Loan Repay 6,900,000.00
Feb 15, 2021 IDA-47110 Int Charges 76,598.81
Feb 15, 2021 IDA-47110 Loan Repay 1,314,684.40
Feb 15, 2021 IDA-47110 Int Charges 389,475.28
Aug 15, 2020 IDA-47110 Loan Repay 25,840.76
Aug 15, 2020 IDA-47110 Loan Repay 1,260,492.20
Aug 15, 2019 IDA-47110 Int Charges 376,239.25
Aug 15, 2019 IBRD-78680 Int Charges 3,258,000.00
Aug 15, 2019 IDA-47110 Int Charges 1,765,816.20
Feb 15, 2019 IBRD-78680 Int Charges 3,056,444.50
Feb 15, 2019 IDA-47110 Int Charges 44,465.37
Feb 15, 2019 IDA-47110 Int Charges 44,465.37
Feb 15, 2019 IDA-47110 Int Charges 335,108.16
Feb 15, 2019 IDA-47110 Int Charges 335,108.16
Feb 15, 2019 IDA-47110 Int Charges 1,769,651.20
Aug 15, 2018 IBRD-78680 Int Charges 2,534,000.00
Aug 15, 2018 IDA-47110 Int Charges 67,009.20
Aug 15, 2018 IDA-47110 Int Charges 378,700.28
Aug 15, 2018 IDA-47110 Int Charges 378,700.28
Aug 15, 2018 IDA-47110 Int Charges 1,777,366.60
Feb 15, 2018 IDA-47110 Int Charges 40,945.51
Feb 15, 2018 IDA-47110 Int Charges 399,289.00
Feb 15, 2018 IDA-47110 Int Charges 399,289.00
Feb 15, 2018 IDA-47110 Int Charges 1,803,344.10
Feb 15, 2018 IBRD-78680 Int Charges 1,952,444.50
Aug 15, 2017 IBRD-78680 Int Charges 1,789,888.90
Aug 15, 2017 IDA-47110 Int Charges 1,768,668.80
Aug 15, 2017 IDA-47110 Int Charges 16,460.03
Aug 15, 2017 IDA-47110 Int Charges 385,264.80
Aug 15, 2017 IDA-47110 Int Charges 385,264.80
Feb 15, 2017 IDA-47110 Int Charges 16,724.40
Feb 15, 2017 IDA-47110 Int Charges 16,724.40
Feb 15, 2017 IBRD-78680 Int Charges 1,645,777.80
Aug 15, 2016 IDA-47110 Int Charges 18,550.77
Aug 15, 2016 IDA-47110 Int Charges 382,037.28
Aug 15, 2016 IDA-47110 Int Charges 382,037.28
Aug 15, 2016 IDA-47110 Int Charges 1,793,028.20
Feb 15, 2017 IDA-47110 Int Charges 352,813.47
Feb 15, 2017 IDA-47110 Int Charges 352,813.47
Feb 15, 2017 IDA-47110 Int Charges 1,718,576.20
Feb 15, 2016 IBRD-78680 Int Charges 889,333.30
Feb 15, 2016 IDA-47110 Int Charges 1,184.49
Feb 15, 2016 IDA-47110 Int Charges 1,184.49
Feb 15, 2016 IDA-47110 Int Charges 383,658.75
Feb 15, 2016 IDA-47110 Int Charges 383,658.75
Aug 15, 2015 IBRD-78680 Int Charges 713,944.44
Feb 15, 2015 IDA-47110 Int Charges 16,383.96
Feb 15, 2015 IDA-47110 Int Charges 16,383.96
Feb 15, 2015 IDA-47110 Int Charges 371,109.16
Feb 15, 2015 IDA-47110 Int Charges 371,109.16
Feb 15, 2015 IDA-47110 Int Charges 1,818,634.40
Aug 15, 2013 IDA-47110 Int Charges 16,364.76
Aug 15, 2013 IDA-47110 Int Charges 399,228.80
Aug 15, 2013 IDA-47110 Int Charges 399,228.80
Aug 15, 2013 IDA-47110 Int Charges 1,950,519.10
Aug 15, 2013 IBRD-78680 Int Charges 724,000.00
Aug 15, 2013 IDA-47110 Int Charges 16,364.76
Feb 15, 2014 IDA-47110 Int Charges 412,928.00
Feb 15, 2014 IDA-47110 Int Charges 1,974,147.10
Feb 15, 2014 IDA-47110 Int Charges 9,772.12
Feb 15, 2014 IDA-47110 Int Charges 9,772.12
Feb 15, 2014 IDA-47110 Int Charges 412,928.00
Feb 15, 2014 IBRD-78680 Int Charges 684,888.90
Aug 15, 2020 IDA-47110 Int Charges 385,899.90
Aug 15, 2020 IDA-47110 Int Charges 385,899.90
Aug 15, 2020 IBRD-78680 Int Charges 2,214,333.20
Aug 15, 2020 IDA-47110 Int Charges 1,736,209.90
Feb 15, 2020 IDA-47110 Int Charges 14,009.62
Feb 15, 2020 IDA-47110 Int Charges 14,009.62
Feb 15, 2020 IDA-47110 Int Charges 1,756,976.90
Feb 15, 2020 IBRD-78680 Int Charges 2,576,000.00
Feb 15, 2020 IDA-47110 Int Charges 360,346.25
Feb 15, 2020 IDA-47110 Int Charges 360,346.25
Aug 15, 2019 IDA-47110 Int Charges 11,710.02
Aug 15, 2019 IDA-47110 Int Charges 376,239.25
Feb 15, 2016 IDA-47110 Int Charges 1,787,510.50
Aug 15, 2016 IBRD-78680 Int Charges 1,243,666.60
Aug 15, 2015 IDA-47110 Int Charges 312,724.62
Aug 15, 2015 IDA-47110 Int Charges 312,724.62
Aug 15, 2015 IDA-47110 Int Charges 1,803,396.60
Aug 15, 2014 IBRD-78680 Int Charges 603,333.30
Aug 15, 2014 IDA-47110 Int Charges 9,630.51
Aug 15, 2014 IDA-47110 Int Charges 418,577.44
Aug 15, 2014 IDA-47110 Int Charges 418,577.44
Aug 15, 2014 IDA-47110 Int Charges 1,964,523.40
Feb 15, 2015 IBRD-78680 Int Charges 644,000.00
Aug 15, 2015 IDA-47110 Int Charges 71,521.84
Aug 15, 2015 IDA-47110 Int Charges 71,521.84
Apr 6, 2010 IBRD-78680 Loan Commitment 200,000,000.00
Apr 6, 2010 IDA-47110 Loan Commitment 111,800,000.00
Feb 15, 2024 IDA-47110 Loan Repay 2,406,840.00
Feb 15, 2024 IDA-47110 Int Charges 307,803.70
Feb 15, 2024 IDA-47110 Int Charges 307,803.70
Feb 15, 2024 IDA-47110 Int Charges 1,444,625.20
Feb 15, 2024 IBRD-78680 Int Charges 5,028,136.00
Feb 15, 2024 IBRD-78680 Loan Repay 6,900,000.00
Feb 15, 2024 IDA-47110 Loan Repay 7,306.46
Aug 15, 2024 IDA-47110 Int Charges 302,307.62
Aug 15, 2024 IBRD-78680 Int Charges 4,825,911.00
Aug 15, 2024 IBRD-78680 Int Charges 29,147.29
Aug 15, 2024 IDA-47110 Loan Repay 56,601.33
Aug 15, 2024 IBRD-78680 Loan Repay 6,900,000.00
Aug 15, 2024 IDA-47110 Loan Repay 2,386,289.00
Aug 15, 2024 IDA-47110 Int Charges 302,307.62
Aug 15, 2024 IDA-47110 Int Charges 1,353,659.40
Feb 15, 2024 IBRD-78680 Int Charges 48,125.85
Aug 15, 2023 IBRD-78680 Int Charges 4,516,747.00
Aug 15, 2023 IBRD-78680 Loan Repay 6,900,000.00
Aug 15, 2023 IBRD-78680 Int Charges 180,773.95
Feb 15, 2023 IDA-47110 Loan Repay 37,453.88
Feb 15, 2023 IDA-47110 Loan Repay 2,403,264.50
Feb 15, 2023 IDA-47110 Int Charges 329,497.00
Feb 15, 2023 IDA-47110 Int Charges 329,497.00
Feb 15, 2023 IDA-47110 Int Charges 1,525,233.20
Feb 15, 2023 IBRD-78680 Int Charges 289,547.00

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Monitoring and Evaluation Satisfactory 2010-04-27
Program Management Satisfactory 2010-04-27
Progress towards achievement of PDO Satisfactory 2010-04-27

COMPLETION RATINGS

INDICATORIMPLEMENTATION COMPLETION & RESULTS REPORT: 07-25-2016
OutcomesModerately Satisfactory
Risk to Development OutcomeHigh
Bank PerformanceModerately Satisfactory
Borrower PerformanceModerately Satisfactory
Government PerformanceModerately Satisfactory
Implementing AgencySubstantial

INDEPENDENT EVALUATION RATINGS

INDICATORICR REVIEW: 10-24-2016PROJECT PERFORMANCE ASSESSMENT REPORT:
Outcome RatingModerately Satisfactory N/a
Risk To Development OutcomeHighN/a
Bank PerformanceModerately SatisfactoryN/a
Borrower PerformanceModerately SatisfactoryN/a
Government PerformanceModerately SatisfactoryN/a
Implementing AgencySatisfactoryN/a
Icr QualitySubstantialN/a
M&e QualitySubstantialN/a

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • Increase in generation availability due to market efficiency incentives improves reserve adequacy and supply security. Indicator: hourly operational reserve.ValueNo hourly operational reserve.Not assessed.End of third operation in programmatic series:Ten
    DateDecember 31, 2008April 17, 2010December 31, 2012
    Comment
  • Enhanced transparency in generation contracting and pricing, creating predictability for investors.Indicators: Single Buyer contracts coverage of generation and disclosure of spot market prices.ValueNo contract coverage.No spot market disclosure.Not assessed.End of third operation in programmatic series:Con
    DateDecember 31, 2008April 17, 2010December 31, 2012
    Comment
  • The independence and diversity of electricity generators increases, creating conditions that enable development of effective competition and allow the transition to wholesale competition.Indicator:ValueHighest proportion of generation owned by a singleNot assessed.End of third operation in programmatic series:Hig
    DateDecember 31, 2008April 17, 2010December 31, 2012
    Comment
  • The System and Market Operator provides efficient and non discriminatory services following VCGM rules, codes and regulations.Indicator: audit by independent consultant firm determines compliance ofValueNo audit (because there is no SMO).Not assessed.End of third operation in programmatic series:Aud
    DateDecember 31, 2008April 17, 2010December 31, 2012
    Comment
  • Annual tariff updates approved by MOIT up to 5 percent.Indicator: annual tariff adjustment is approved by March each year.ValueNo annual update.Annual update approved in March 2010.End of third operation in programmatic series:Ann
    DateDecember 31, 2008April 17, 2010December 31, 2012
    Comment
  • Phase out of cross subsidy between different tariff categories.Indicators: level of cross subsidy from industrial and commercial categories reduced at least 50 percent; and subsidies targeted to pooValueCross subsidy of $370 million from industrial and Subsidized block reduced to 50 kWh per month, but End of third operation in programmatic series:Cro
    DateDecember 31, 2007April 17, 2010December 31, 2012
    Comment
  • Enhanced energy efficiency through legal framework, and adequate monitoring and enforcement mechanisms.Inidcator: energy efficiency target established by law, and MoIT and ERAV have capacity to enfoValueNo Energy Efficiency Law, and no formal demand sidNot assessed.End of third operation in programmatic series:Ene
    DateDecember 31, 2008April 17, 2010December 31, 2012
    Comment

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • Milestones for Policy Area A, Development of Competitive Market:ERAV completes draft Vietnam Competitive Generation Market (VCGM)Rules and submits to MoIT consultation and approval.MoIT issues CiValueNo VCGM Rules draft submitted or Grid Code circulaDraft market rules have been sent for consultationVCGM Rules draft submitted and Grid Code circular
    DateApril 6, 2010April 17, 2010June 30, 2011
    Comment
  • Milestones for Policy Area B, Power Sector Restructuring:EVN submits recommendations on independent generation companies to PrimeMinister.MoIT issues Circular on methodology and procedures to calValueNo recommendation on independent generation companVietnam Electricity has submitted its recommendatiRecommendation on independent generation companies
    DateApril 6, 2010April 17, 2010June 30, 2011
    Comment
  • Milestones for Policy Area C, Electricity Tariff Reform:Prime Minister Decision to promulgates Regulations on methodology to calculate and procedures for appraisal of market-based electricity pricesValueNo regulations on methodology for market based priA tariff regulation on methodology for calculationRegulation on methodology for market based pricing
    DateApril 6, 2010April 17, 2010June 30, 2011
    Comment
  • Milestones for Policy Area D, Improving Demand Side Energy Efficiency:MoIT submits draft Energy Efficiency Law to Prime Minister.ERAV completes load research and drafts procedures for PCs' periodiValueDraft Energy Efficiency Law not submitted.Load reNot assessedDraft Energy Efficiency Law submitted by MoIT to P
    DateApril 6, 2010April 17, 2010June 30, 2011
    Comment